Home / Browse projects / Pune, Maharashtra / GANGA AMBER PH II
GANGA AMBER PH II
By SHRI SIDDHIVINAYAK DEVELOPERS
RG-MH-16454 · RERA P52100026055 · Last updated on MahaRERA portal: 27 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 23 complaints at MahaRERA
- Completion date moved by 24 months
- 2 extensions taken
- Rs 20.25 crore secured on the land, in favour of PRACHAY CAPITAL LIMITED
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
GANGA AMBER PH II is a Residential / Group Housing project by SHRI SIDDHIVINAYAK DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100026055 on 12 Aug 2020. Possession is promised by 30 Jun 2027. The completion date has moved by 24 months from the original filing. 90 of the 206 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete. 23 complaints are on record with the regulator.
At a glance
Project
- NameGANGA AMBER PH II
- TypeResidential / Group Housing
- Location
- AMBER STREET
- TATHAWDE
- Tathwade
- Mulshi
- Pune
- 411033
- Pincode411033
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100026055
- ReraGenie IDRG-MH-16454
Builder
- NameSHRI SIDDHIVINAYAK DEVELOPERS
- Entity typePartnership
- GSTIN27ACEFS7660L1ZJ
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnerAnkit Umesh Goel
- Other registrations3 more →
- Completed2 of 4
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on12 Aug 2020
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2025)
- Buildings2 building records
- Documents filed148 files
Current status
Figures as on 27 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| D | NA | 14 | 10 | 103 | 0 | 103 |
| E | NA | 14 | 10 | 103 | 0 | 103 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 27 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 75%.
D39%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 20% |
| Sanitary Fittings within the flats / premises | 14% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 25% |
E47%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 41% |
| Sanitary Fittings within the flats / premises | 29% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 75% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 38% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 30% |
Progress on shared amenities15
As on 27 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 90% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| D | NA | Rs 19.86 cr | Rs 8.61 cr |
| E | NA | Rs 19.86 cr | Rs 8.61 cr |
| - | NA | Rs 15.43 cr | Rs 4.63 cr |
Certifying professionals and partners9
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | A AND T CONSULTANTS |
| Architect | A & T CONSULTANTS |
| Engineer | Rajendra Uttamrao Gawade |
| Engineer | Shrikant Morajkar |
| Engineer | G A BHILARE |
| Chartered Accountant | SHAH KHANDELWAL JAIN AND ASSOCIATES |
| Chartered Accountant | Pooja Dagdiya & associates |
| Chartered Accountant | DMKH & CO. |
| Chartered Accountant | DMKH & CO |
| Partner | Role in project |
|---|---|
| SHRI SIDDHIVINAYAK DEVELOPERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterNon-availability of labor and other resources.
Reason as filed by the promoterThe project timeline has been impact as promoter was required to replace construction contractor engaged for Building D & E resulting in disruption of the construction schedule and project was subjected to stop Work notice from Deputy Labour Commisioner which significantly impact the construction activities.
Complaints filed with MahaRERA23
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12500706 | Devendra Yashwant Palav | Anuj Goel | 28/02/2025 |
| CC12500705 | BHAGAWAN VISHWANATH SHRIRAME | SHRI SIDDHIVINAYAK DEVELOPERS | 28/02/2025 |
| CC12500655 | Shrushti Prashant Deshmukh | SHRI SIDDHIVINAYAK DEVELOPERS | 24/02/2025 |
| CC12500717 | Sunil Wamanrao Kadam | SHRI SIDDHIVINAYAK DEVELOPERS | 01/03/2025 |
| CC12500701 | Lalit Ravindra Amrutkar | SHRI SIDDHIVINAYAK DEVELOPERS | 28/02/2025 |
| CC12500704 | Abhishek CHANDRAKANT Yadav | SHRI SIDDHIVINAYAK DEVELOPERS | 28/02/2025 |
| CC12501031 | Mayur Lalchand Jiwatramani | SHRI SIDDHIVINAYAK DEVELOPERS | 27/03/2025 |
| CC12501127 | sangeeta Sameer Bhole | SHRI SIDDHIVINAYAK DEVELOPERS | 04/04/2025 |
| CC12502199 | SONAL SAGAR LAKADE | SHRI SIDDHIVINAYAK DEVELOPERS | 02/07/2025 |
| CC12503474 | Neha Ganesh Bhole | SHRI SIDDHIVINAYAK DEVELOPERS | 29/09/2025 |
| CC12503475 | mayur umesh phadke | SHRI SIDDHIVINAYAK DEVELOPERS | 29/09/2025 |
| CC12503500 | Vaibhav ganesh Bhole | SHRI SIDDHIVINAYAK DEVELOPERS | 30/09/2025 |
| CC12604459 | SHRI SIDDHIVINAYAK DEVELOPERS | Mr Abhishek Chandrakant Yadav | 17/07/2026 |
| CC12604460 | SHRI SIDDHIVINAYAK DEVELOPERS | Shrusti Prashant Deshmukh | 17/07/2026 |
| CC12604461 | SHRI SIDDHIVINAYAK DEVELOPERS | Neha Ganesh Bhole | 17/07/2026 |
| CC12604462 | SHRI SIDDHIVINAYAK DEVELOPERS | Lalit Ravindra Amrutkar | 17/07/2026 |
| CC12604472 | SHRI SIDDHIVINAYAK DEVELOPERS | Sunil Wamanrao Kadam | 18/07/2026 |
| CC12604475 | SHRI SIDDHIVINAYAK DEVELOPERS | Vaibhav Ganesh Bhole | 18/07/2026 |
| CC12604481 | SHRI SIDDHIVINAYAK DEVELOPERS | Mayur Umesh Phadke | 18/07/2026 |
| CC12604483 | SHRI SIDDHIVINAYAK DEVELOPERS | Bhagwan Vishwanath Shrirame | 18/07/2026 |
| CC12604486 | SHRI SIDDHIVINAYAK DEVELOPERS | Devendra yashwant Palav | 18/07/2026 |
| CC12604489 | SHRI SIDDHIVINAYAK DEVELOPERS | Sonal Sagar Lakade | 18/07/2026 |
| CC12604493 | SHRI SIDDHIVINAYAK DEVELOPERS | Sangeeta Sameer Bhole | 18/07/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 May 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed148
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 148 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A.pdf | 27 Aug 2026 |
| Form 5 (FY 2025-2026)File: Form_5_SSD_Phase_II_FY25-26_Signed.pdf | 26 Aug 2026 |
| Form 2A (FY 2024-2025)File: Form 2A.pdf | 23 Jul 2026 |
