Home / Browse projects / Dadra & Nagar Haveli / GANESH SOCIETY PHASE 1

Registration lapsed No litigation declared Mixed project

GANESH SOCIETY PHASE 1

By ASHISHBHAI BHARATBHAI THAKKAR

RG-MH-00433 · RERA P49600000012 · Last updated on MahaRERA portal: 19 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 53 months past the filed date
  • Completion date moved by 37 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Dadra & Nagar Haveli registration emailed to you, free during the pilot beta.
May 2022Possession promised53 months past this date
1 of 11Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 85%
62 of 64Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

GANESH SOCIETY PHASE 1 is a Mixed project by ASHISHBHAI BHARATBHAI THAKKAR in Dadra & Nagar Haveli, registered with MahaRERA as P49600000012 on 7 Nov 2017. Possession was promised by 20 May 2022 and is now 53 months past that date. The completion date has moved by 37 months from the original filing. 2 of the 64 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete.

At a glance

Project

  • NameGANESH SOCIETY PHASE 1
  • TypeMixed
  • Location
    • SILVASSA
    • Others
    • Dadra & Nagar Haveli
    • 396230
  • Pincode396230
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P49600000012
  • ReraGenie IDRG-MH-00433

Builder

  • NameASHISHBHAI BHARATBHAI THAKKAR
  • Entity typeIndividual

Key dates

53 months past promisethis monthRegisteredNov 2017First promiseApr 2019Revised toMay 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Nov 2017
  • Promised completion20 May 2022
  • Revised completionRevised to 20 May 2022 (originally 30 Apr 2019)
  • Buildings1 building record
  • Documents filed93 files

Current status

3%2 of 64 units booked

Figures as on 19 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GANESH SOCIETY PHASE 2NA128441963

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 19 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 85%.

GANESH SOCIETY PHASE 249%
ActivityProgress
Excavation100%
Basement (if any)60%
Podiums (if any)0%
Plinth60%
Stilt Floor75%
Slabs of Super Structure85%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
NA Plot Without StructureNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 19 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes11%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed13

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots13
Closed/Covered1
Open Space12

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,950 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Aug 2025

Approvals and building plan

Sanctioning authorityDADRA AND NAGAR HAVELI PLANNING & DEVELOPMENT AUTHORITY
Permissible FSI8051.56
Proposed, not sanctioned4,152 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSILVASSA

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPARUL KANSARA
EngineerJANAK BHAVSAR
Chartered AccountantKUNAL B SHAH
Chartered AccountantRAJESHBHAI A KATARIYA
PartnerRole in project
ASHISHBHAI BHARATBHAI THAKKAR-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT49600008539Apr 2019 → Nov 2021

Reason as filed by the promoter8 Month Delay in our project for covid-19, please extend my Maharera Registration for 12 month

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Oct 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Oct 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Oct 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Oct 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 DEC 2017.pdf19 May 2026
Form 2File: FORM 2 DEC 2017.pdf19 May 2026
Form 3File: 31-12-2017.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 31-12-2017.pdf19 May 2026
Form 1File: FORM 1 MAR 2018.pdf19 May 2026
Form 2File: FORM 2 MAR 2018.pdf19 May 2026
Form 3File: 31-03-2018.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 31-03-2018.pdf19 May 2026
Form 1File: FORM 1 JUN 2018.pdf19 May 2026
Form 2File: FORM 2 JUN 2018.pdf19 May 2026
Form 3File: 30-06-2018.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 30-06-2018.pdf19 May 2026
Form 1File: FORM 1 SEP 2018.pdf19 May 2026
Form 2File: FORM 2 SEP 2018.pdf19 May 2026
Form 3File: 30-09-2018.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 30-09-2018.pdf19 May 2026
Form 1File: FORM 1 DEC 2018.pdf19 May 2026
Form 2File: FORM 2 DEC 2018.pdf19 May 2026
Form 3File: 31-12-2018.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 31-12-2018.pdf19 May 2026
Form 1File: FORM 1 MAR 2019.pdf19 May 2026
Form 2File: FORM 2 MAR 2019.pdf19 May 2026
Form 3File: 31-03-2019.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 31-03-2019.pdf19 May 2026
Form 1File: FORM 1 JUN 2019.pdf19 May 2026
Form 2File: FORM 2 JUN 2019.pdf19 May 2026
Form 3File: 30-06-2019.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 30-06-2019.pdf19 May 2026
Form 1File: FORM 1 SEP 2019.pdf19 May 2026
Form 2File: FORM 2 SEP 2019.pdf19 May 2026
Form 3File: 30-09-2019.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 30-09-2019.pdf19 May 2026
Form 1File: FORM 1 DEC 2019.pdf19 May 2026
Form 2File: FORM 2 DEC 2019.pdf19 May 2026
Form 3File: 31-12-2019.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 31-12-2019.pdf19 May 2026
Form 1File: FORM 1 MAR 2020.pdf19 May 2026
Form 2File: FORM 2 MAR 2020.pdf19 May 2026
Form 3File: 31-03-2020.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 31-03-2020.pdf19 May 2026
Form 1File: FORM 1 JUN 2020.pdf19 May 2026
Form 2File: FORM 2 JUN 2020.pdf19 May 2026
Form 3File: 30-06-2020.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 30-06-2020.pdf19 May 2026
Form 1File: FORM 1 SEP 2020.pdf19 May 2026
Form 2File: FORM 2 SEP 2020.pdf19 May 2026
Form 3File: 30-09-2020.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 30-09-2020.pdf19 May 2026
Form 1File: FORM 1 DEC 2020.pdf19 May 2026
Form 2File: FORM 2 DEC 2020.pdf19 May 2026
Form 3File: 31-12-2020.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 31-12-2020.pdf19 May 2026
Form 1File: FORM 1 MAR 2021.pdf19 May 2026
Form 2File: FORM 2 MAR 2021.pdf19 May 2026
Form 3File: 31-03-2021.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 31-03-2021.pdf19 May 2026
Form 1File: FORM 1 JUN 2021.pdf19 May 2026
Form 2File: FORM 2 JUN 2021.pdf19 May 2026
Form 3File: 30-06-2021.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 30-06-2021.pdf19 May 2026
Form 1File: FORM 1 SEP 2021.pdf19 May 2026
Form 2File: FORM 2 SEP 2021.pdf19 May 2026
Form 3File: 30-09-2021.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 30-09-2021.pdf19 May 2026
Form 1File: FORM 1 DEC 2021.pdf19 May 2026
Form 2File: FORM 2 DEC 2021.pdf19 May 2026
Form 3File: 31-12-2021.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 31-12-2021.pdf19 May 2026
Form 1File: FORM 1 MAR 2022.pdf19 May 2026
Form 2File: FORM 2 MAR 2022.pdf19 May 2026
Form 3File: 31-03-2022.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 31-03-2022.pdf19 May 2026
Form 1File: FORM 1 JUN 2022.pdf19 May 2026
Form 2File: FORM 2 JUN 2022.pdf19 May 2026
Form 3File: 30-06-2022.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: SBD 20-05-2022.pdf19 May 2026
Certificates of CA (Form 5) (UT)File: bhagwati form 5.pdf15 Oct 2018
Layout approvalFile: download (9).pdf30 Oct 2017
Building plan approval or NA orderFile: download (10).pdf30 Oct 2017
PAN CardFile: download (2).pdf30 Oct 2017

How this compares with Dadra & Nagar Haveli

3%of this project is bookeddistrict median 30%
10%of Dadra & Nagar Haveli projects moved their completion datethis one moved by 37 months
28%of Dadra & Nagar Haveli registrations have lapsed or been cancelledthis one is among them

Computed across the 210+ Dadra & Nagar Haveli projects on ReraGenie, from their own filings.

Keep GANESH SOCIETY PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Others210+ in Dadra & Nagar Haveli

Builder: ASHISHBHAI BHARATBHAI THAKKAR

ASHISHBHAI BHARATBHAI THAKKAR has 1 registration on MahaRERA, including GANESH SOCIETY PHASE 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Dadra & Nagar Haveli district page.

Frequently asked questions

What does it mean that GANESH SOCIETY PHASE 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GANESH SOCIETY PHASE 1 is delayed beyond 20 May 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GANESH SOCIETY PHASE 1?

The registered promoter entity is ASHISHBHAI BHARATBHAI THAKKAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GANESH SOCIETY PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GANESH SOCIETY PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GANESH SOCIETY PHASE 1?

The professionals named in the filing: Architect: PARUL KANSARA; Engineer: JANAK BHAVSAR; Chartered Accountant: KUNAL B SHAH; Chartered Accountant: RAJESHBHAI A KATARIYA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GANESH SOCIETY PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GANESH SOCIETY PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GANESH SOCIETY PHASE 1 to a free account