Home / Browse projects / Pune, Maharashtra / GANDHARV SERENITY

Completed No litigation declared Others project

GANDHARV SERENITY

By Gandharv Developers

RG-MH-21063 · RERA P52100005405 · Last updated on MahaRERA portal: 30 Sep 2020

Source: official MahaRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2019Possession promisedregistration recorded completed
1 of 11Construction stages donefurthest along: Basement (if any), 80%
0Complaints at MahaRERAon this registration
Jump to the 53 documents Report an error

GANDHARV SERENITY is a Others project by Gandharv Developers in Pune, Maharashtra, registered with MahaRERA as P52100005405 on 11 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2019. The completion date has moved by 6 months from the original filing.

At a glance

Project

  • NameGANDHARV SERENITY
  • TypeOthers
  • Location
    • PUNE - SOLAPUR ROAD
    • HADAPSAR
    • Haveli
    • Pune
    • 411028
  • Pincode411028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100005405
  • ReraGenie IDRG-MH-21063

Builder

  • NameGandharv Developers
  • Entity typePartnership
  • PartnersSANJAY RAMCHANDRA RASKAR, RAJ SANJAY RASKAR
  • Other registrations1 more →
  • Completed1 of 2
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseJun 2019Revised toDec 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on11 Aug 2017
  • Promised completion31 Dec 2019
  • Revised completionRevised to 31 Dec 2019 (originally 30 Jun 2019)
  • Buildings1 building record
  • Documents filed53 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
GANDHARVA SERENITYNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Sep 2020, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 80%.

GANDHARVA SERENITY: 35% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor50%
Slabs of Super Structure45%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks15%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities16

As on 30 Sep 2020, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable
Society OfficeYes100%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership13

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,394 sq m
Land owned byThe promoter, with other names on the file
Named landowners13
LandownerVillageDistrict
VIKAS VINAYAK RAYKARHadapsarPune
ARCHANA VIKAS RAYKARHadapsarPune
VISWAS VINAYAK RAYKARHadapsarPune
SAVITA VISWAS RAYKARHadapsarPune
UTTAM VAMANRAO RAYKARHadapsarPune
MANGESH UTTAM RAYKARHadapsarPune
SUMEDHA MANGESH RAYKARHadapsarPune
RAVINDRA VAMANRAO RAYKARHadapsarPune
DINESH RAVINDRA RAYKARHadapsarPune
VIJAYA VINAYAK RAYKARHadapsarPune
MEGHA UTTAM RAYKARHadapsarPune
MANGAL UTTAM RAYKARHadapsarPune
USHA RAVINDRA RAYKARHadapsarPune

Approvals and building plan

Permissible FSI3848.43
Proposed, not sanctioned3,848 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchARYAN CENTER ,OPP VAIBHAV THEATER PUNE - SOLAPUR ROAD ,HADAPSAR PUNE -411028

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectM.B.Chaudhari & Associates
PartnerRole in project
Gandharv Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100001962Jun 2019 → Dec 2019

Reason as filed by the promoterSir we would like to put it on record that project had been physically completed by and also obtained Completion Certificate (Part No. I) No. OCC/1440/18 dated 13/2/2019 bearing No. 5113 and Completion Certificate (Part No. II) No. OCC/0108/19 dated 16/5/2019 bearing No. 5131 by PMC Pune keeping 7 Flats as uncompleted due to new NOC of MOD/AMSL required vide Office Circular dated 28/5/2019 No. Sha.A.J./J/2737 which has been started recently in PMC area and Developer have applied through Architect. Now that process for issuing such NOC is streamed lined in PMC and said NOC is expected in 2 to 3

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Dec 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 4 Dec 2019

