Registration lapsed No litigation declared Residential / Group Housing project

Gagan Vihar Co-operative Housing Society Limited

By Mishal Construction Private Limited

RG-MH-20491 · RERA P51900006748 · Last updated on MahaRERA portal: 11 Sep 2019

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 58 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2021Possession promised58 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 37%
1Complaints at MahaRERAon this registration
Jump to the 15 documents Report an error

Gagan Vihar Co-operative Housing Society Limited is a Residential / Group Housing project by Mishal Construction Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51900006748 on 16 Aug 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date. The completion date has moved by 24 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameGagan Vihar Co-operative Housing Society Limited
  • TypeResidential / Group Housing
  • Location
    • 126/7 Navghar Lane 1
    • Mulund East
    • Kurla
    • Mumbai Suburban
    • 400081
  • Pincode400081
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900006748
  • ReraGenie IDRG-MH-20491

Builder

  • NameMishal Construction Private Limited
  • Entity typeCompany
  • ChairpersonNaveenkumar Mishrimal Jain
  • Other registrations10 more →
  • No longer live9 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

58 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toDec 2021

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on16 Aug 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed15 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Gagan Vihar Co-operative Housing Society LimitedNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 11 Sep 2019, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 37%.

Gagan Vihar Co-operative Housing Society Limited: 49% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises37%
Sanitary Fittings within the flats / premises2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 11 Sep 2019, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed48

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots48
Closed/Covered48

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,104 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2981.34
Proposed, not sanctioned1,993 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP 12-16, SUNNY ESTATE II,SION TROMBAY ROAD, CHEMBUR

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectV.S.Vaidya & Associates
EngineerAssociated Consultants Consulting Engineers
PartnerRole in project
Mishal Construction Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005519Dec 2019 → Dec 2020

Reason as filed by the promoterDue to Implementation of DCR-2034 and modification in some of the provision the said DCR the final approvals was got delayed. As the same was beyond our control due to reason mentioned herein above, we request you hon’ble authority to grant us the extension of 1 year for completion of the said project. Once we obtain full Occupation Certificate from MCGM, we shall update the same on MahaRERA website.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000197454Mr. Deepak Kanhaiyalal ShimpiMishal Construction Pvt. Ltd01/07/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed15

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5)File: FORM 5 GAGANVIHAR CHS.pdf11 Sep 2019
Proforma of Allotment letterFile: Allotment Letter Draft Gaganvihar.pdf31 Oct 2017
Details of encumbrancesFile: Gagan Vihar_Encumbrance certificate.pdf28 Jul 2017
Declaration in FORM BFile: Form B Gaganvihar.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gagan Vihar_Architect Certificate.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gagan Vihar_Engg Certificate.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA certificate_Gagan Vihar.pdf28 Jul 2017
Proforma of Allotment letterFile: AGREEMENTFORSALE - GAGAN VIHAR.pdf28 Jul 2017
Building plan approvalFile: Gagan Vihar_IOD to be uploaded.pdf26 Jul 2017
Layout approvalFile: Last amended plan.pdf26 Jul 2017
Copy of the legal title reportFile: Gagan Vihar Title Certificate to be uploaded.pdf26 Jul 2017
Copy of Layout Approval (in case of layout)File: Last amended plan.pdf26 Jul 2017
Building Plan Approval (IOD)File: Gagan Vihar_IOD to be uploaded.pdf26 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Gagan Vihar_Commencement Certificate.pdf26 Jul 2017
PAN CardFile: Mishal Construction Private Limited PAN card.pdf24 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Mahesh Villa Ghatkopar Cooperative Housing Society LtdPlot No 12 Vallabhaug Lane Garodia Nagar Ghatkopar East Mumbai - 40007716CompletedDec 2015Late, Jun 2017
Mohan Sadan Co-Operative Housing Society LtdPlot No 2A of TPS III CTS No 5991 MG Road Ghatkopar East Mumbai 40007726CompletedJun 2015Late, Sep 2015

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Gagan Vihar Co-operative Housing Society Lim on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund East6,700+ in Mumbai Suburban

2 kmGagan Vihar Co-operativeCompleted 85Lapsed / revoked 75Other 109Dot size: filed unitsN

Filed coordinates, straight-line distance. 269 registered projects within 2 km.

Builder: Mishal Construction Private Limited

Mishal Construction Private Limited has 11 registrations on MahaRERA, including Gagan Vihar Co-operative Housing Society Limited and Gulistan Manzil Co-operative Housing Society Limited. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Gagan Vihar Co-operative Housing Society Limited shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Gagan Vihar Co-operative Housing Society Limited is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Gagan Vihar Co-operative Housing Society Limited?

The registered promoter entity is Mishal Construction Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Gagan Vihar Co-operative Housing Society Limited?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Gagan Vihar Co-operative Housing Society Limited?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Gagan Vihar Co-operative Housing Society Limited?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Gagan Vihar Co-operative Housing Society Limited?

The professionals named in the filing: Architect: V.S.Vaidya & Associates; Engineer: Associated Consultants Consulting Engineers. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Gagan Vihar Co-operative Housing Society Limited?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Gagan Vihar Co-operative Housing Society Limited. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Gagan Vihar Co-operative Housing Society Lim to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.