Home / Browse projects / Solapur, Maharashtra / GALAXY GOLD

Registration lapsed No litigation declared Plotted project

GALAXY GOLD

By GALAXY DEVELOPERS

RG-MH-16528 · RERA P52600027931 · Last updated on MahaRERA portal: 25 Jan 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 55 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.
Mar 2022Possession promised55 months past this date
19 of 19Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 15 documents Report an error

GALAXY GOLD is a Plotted project by GALAXY DEVELOPERS in Solapur, Maharashtra, registered with MahaRERA as P52600027931 on 21 Jan 2021. Possession was promised by 30 Mar 2022 and is now 55 months past that date. 0 of the 19 units on this registration are recorded sold or booked.

At a glance

Project

  • NameGALAXY GOLD
  • TypePlotted
  • Location
    • PRATAP NAGAR
    • DONGAON ROAD
    • Solapur (M Corp.)
    • Solapur North
    • Solapur
    • 413008
  • Pincode413008
  • RERA no.P52600027931
  • ReraGenie IDRG-MH-16528

Builder

  • NameGALAXY DEVELOPERS
  • Entity typePartnership
  • PartnerVRUSHALI AMIT MITKARI
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live3 lapsed, de-registered or revoked

Key dates

55 months past promisethis monthRegisteredJan 2021PromisedMar 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on21 Jan 2021
  • Promised completion30 Mar 2022
  • Revised completionNone
  • BuildingsNot stated in filing
  • Documents filed15 files

Current status

0%0 of 19 units booked

Figures as on 25 Jan 2025, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 25 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 25 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes50%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes50%
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,750 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2704.55

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAILWAY LINES SOLAPUR

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSHRIDHAR PAGUL
EngineerSHRIDHAR PAGUL
Chartered AccountantSHAILESH SHARMA & CO
PartnerRole in project
GALAXY DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Aug 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Dec 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Sep 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed15

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: rera certificate with dsc.pdf25 Jan 2025
Other - LegalFile: 12_20230719_0001 (1)_compressed.pdf19 Jul 2023
Building plan approval or NA orderFile: FINAL APPROVAL-converted.pdf25 Dec 2020
Building Plan Approval / NA Order for plotted developmentFile: FINAL APPROVAL-converted.pdf25 Dec 2020
Details of encumbrancesFile: ENCUMBERENCE.pdf25 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: cp2ov-7ngdw.pdf25 Sep 2020
Declaration in FORM BFile: img_71821.pdf25 Sep 2020
Proforma of Allotment letterFile: AGREEMENT TO SALE- Galaxy Developers- Gaurav Nashte.pdf25 Sep 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_compressed.pdf19 Sep 2020
Building plan approval or NA orderFile: APPROVAL 1.pdf27 Aug 2020
Copy of the legal title reportFile: SEARCH REPORT 1.pdf27 Aug 2020
Building Plan Approval / NA Order for plotted developmentFile: APPROVAL 1.pdf27 Aug 2020
Layout approvalFile: APPROVAL 3.pdf21 Aug 2020
PAN CardFile: PANCARD.pdf21 Aug 2020
Copy of Layout Approval (in case of layout)File: APPROVAL 3.pdf21 Aug 2020

How this compares with Solapur

0%of this project is bookeddistrict median 15%
15%of Solapur projects moved their completion datethis one has not
39%of Solapur registrations have lapsed or been cancelledthis one is among them

Computed across the 550+ Solapur projects on ReraGenie, from their own filings.

Keep GALAXY GOLD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DONGAON ROAD550+ in Solapur

Builder: GALAXY DEVELOPERS

GALAXY DEVELOPERS has 4 registrations on MahaRERA, including GALAXY APARTMENT and GALAXY COMPLEX. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Solapur district page.

Frequently asked questions

What does it mean that GALAXY GOLD shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GALAXY GOLD is delayed beyond 30 Mar 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GALAXY GOLD?

The registered promoter entity is GALAXY DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GALAXY GOLD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for GALAXY GOLD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GALAXY GOLD?

The professionals named in the filing: Architect: SHRIDHAR PAGUL; Engineer: SHRIDHAR PAGUL; Chartered Accountant: SHAILESH SHARMA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GALAXY GOLD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GALAXY GOLD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GALAXY GOLD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.