Documents filed53

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: form 5.pdf30 Sep 2020
Architect’s Certificate on Completion of Project (Form 4)File: From 4 GD.pdf23 Jan 2020
Certificates of CA (Form 3)File: CA Certificate 30 06 2019 -GD.pdf28 Dec 2019
Certificates of CA (Form 3)File: CA Certificate 30 09 2019 GD.pdf28 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA from 5 GD.pdf24 Dec 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: society formation cert.PDF5 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GD Architect Certificate.PDF4 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GD Engineer Certificate.PDF4 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: gd final completion.pdf4 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Arch Complition.pdf4 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: GD part 1 complition.pdf4 Dec 2019
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion G Serenity.pdf4 Dec 2019
Certificates of CA (Form 5)File: Form 5-min.pdf30 Sep 2019
OtherFile: GD part 1 complition.pdf26 Jun 2019
OtherFile: Part Completion G Serenity.pdf26 Jun 2019
OtherFile: Arch Complition.pdf26 Jun 2019
Certificates of CA (Form 3)File: CA GD 31 12 18.PDF25 Jun 2019
Certificates of CA (Form 3)File: CA GD 31 03 19.PDF25 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect GD march 19.PDF28 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: GD MAR 19.PDF28 May 2019
Status of ConveyanceFile: GD part 1 complition.pdf28 May 2019
OtherFile: GD part 1 complition.pdf28 May 2019
Building plan approvalFile: Revise plan part 1-4.pdf31 Dec 2018
Building plan approvalFile: Revise plan 5-8.pdf31 Dec 2018
Building Plan Approval (IOD)File: Revise plan part 1-4.pdf31 Dec 2018
Building Plan Approval (IOD)File: Revise plan 5-8.pdf31 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: Revise CC.pdf31 Dec 2018
Certificates of CA (Form 3)File: CA 30-09-18.pdf31 Dec 2018
Building plan approvalFile: G D plan.pdf29 Dec 2018
Building Plan Approval (IOD)File: G D plan.pdf29 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: GD com.pdf29 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert 30 6 18.pdf29 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Archi Cert 30 9 18.pdf29 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Cert 30 9 18.pdf29 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engi Cert 30 6 18.pdf29 Dec 2018
Certificates of CA (Form 3)File: GD 30-6-18CA.pdf29 Dec 2018
Certificates of CA (Form 5)File: Form 5 GD.pdf30 Sep 2018
Certificates of CA (Form 3)File: GD CA Certificate.pdf11 May 2018
Layout approvalFile: LAYOUT.pdf30 Jul 2017
Building plan approvalFile: Lower ground plan.pdf30 Jul 2017
Building plan approvalFile: Floor Plan.pdf30 Jul 2017
PAN CardFile: pan card.pdf30 Jul 2017
Copy of the legal title reportFile: GD Search and Title.pdf30 Jul 2017
Details of encumbrancesFile: GD Encumbrance.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT.pdf30 Jul 2017
Building Plan Approval (IOD)File: Lower ground plan.pdf30 Jul 2017
Building Plan Approval (IOD)File: Floor Plan.pdf30 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: cc.pdf30 Jul 2017
Declaration in FORM BFile: GD B FORM.pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT Certificate.pdf30 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gandharv Developers Engineer Certificate.pdf30 Jul 2017
Certificates of CA (Form 3)File: Gandharv Developers CA Certificate.pdf30 Jul 2017
Proforma of Allotment letterFile: Agr - RERA - Gandharva Developers - Serenity - 03-07-17.pdf30 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 6 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GANDHARV SERENITY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near HADAPSAR13,700+ in Pune

2 kmGANDHARV SERENITYCompleted 11Lapsed / revoked 5Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 20 registered projects within 2 km.

Builder: Gandharv Developers

Gandharv Developers has 2 registrations on MahaRERA, including GANDHARV SERENITY and Gandharv Leela. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GANDHARV SERENITY is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GANDHARV SERENITY?

The registered promoter entity is Gandharv Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GANDHARV SERENITY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GANDHARV SERENITY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GANDHARV SERENITY?

The professionals named in the filing: Architect: M.B.Chaudhari & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GANDHARV SERENITY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GANDHARV SERENITY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GANDHARV SERENITY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.