Gadsing Empire
RG-MH-11333 · RERA P52600001866 · Last updated on MahaRERA portal: 3 Dec 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- Completion date moved by 79 months
- 4 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Gadsing Empire is a Residential / Group Housing project by Pradeep Shankar Gadsing in Solapur, Maharashtra, registered with MahaRERA as P52600001866 on 29 Jul 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 79 months from the original filing.
At a glance
Project
- NameGadsing Empire
- TypeResidential / Group Housing
- Location
- Alipur Road
- Barshi
- Solapur
- 413411
- Pincode413411
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52600001866
- ReraGenie IDRG-MH-11333
Builder
- NamePradeep Shankar Gadsing
- Entity typeIndividual
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on29 Jul 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 12 May 2019)
- Buildings3 building records
- Documents filed96 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Wing | NA | 6 | 0 | 0 | 0 | 0 |
| B Wing | NA | 8 | 0 | 0 | 0 | 0 |
| C Wing | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 3 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 60%.
A Wing37%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 60% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 5% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 5% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B Wing37%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 60% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 40% |
| Sanitary Fittings within the flats / premises | 5% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 5% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C Wing36%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 60% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 5% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 5% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 3 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 0% |
Parking filed100
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| B Wing | 28 | 21 | 49 |
| C Wing | 28 | 23 | 51 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Partner | Role in project |
|---|---|
| Pradeep Shankar Gadsing | - |
Extensions applied for4
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDear Sir/Madam, We would like to request you for extension of our Barshi Project due to the following reasons 1. Our Barshi Project has been on hold due to the lockdown since last year 2020. 2. Due to the lockdown last year and even today in 2021, we having been facing problems of not getting labour on time. 3.Overall market situation due to Covid since last year and present condition, we are not able to commence work on time. 4.We had applied for extension till April 2021 but the Covid situation has been the same and for the safety of the people and area lockdown we could not start the projec
Reason as filed by the promoterOur project is big. The market situation is low due to recession and national Covid 19 lockdown. The area is under complete lockdown.
Reason as filed by the promoterThe Project is extended due to down in market status and also recession in market. DUE to The demonetization suddenly in real estate market.
Reason as filed by the promoterDear Sir/Madam, We were in financial crunch from last 2-3 years due to Corona & market uncertain situations. Now we have currently started our project from Nov 2023. We have solved our financial and customer problems of Barshi project. Our customers have supported us by providing Resolution of the Association of Allottees. We have attached copy. The project will be completed within one year. Hence, we request you to give us extension period for our Barshi project. Kindly support us for completion of project.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed96
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Gadsing Constructions 2021-22.pdf | 3 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Gadsing Constructions 2022-23.pdf | 3 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Gadsing Constructions 2023-24.pdf | 3 Dec 2024 |
| Certificates of CA (Form 5)File: Form 5 Gadsing Constructions 2022-23.pdf | 20 Oct 2024 |
| Certificates of CA (Form 5)File: Form 5 Gadsing Constructions 2023-24.pdf | 20 Oct 2024 |
| Certificates of CA (Form 5)File: Form 5 Gadsing Constructions 2021-22.pdf | 20 Oct 2024 |
| Certificates of CA (Form 3)File: 9 APR 24 - converted.pdf | 9 Oct 2024 |
| Certificates of CA (Form 3)File: 9 APR 24 - converted.pdf | 9 Oct 2024 |
| Certificates of CA (Form 3)File: 8 JAN 24 - converted.pdf | 9 Oct 2024 |
| Certificates of CA (Form 3)File: 7 OCT 23 - converted.pdf | 9 Oct 2024 |
| Certificates of CA (Form 3)File: 6 JULY 23 - converted.pdf | 9 Oct 2024 |
| Certificates of CA (Form 3)File: 5 APR 23 - converted.pdf | 9 Oct 2024 |
| Certificates of CA (Form 3)File: 4 JAN 23 - converted.pdf | 9 Oct 2024 |
| Certificates of CA (Form 3)File: 3 OCT 22 - converted.pdf | 9 Oct 2024 |
| Certificates of CA (Form 3)File: 2 JULY 22.pdf | 9 Oct 2024 |
| Certificates of CA (Form 3)File: 1APR 22.pdf | 9 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: sold rev.pdf | 9 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - 2.pdf | 9 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - 3.pdf | 9 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 4.pdf | 9 Oct 2024 |
| Declaration in FORM BFile: form b.pdf | 8 Oct 2024 |