| Form 5 (FY 2024-2025)File: Form-5.pdf | 23 Jul 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 13 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 (1).pdf | 13 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 13 Jul 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 13 Jun 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 13 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 13 Jun 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 12 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 12 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 12 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 12 May 2026 |
| Withdrawal Update Form 3File: FORM 3 Q3.pdf | 12 May 2026 |
| Withdrawal Update Form 3File: FORM 3 Q3.pdf | 12 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 7 Apr 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 7 Apr 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 7 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 7 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 7 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 7 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 7 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 7 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3 Q3.pdf | 7 Apr 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 6 Apr 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 6 Apr 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 6 Apr 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 6 Apr 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 6 Apr 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 6 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 6 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 6 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 6 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 6 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 6 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 6 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 6 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 6 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 6 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 6 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 6 Apr 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 6 Apr 2026 |
| Form 1File: Form 1.pdf | 3 Apr 2026 |
| Form 2File: Form 2.pdf | 3 Apr 2026 |
| Form 3File: Form 3.pdf | 3 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Form D.pdf | 3 Apr 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 30 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 30 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold unsold.pdf | 30 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold unsold.pdf | 30 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Amber.pdf | 28 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Amber.pdf | 28 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Amber phase II.pdf | 28 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Amber.pdf | 30 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Amber.pdf | 30 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Amber phase II.pdf | 30 Oct 2024 |
| Other - FinanceFile: Self declaration amber phase II.pdf | 30 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Amber.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Amber.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Form D amber.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Amber.pdf | 20 Jul 2024 |
| Layout approvalFile: 1-Amber Layout 2022.pdf | 21 May 2024 |
| Layout approvalFile: parking layout.pdf | 21 May 2024 |
| Layout approvalFile: Parking Bldg.pdf | 21 May 2024 |
| Copy of Layout Approval (in case of layout)File: 1-Amber Layout 2022.pdf | 21 May 2024 |
| Copy of Layout Approval (in case of layout)File: parking layout.pdf | 21 May 2024 |
| Copy of Layout Approval (in case of layout)File: Parking Bldg.pdf | 21 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 23 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 AMBER.pdf | 21 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 AMBER.pdf | 21 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A AMBER II.pdf | 21 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: FORM D AMBER II.pdf | 21 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 21 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 17 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 17 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Form D.pdf | 17 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 17 Jan 2024 |
| Declaration in FORM BFile: Form B_rotated_11zon.pdf | 3 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 30 Dec 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 148 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep GANGA AMBER PH II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near TATHAWDE13,700+ in Pune
Filed coordinates, straight-line distance. 253 registered projects within 2 km.
Construction of 24 LIG, 768 MIG and commercial
Pune Housing & Area Development Board
Kohinoor Avantara
Intofinity Promoters Private Limited
AISHWARYAM INSIGNIA
VIKSAK VINODE INFRATECH LLP
KOHINOOR UPTOWN AVENUE
MOONSTONE REALINFRA PRIVATE LIMITED
LUSH RESIDENCES
LUSH RESIDENCES LLP
RENUKA PANCHATATTVA
Renuka Realty Private Limited
Builder: SHRI SIDDHIVINAYAK DEVELOPERS
SHRI SIDDHIVINAYAK DEVELOPERS has 4 registrations on MahaRERA, including GANGA AMBER PH I and BRJ RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if GANGA AMBER PH II is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of GANGA AMBER PH II?
The registered promoter entity is SHRI SIDDHIVINAYAK DEVELOPERS, a partnership as per the filing. Its GSTIN 27ACEFS7660L1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in GANGA AMBER PH II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against GANGA AMBER PH II?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for GANGA AMBER PH II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at GANGA AMBER PH II?
The professionals named in the filing: Architect: A AND T CONSULTANTS; Architect: A & T CONSULTANTS; Engineer: Rajendra Uttamrao Gawade; Engineer: Shrikant Morajkar; Engineer: G A BHILARE; Chartered Accountant: SHAH KHANDELWAL JAIN AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in GANGA AMBER PH II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback