Home / Browse projects / Pune, Maharashtra / GAGAN CEFIRO PHASE 3

Registration lapsed No litigation declared Residential / Group Housing project

GAGAN CEFIRO PHASE 3

By GAGAN UNNATI PROMOTERS

RG-MH-10097 · RERA P52100002655 · Last updated on MahaRERA portal: 2 Jun 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • 7 complaints at MahaRERA
  • Completion date moved by 45 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
14 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 90%
7 of 37Units unsoldnot recorded sold or booked
7Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

GAGAN CEFIRO PHASE 3 is a Residential / Group Housing project by GAGAN UNNATI PROMOTERS in Pune, Maharashtra, registered with MahaRERA as P52100002655 on 2 Aug 2017. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 45 months from the original filing. 30 of the 37 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete. 7 complaints are on record with the regulator.

At a glance

Project

  • NameGAGAN CEFIRO PHASE 3
  • TypeResidential / Group Housing
  • Location
    • Undri Pisoli road
    • Undri
    • Haveli
    • Pune
    • 411028
  • Pincode411028
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100002655
  • ReraGenie IDRG-MH-10097

Builder

  • NameGAGAN UNNATI PROMOTERS
  • Entity typePartnership
  • PartnersGAGAN LIFESPACE LLP THROUGH AUTHORISED PARTNER SUSHIL AGARWAL, UNNATI WORLD LIFEPACE LLP THROUGH AUTHORISED PARTNER NIKUNJ SANGHVI
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

34 months past promisethis monthRegisteredAug 2017First promiseMar 2020Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on2 Aug 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 31 Mar 2020)
  • Buildings2 building records
  • Documents filed61 files

Current status

81%30 of 37 units booked

Figures as on 2 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING B1NA12037037
BUILDING B2NA120000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 2 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 90%.

BUILDING B183%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
BUILDING B283%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises30%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities16

As on 2 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes75%
Landscaping & Tree PlantingYes90%
Street LightingYes60%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes60%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes80%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
SWIMMING POOLYes100%

Parking filed37

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots37
Closed/Covered37
BuildingClosed/CoveredTotal
BUILDING B11818
BUILDING B21919

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,969 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
MAHALAXMI PUNYAI DEVELOPERSUNDRIPune
VANITA ARUN BHAGTANIPune (M Corp.)Pune
BHARATI ARJUN BHAGTANIPune (M Corp.)Pune
KISHOR ARJUN BHAGTANIPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI4180.08
Proposed, not sanctioned3,923 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAUNDH PUNE

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVILAS TARAWADI
EngineerG A BHILARE CONSULTANTS PVT LTD
Engineersiddhanath kamble
Chartered Accountantshankar agarwal
PartnerRole in project
GAGAN UNNATI PROMOTERS-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100005392Mar 2020 → Mar 2021

Reason as filed by the promoterOn Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. any notice, order, rule, notification of the Government and/or other public or competent authority/court c. Delay in grant of any NOC/permission/license/ connection installation of any services such as lifts, electricity & water connections & meters to the scheme/unit /road NOC or completion certificate from Appropriate Authority the Promoters/Owners having complied with all requirements. d. Del

EXT52100011599Mar 2020 → Mar 2023

Reason as filed by the promoterReason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. Delay on the part of the Local Authority or any other Public Body or Authority including the M.S.E.D.C.L, in issuing or granting necessary Certificates / Noc’s / Permissions / Licenses / Connections of any service such as Electricity, Drains and Water Connections and Meters to the said Project under construction by the Promoters on the said Land. c. Compliances with the cha

EXT52100017663Mar 2020 → Dec 2023

Reason as filed by the promoterReason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. Delay on the part of the Local Authority or any other Public Body or Authority including the M.S.E.D.C.L, in issuing or granting necessary Certificates / Noc’s / Permissions / Licenses / Connections of any service such as Electricity, Drains and Water Connections and Meters to the said Project under construction by the Promoters on the said Land. c. Compliances with the cha

EXT52100014017Mar 2020 → Sep 2023

Reason as filed by the promoterReason for Extension: On Account of varied reasons at different points of time during the tenure of the project such as: a. Non- availability or limited supply of steel, other building material, water or electric supply. b. Delay on the part of the Local Authority or any other Public Body or Authority including the M.S.E.D.C.L, in issuing or granting necessary Certificates / Noc’s / Permissions / Licenses / Connections of any service such as Electricity, Drains and Water Connections and Meters to the said Project under construction by the Promoters on the said Land. c. Compliances with the cha

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC005000000177947Nirmala BhosaleM/s Gagan Unnati Promoters23/12/2022
CC005000000228390Raviraj Rajendra GaikwadGagan Unnati Promoters06/03/2023
CC005000000238517Vaibhav Ashok KalangeGagan Unnati Promoters04/04/2023
CC005000000310383Rahul Anil GadkarGagan Unnati Promoters22/07/2024
CC12401250Rahul Anilrao GadkarGAGAN UNNATI PROMOTERS27/12/2024
CC12500246Shyam Babu ChoudharyGAGAN UNNATI PROMOTERS24/01/2025
CC12602260GAGAN UNNATI PROMOTERSNishant Kumar Pathak17/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 Jun 2024

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form - 1 (1).pdf2 Jun 2026
Form 2File: Form - 2 (1).pdf2 Jun 2026
Form 3File: Form - 3 (1)_compressed.pdf2 Jun 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD (5).pdf2 Jun 2026
Declaration in FORM BFile: FORM B.pdf19 Aug 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: B1B2 Completion.pdf26 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Under Taking FY 21-22.pdf5 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Under Taking FY 22-23.pdf5 Oct 2023
Declaration in FORM BFile: Rera Affidavit Cefiro.pdf4 Oct 2023
Certificates of CA (Form 3)File: RERA FORM 3.pdf4 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gagan Cefiro Engineer Certificate.pdf3 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer Certificate for quality asuarance_c.pdf3 Oct 2023
Disclosure of sold/ booked inventoryFile: Gagan Cefiro Sold book Inventory_c.pdf29 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rera-Architect Certificate-min.pdf28 Sep 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rera- Engineer Certificate-min.pdf28 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FY 18-19.pdf18 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FY 19-20.pdf18 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FY 20-21.pdf18 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Undertaking for form 5.pdf18 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate 21.pdf17 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate 22.pdf17 Mar 2023
Declaration about Commencement CertificateFile: Cefiro Format D.pdf16 Mar 2023
Disclosure of sold/ booked inventoryFile: Cefiro Sold Unsold Inventory 1.pdf16 Mar 2023
Disclosure of sold/ booked inventoryFile: Cefiro Revised Sold Unsold Inventory.pdf25 Jan 2023
Layout approvalFile: Cefiro Layout sanction1.pdf29 Jun 2022
Building plan approvalFile: Cefiro Building sanction1.pdf29 Jun 2022
Copy of Layout Approval (in case of layout)File: Cefiro Layout sanction1.pdf29 Jun 2022
Building Plan Approval (IOD)File: Cefiro Building sanction1.pdf29 Jun 2022
Disclosure of sold/ booked inventoryFile: Cefiro Sold Unsold Inventory.pdf23 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gagan Cefiro Ph 3 Arch certificate 31122021.pdf4 Jan 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gagan Cefiro Ph 3 Arch certificate 23032020.pdf10 Dec 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gagan Cefiro Ph 3 Arch certificate 06112020.pdf10 Dec 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gagan Cefiro Arch Certificate Phase 3 21062019.pdf27 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Cefiro Architect certificate Phase 3 29032019.pdf2 Apr 2019
Form 2AFile: Cefiro Ph 3 Quality assurance Certificate.pdf11 Dec 2018
Certificates of CA (Form 5)File: Gagan Cefiro Phase 3 Form 5.pdf4 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gagan Cefiro ph 3 Arch certificate 25082018.pdf28 Aug 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gagan Cefiro Ph 3 26042018.pdf3 May 2018
Layout approvalFile: Cefiro PH 3 Latest Sanction.pdf16 Apr 2018
Copy of Layout Approval (in case of layout)File: Cefiro PH 3 Latest Sanction.pdf16 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gagan Cefiro ph 3 Arch certificate.pdf18 Jan 2018
Details of encumbrancesFile: Encumbrance Cefiro.pdf6 Dec 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gagan Cefiro ph 3 arch certificate 1112017.pdf1 Nov 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: REV ARCH CERT CEFIRO PH 3.pdf23 Aug 2017
Layout approvalFile: Temp04297 PHASING VK 1.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Temp04297 PHASING VK 1.pdf27 Jul 2017
Declaration in FORM BFile: B-Form_Phase III_GUP.pdf27 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate phase 3.pdf27 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certificate phase 3.pdf27 Jul 2017
Certificates of CA (Form 3)File: CEFIRO CA CERT PHASE 3.pdf27 Jul 2017
Proforma of Allotment letterFile: Phase III_FP_ Gagan Cefiro.pdf26 Jul 2017
Building plan approvalFile: Temp04301.pdf20 Jul 2017
Building plan approvalFile: Temp04300.pdf20 Jul 2017
Building plan approvalFile: Temp04303.pdf20 Jul 2017
PAN CardFile: Gagan Unnati Promters Pan No (1).pdf20 Jul 2017
Copy of the legal title reportFile: TITLE REPORT.pdf20 Jul 2017
Details of encumbrancesFile: Mortgage Deed Index II 7711-2015.pdf20 Jul 2017
Building Plan Approval (IOD)File: Temp04303.pdf20 Jul 2017
Building Plan Approval (IOD)File: Temp04301.pdf20 Jul 2017
Building Plan Approval (IOD)File: Temp04300.pdf20 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: NA_Order-dt-31-3-2015.pdf20 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
GAGAN CEFIRO SHOPSUNDRI PUNE 41102812CompletedMar 2018Jan 2017

How this compares with Pune

81%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 45 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep GAGAN CEFIRO PHASE 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Undri13,700+ in Pune

2 kmGAGAN CEFIRO PHASE 3Completed 73Lapsed / revoked 29Other 54Dot size: filed unitsN

Filed coordinates, straight-line distance. 156 registered projects within 2 km.

Builder: GAGAN UNNATI PROMOTERS

GAGAN UNNATI PROMOTERS has 3 registrations on MahaRERA, including GAGAN CEFIRO PHASE 2 and GAGAN CEFIRO PHASE 3. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that GAGAN CEFIRO PHASE 3 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if GAGAN CEFIRO PHASE 3 is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of GAGAN CEFIRO PHASE 3?

The registered promoter entity is GAGAN UNNATI PROMOTERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in GAGAN CEFIRO PHASE 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against GAGAN CEFIRO PHASE 3?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for GAGAN CEFIRO PHASE 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at GAGAN CEFIRO PHASE 3?

The professionals named in the filing: Architect: VILAS TARAWADI; Engineer: G A BHILARE CONSULTANTS PVT LTD; Engineer: siddhanath kamble; Chartered Accountant: shankar agarwal. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in GAGAN CEFIRO PHASE 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About GAGAN CEFIRO PHASE 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save GAGAN CEFIRO PHASE 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.