ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / GALAXY

Completed No litigation declared Residential / Group Housing project

GALAXY

By ASWANI PARADISE

RG-MH-93640 · RERA P52100017540 · Last updated on MahaRERA portal: 26 Feb 2025

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • 1 extension taken

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
24 of 55Construction stages doneacross 5 buildings; furthest along: Installation of Lifts, 95%
3Complaints at MahaRERAon this registration
Jump to the 134 documents Report an error

GALAXY is a Residential / Group Housing project by ASWANI PARADISE in Pune, Maharashtra, registered with MahaRERA as P52100017540 on 24 Aug 2018. The registration is recorded completed; possession was promised by 30 Dec 2023. 3 complaints are on record with the regulator.

At a glance

Project

  • NameGALAXY
  • TypeResidential / Group Housing
  • Location
    • PINK CITY ROAD
    • WAKAD
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100017540
  • ReraGenie IDRG-MH-93640

Builder

  • NameASWANI PARADISE
  • Entity typePartnership
  • PartnersSANDIP RASIKLAL SHAH, JAYESH SUNIL CHUGWANI, SHREECHAND SHAMANDAS ASWANI
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2018PromisedDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Aug 2018
  • Promised completion30 Dec 2023
  • Revised completionNone
  • Buildings5 building records
  • Documents filed134 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ABNA120000
CNA120000
DNA100000
ENA120000
FNA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 26 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Installation of Lifts, at 95%.

AB81%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
C80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
D76%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises88%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks88%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
E80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
F79%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 26 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes90%
Street LightingYes100%
Community BuildingsYes80%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed43

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots43
Closed/Covered43

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,987 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI10202.19
Proposed, not sanctioned5,317 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWAKAD, PUNE, MAHARASHTRA

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANKUR ASSOCIATES
EngineerM/s. G. A. Bhilare Consultants Pvt. Ltd
EngineerMayur Belose
Chartered AccountantA N J K & CO LLP
PartnerRole in project
ASWANI PARADISE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018904Dec 2023 → Dec 2024

Reason as filed by the promoterWe apply for extension of the registered project with the regulatory authority vide project registration certificate bearing no. P52100017540 which expired on 30/12/2023. We request you to grant extension of RERA Registration for a further period of 12 months i.e. upto 29/12/2024.

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC005000000064310Santosh M KalateAswani Paradise24/06/2020
CC12501306omprakash ramniwas jangirASWANI PARADISE20/04/2025
CC12504664Aswani CHS LtdASWANI PARADISE29/12/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Jan 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 12 Feb 2025