| Certificates of CA (Form 3)File: 1APR 22.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: 9 APR 24 - converted.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: 8 JAN 24 - converted.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: 7 OCT 23 - converted.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: 6 JULY 23 - converted.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: 5 APR 23 - converted.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: 4 JAN 23 - converted.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: 3 OCT 22 - converted.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: 2 JULY 22.pdf | 7 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 7 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD.pdf | 7 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: a 1 jan 23.pdf | 12 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: b 1 apr 23.pdf | 12 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: c 1 july 23.pdf | 12 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: d 1 oct 23.pdf | 12 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: e jan 24.pdf | 12 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: f apr 24.pdf | 12 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: SKMBT_C28422052509290.pdf | 3 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: SKMBT_C28020122419030.pdf | 26 May 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SKM_C284e22052305250.pdf | 23 May 2022 |
| Certificates of CA (Form 3)File: GC.pdf | 13 May 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA_A_Building.pdf | 27 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA_A_Building.pdf | 27 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA_B_Building.pdf | 27 Apr 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA_C_Building.pdf | 27 Apr 2022 |
| Declaration about Commencement CertificateFile: Declaration Of CC.pdf | 14 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2021 (1) Architect Certificate.pdf | 14 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20).pdf | 14 Oct 2021 |
| Disclosure of sold/ booked inventoryFile: Sold Inventory.pdf | 14 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19).pdf | 14 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2020.pdf | 14 Oct 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2021.pdf | 14 Oct 2021 |
| Certificates of CA (Form 3)File: Certificate (1) (1).pdf | 4 Sep 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annual Report (1).pdf | 4 Sep 2021 |
| Certificates of CA (Form 3)File: Form 3 2020_11zon.pdf | 29 Jul 2021 |
| Certificates of CA (Form 3)File: Form 3 2021_11zon.pdf | 29 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2020.pdf | 29 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2021.pdf | 29 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate (19-20).pdf | 2 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate (20-21).pdf | 2 Jul 2021 |
| Declaration about Commencement CertificateFile: Declaration of CC.pdf | 28 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: gad-01.pdf | 28 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 2020.pdf | 28 Jun 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 2021.pdf | 28 Jun 2021 |
| OtherFile: Barshi Project Photos.pdf | 22 Jun 2021 |
| OtherFile: Barshi Project Photos.pdf | 22 Jun 2021 |
| OtherFile: Barshi Project Photos.pdf | 22 Jun 2021 |
| Disclosure of sold/ booked inventoryFile: Gadsing Empire Sales Statement B.pdf | 21 May 2021 |
| Disclosure of sold/ booked inventoryFile: Gadsing Empire Sales Statement C.pdf | 21 May 2021 |
| Certificates of CA (Form 5)File: Form 5.pdf | 25 May 2019 |
| Certificates of CA (Form 5)File: Form 3 Annexture- A.pdf | 25 May 2019 |
| Certificates of CA (Form 5)File: Form 3 CA Certificate.pdf | 25 May 2019 |
| Certificates of CA (Form 5)File: Form 3 Additional Information.pdf | 25 May 2019 |
| OtherFile: B Building.pdf | 10 May 2019 |
| OtherFile: C Building.pdf | 10 May 2019 |
| OtherFile: Plinth Certificate .pdf | 25 Oct 2017 |
| OtherFile: Plinth Certificate .pdf | 25 Oct 2017 |
| Declaration in FORM BFile: Promoter Affidavit cum declaration.pdf | 28 Jul 2017 |
| Layout approvalFile: Sanction Plan Layout.pdf | 25 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Gadsing Paradise | Chinchwad Pune | 15 | Completed | Apr 2008 | Late, Jun 2011 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Solapur
Computed across the 550+ Solapur projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 96 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Gadsing Empire on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Barshi550+ in Solapur
KATHALE VIHAR
SATISH MALANBAI ANDHARE
Royal Residency Building No 4
Shubhankar Developers
Ray Nagar Housing Project Phase 2
Vasant Vihar Realty Pvt Ltd
PMAY BARSHI NAGAR PARISHAD AHP
BARSHI NAGAR PARISHAD
R M Dhariwal Township Velapur Plotting
Dhariwal And Chhoriya Buildcon Pvt Ltd
Kurdu Plotting on Gat No 264
Pragati Infra Services Pvt. Ltd.
See every Solapur project, with the district possession charts
Builder: Pradeep Shankar Gadsing
Pradeep Shankar Gadsing has 1 registration on MahaRERA, including Gadsing Empire. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Solapur district page.
Frequently asked questions
What does it mean that Gadsing Empire shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Gadsing Empire is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Gadsing Empire?
The registered promoter entity is Pradeep Shankar Gadsing, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Gadsing Empire?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Gadsing Empire?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
What should I check before booking in Gadsing Empire?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback