Home / Browse projects / Mumbai Suburban, Maharashtra / Ganesh Dham

Registered No litigation declared Residential / Group Housing project

Ganesh Dham

By MEHTA & SHIRODKAR DEVELOPERS

RG-MH-07100 · RERA P51800053763 · Last updated on MahaRERA portal: 20 Aug 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2029Possession promisedno revision filed
0 of 44Construction stages doneacross 4 buildings; furthest along: Excavation, 80%
161 of 190Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 101 documents Report an error

Ganesh Dham is a Residential / Group Housing project by MEHTA & SHIRODKAR DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800053763 on 28 Nov 2023. Possession is promised by 31 Dec 2029. 29 of the 190 units on this registration are recorded sold or booked, and 0 of 44 construction stages are filed complete.

At a glance

Project

  • NameGanesh Dham
  • TypeResidential / Group Housing
  • Location
    • Gawanpada
    • Mulund East
    • Mulund
    • Kurla
    • Mumbai Suburban
    • 400081
  • Pincode400081
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800053763
  • ReraGenie IDRG-MH-07100

Builder

  • NameMEHTA & SHIRODKAR DEVELOPERS
  • Entity typePartnership
  • PartnerManohar Kashinath Shirodkar
  • PartnerROHAN SHIRODKAR

Key dates

this monthRegisteredNov 2023PromisedDec 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Nov 2023
  • Promised completion31 Dec 2029
  • Revised completionNone
  • Buildings4 building records
  • Documents filed101 files

Current status

15%29 of 190 units booked
13.4%Work done, per cost certificate

Figures as on 20 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA191950050
Wing BNA191940040
Wing CNA181848048
Wing DNA181852052

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 20 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 80%.

Wing A33%
ActivityProgress
Excavation80%
Basement (if any)80%
Podiums (if any)25%
Plinth80%
Stilt Floor45%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises9%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks8%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B33%
ActivityProgress
Excavation80%
Basement (if any)80%
Podiums (if any)25%
Plinth80%
Stilt Floor45%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises9%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks8%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C33%
ActivityProgress
Excavation80%
Basement (if any)80%
Podiums (if any)25%
Plinth80%
Stilt Floor45%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises9%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks8%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing D34%
ActivityProgress
Excavation80%
Basement (if any)80%
Podiums (if any)25%
Plinth80%
Stilt Floor45%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises9%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks8%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.7%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed249

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots249
Open Space249
BuildingOpen SpaceTotal
Wing A6262
Wing B6262
Wing C6363
Wing D6262

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area5,513 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on19 Jun 2025
LandownerVillageDistrict
Ganesh Dham Co-operative Housing Society LimitedMulundMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI20187.45
Proposed, not sanctioned8,232 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchB 37 Wagle Ind Estate Thane 400604
Estimated costRs 188.64 cr
Cost incurredRs 25.35 cr
Work done13.44%
BuildingWingEstimatedIncurred
Wing ANARs 43.91 crRs 6.89 cr
Wing BNARs 43.91 crRs 6.13 cr
Wing CNARs 43.91 crRs 6.13 cr
Wing DNARs 43.91 crRs 6.13 cr
-NARs 13.00 crRs 6.16 lakh

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYMS Consultants Limited
EngineerRC Tipnis
Chartered AccountantJagadish and Harish
Chartered AccountantShripati Gandhi Choudhari & Co.
PartnerRole in project
MEHTA & SHIRODKAR DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Nov 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2029

Documents filed101

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 101 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2023-2024)File: FORM 2A - March 24.pdf20 Aug 2026
Form 2A (FY 2025-2026)File: FORM 2A 25-26.pdf20 Aug 2026
Withdrawal Update Form 1File: Form 1 - Sept 25.pdf18 Jul 2026
Withdrawal Update Form 2File: Form 2 June 26.pdf18 Jul 2026
Withdrawal Update Form 3File: Form 3 - June 26 - Ganesh Dham.pdf18 Jul 2026
Withdrawal Update Form 1File: Form 1 - Sept 25.pdf26 Jun 2026
Withdrawal Update Form 2File: FORM 2 WITH SIGN.pdf26 Jun 2026
Withdrawal Update Form 3File: Signed FORM 3.pdf26 Jun 2026
Withdrawal Update Form 1File: Form 1 - Sept 25.pdf24 Jun 2026
Withdrawal Update Form 2File: Form 2 Dec 25.pdf24 Jun 2026
Withdrawal Update Form 3File: Form 3 - Dec 25.pdf24 Jun 2026
Withdrawal Update Form 1File: Form 1 - Sept 25.pdf2 Jan 2026
Withdrawal Update Form 2File: Form 2 - Sept 25.pdf2 Jan 2026
Withdrawal Update Form 3File: Form 3 - Sept 25.pdf2 Jan 2026
Withdrawal Update Form 1File: Form 1 - June 25.pdf19 Dec 2025
Withdrawal Update Form 1File: Form 1 - June 25.pdf19 Dec 2025
Withdrawal Update Form 2File: Form 2 - June 25.pdf19 Dec 2025
Withdrawal Update Form 2File: Form 2 - June 25.pdf19 Dec 2025
Withdrawal Update Form 3File: Form 3 - June 25.pdf19 Dec 2025
Withdrawal Update Form 3File: Form 3 - June 25.pdf19 Dec 2025
Form 1File: Form 1 - June 24.pdf19 Nov 2025
Form 2File: Form 2 - June 24.pdf19 Nov 2025
Form 3File: FORM 3 WITH SIGN_compressed.pdf19 Nov 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold_Booked Inventory - June 24.pdf19 Nov 2025
Form 1File: Form 1 - Sept 24.pdf30 Oct 2025
Form 2File: Form 2 - Sept 24.pdf30 Oct 2025
Form 3File: Form 3 - Sept 24.pdf30 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - Sept 24.pdf30 Oct 2025
Form 1File: Form 1 - Dec 24.pdf30 Oct 2025
Form 2File: Form 2 - Dec 24.pdf30 Oct 2025
Form 3File: Form 3 - Dec 24.pdf30 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - Dec 24.pdf30 Oct 2025
Form 1File: Form 1 - March 25.pdf30 Oct 2025
Form 2File: Form 2 - March 25.pdf30 Oct 2025
Form 3File: Form 3 - March 25.pdf30 Oct 2025
Disclosure of Sold and Booked InventoryFile: Disclosure - March 25.pdf30 Oct 2025
Form 1File: FORM 1.pdf8 Jul 2025
Form 2File: FORM 2 ENGINEER CERTIFICATE.pdf8 Jul 2025
Form 3File: FORM 3 - March 24 - Shirodkar.pdf8 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure.pdf8 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 WITH SIGN_compressed.pdf9 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold_Booked Inventory - June 24.pdf7 Apr 2025
Layout approvalFile: Approved Amended Plan Part1.pdf4 Jul 2024
Layout approvalFile: Approved Amended Plan Part2.pdf4 Jul 2024
Building plan approvalFile: Approved Amended Plan Part1.pdf4 Jul 2024
Building plan approvalFile: Approved Amended Plan Part2.pdf4 Jul 2024
Copy of Layout Approval (in case of layout)File: Approved Amended Plan Part1.pdf4 Jul 2024
Copy of Layout Approval (in case of layout)File: Approved Amended Plan Part2.pdf4 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Amended Plan Part1.pdf4 Jul 2024
Building Plan Approval / NA Order for plotted developmentFile: Approved Amended Plan Part2.pdf4 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: Shirodkar - CC.pdf3 Jul 2024
Declaration about Commencement CertificateFile: Declaration CC Letter.pdf3 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A - March 24.pdf29 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Dec 23.pdf28 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Dec 23.pdf28 Jun 2024
Disclosure of sold/ booked inventoryFile: Disclosure.pdf13 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf8 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 ENGINEER CERTIFICATE.pdf8 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - March 24 - Shirodkar.pdf8 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MSD FORM-3 Promoters Acceptance.pdf12 Apr 2024
Other - LegalFile: RECEIPT-ROF-1623.pdf23 Nov 2023
Other - LegalFile: MSD Partnership deed.pdf18 Nov 2023
Declaration about Commencement CertificateFile: Declaration CC RERA171123.pdf17 Nov 2023
Other - FinanceFile: A wing Declaration RERA.pdf17 Nov 2023
Other - TechnicalFile: A wing Declaration RERA.pdf17 Nov 2023
Layout approvalFile: PAGE 1-2.pdf9 Nov 2023
Layout approvalFile: PAGE 3-4.pdf9 Nov 2023
Layout approvalFile: PAGE 5-7.pdf9 Nov 2023
Layout approvalFile: PAGE 8-9.pdf9 Nov 2023
Building plan approvalFile: PAGE 1-2.pdf9 Nov 2023
Building plan approvalFile: PAGE 3-4.pdf9 Nov 2023
Building plan approvalFile: PAGE 5-7.pdf9 Nov 2023
Building plan approvalFile: PAGE 8-9.pdf9 Nov 2023
PAN CardFile: PAN Card msd.pdf9 Nov 2023
Copy of the legal title reportFile: LEGAL TITLE REPORT.pdf9 Nov 2023
Details of encumbrances concerned to FinanceFile: DECLARATION OF No Encumbrances concerned to finance.pdf9 Nov 2023
Details of encumbrances concerned to FinanceFile: Rera Encumbrances Concerned To Legal.pdf9 Nov 2023
Details of encumbrances concerned to LegalFile: DECLARATION OF No Encumbrances concerned to finance.pdf9 Nov 2023
Details of encumbrances concerned to LegalFile: Rera Encumbrances Concerned To Legal.pdf9 Nov 2023
Copy of Layout Approval (in case of layout)File: PAGE 1-2.pdf9 Nov 2023

How this compares with Mumbai Suburban

15%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Ganesh Dham on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund East6,700+ in Mumbai Suburban

2 kmGanesh DhamCompleted 90Lapsed / revoked 79Other 111Dot size: filed unitsN

Filed coordinates, straight-line distance. 280 registered projects within 2 km.

Builder: MEHTA & SHIRODKAR DEVELOPERS

MEHTA & SHIRODKAR DEVELOPERS has 1 registration on MahaRERA, including Ganesh Dham. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Ganesh Dham is delayed beyond 31 Dec 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Ganesh Dham?

The registered promoter entity is MEHTA & SHIRODKAR DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Ganesh Dham?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Ganesh Dham?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Ganesh Dham?

The professionals named in the filing: Architect: YMS Consultants Limited; Engineer: RC Tipnis; Chartered Accountant: Jagadish and Harish; Chartered Accountant: Shripati Gandhi Choudhari & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Ganesh Dham?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Ganesh Dham. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Ganesh Dham to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.