Documents filed134

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 134 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RERA Form 5 Aswani Galaxy.pdf26 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Verification Email to Corporation.pdf12 Feb 2025
Other - TechnicalFile: Aswani Paradise PCMC_RERA Email.pdf12 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4.PDF11 Feb 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Aswani Paradise PCMC Completion Certificate 30March2024.pdf14 Dec 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration Format A on Seperate bank account.pdf22 Feb 2024
Declaration about Commencement CertificateFile: DECLRATION ABOUT COMMENCEMENT CERTIFICATE.PDF3 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 2018-19.PDF3 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2020-21.PDF3 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2021-22.PDF3 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2022-23.PDF3 Feb 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory December 2023.pdf31 Jan 2024
Layout approvalFile: Layout Approval.pdf30 Jan 2024
Building plan approvalFile: Building Plan AB.pdf30 Jan 2024
Building plan approvalFile: Building Plan C.pdf30 Jan 2024
Building plan approvalFile: Building Plan D-1.pdf30 Jan 2024
Building plan approvalFile: Building Plan D-2.pdf30 Jan 2024
Building plan approvalFile: Building Plan E-1.pdf30 Jan 2024
Building plan approvalFile: Building Plan E-2.pdf30 Jan 2024
Building plan approvalFile: Building Plan F-1.pdf30 Jan 2024
Building plan approvalFile: Building Plan F-2.pdf30 Jan 2024
Copy of Layout Approval (in case of layout)File: Layout Approval.pdf30 Jan 2024
Building Plan Approval (IOD)File: Building Plan AB.pdf30 Jan 2024
Building Plan Approval (IOD)File: Building Plan C.pdf30 Jan 2024
Building Plan Approval (IOD)File: Building Plan D-1.pdf30 Jan 2024
Building Plan Approval (IOD)File: Building Plan D-2.pdf30 Jan 2024
Building Plan Approval (IOD)File: Building Plan E-1.pdf30 Jan 2024
Building Plan Approval (IOD)File: Building Plan E-2.pdf30 Jan 2024
Building Plan Approval (IOD)File: Building Plan F-1.pdf30 Jan 2024
Building Plan Approval (IOD)File: Building Plan F-2.pdf30 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf30 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory December 2021.pdf30 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory March 2022.pdf30 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory June 2022.pdf30 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory September 2022.pdf30 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory December 2022.pdf30 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory March 2023.pdf30 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory June 2023.pdf30 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory October 2023.pdf30 Jan 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration format A on Seperate bank account.pdf25 Jan 2024
Certificates of CA (Form 3)File: 1.pdf24 Jan 2024
Certificates of CA (Form 3)File: 2.pdf24 Jan 2024
Certificates of CA (Form 3)File: 4.pdf24 Jan 2024
Certificates of CA (Form 3)File: 5.pdf24 Jan 2024
Certificates of CA (Form 3)File: 3.pdf24 Jan 2024
Certificates of CA (Form 3)File: 6.pdf24 Jan 2024
Certificates of CA (Form 3)File: 7.pdf24 Jan 2024
Certificates of CA (Form 3)File: 8.pdf24 Jan 2024
Certificates of CA (Form 3)File: 9.pdf24 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1.PDF23 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2.PDF23 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 3.PDF23 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 4.PDF23 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5.PDF23 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 6.PDF23 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 7.PDF23 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 8.PDF23 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 9.PDF23 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1.pdf23 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2.PDF23 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3.PDF23 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4.PDF23 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5.PDF23 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6.PDF23 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7.PDF23 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 8.PDF23 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 9.PDF23 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A - MARCH 2020.PDF20 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A - MARCH 2021.PDF20 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A- MARCH 2022.PDF20 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A- MARCH 2023.PDF20 Jan 2024
Declaration about Commencement CertificateFile: Declaration Commencement Certificates.pdf13 Nov 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form5_Project Galaxy.pdf2 Jul 2021
Layout approvalFile: LAYOUT 1.pdf23 Sep 2019
Building plan approvalFile: COMM AB.pdf23 Sep 2019
Building plan approvalFile: AB1.pdf23 Sep 2019
Building plan approvalFile: C WING.pdf23 Sep 2019
Building plan approvalFile: C 1.pdf23 Sep 2019
Building plan approvalFile: D WING.pdf23 Sep 2019
Building plan approvalFile: D 1.pdf23 Sep 2019

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
GREEN VALLEYSURVEY NO 257179CompletedJul 2017Late, Dec 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GALAXY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WAKAD13,700+ in Pune

2 kmGALAXYCompleted 132Lapsed / revoked 49Other 78Dot size: filed unitsN

Filed coordinates, straight-line distance. 259 registered projects within 2 km.

Builder: ASWANI PARADISE

ASWANI PARADISE has 1 registration on MahaRERA, including GALAXY. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if GALAXY is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GALAXY?

The registered promoter entity is ASWANI PARADISE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GALAXY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GALAXY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GALAXY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GALAXY?

The professionals named in the filing: Architect: ANKUR ASSOCIATES; Engineer: M/s. G. A. Bhilare Consultants Pvt. Ltd; Engineer: Mayur Belose; Chartered Accountant: A N J K & CO LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GALAXY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GALAXY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GALAXY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.