Home / Browse projects / Pune, Maharashtra / FUTURE ELITE

Registration lapsed No litigation declared Residential / Group Housing project

FUTURE ELITE

By FUTURE HOMES

RG-MH-61644 · RERA P52100051491 · Last updated on MahaRERA portal: 9 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 19 months past the filed date
  • Completion date moved by 19 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2025Possession promised19 months past this date
6 of 11Construction stages donefurthest along: External plumbing and external plaster, 80%
0Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

FUTURE ELITE is a Residential / Group Housing project by FUTURE HOMES in Pune, Maharashtra, registered with MahaRERA as P52100051491 on 23 Jun 2023. Possession was promised by 31 Mar 2025 and is now 19 months past that date. The completion date has moved by 19 months from the original filing.

At a glance

Project

  • NameFUTURE ELITE
  • TypeResidential / Group Housing
  • Location
    • MUNJOBA NAGAR KALAKHADAK
    • WAKAD
    • Mulshi
    • Pune
    • 411057
  • Pincode411057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100051491
  • ReraGenie IDRG-MH-61644

Builder

  • NameFUTURE HOMES
  • Entity typePartnership
  • PartnersSUMIT OMPRAKASH SAKOLKAR, SARANG ARUN UJAWANE, NIKHIL RAMHARI KATORE, SANIL RAMESH SHINDE

Key dates

19 months past promisethis monthRegisteredJun 2023First promiseAug 2023Revised toMar 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Jun 2023
  • Promised completion31 Mar 2025
  • Revised completionRevised to 31 Mar 2025 (originally 25 Aug 2023)
  • Buildings1 building record
  • Documents filed58 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
future eliteNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 80%.

future elite: 65% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities15

As on 9 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Open Space4

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area300 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
FUTURE HOMESTathwadePune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municiple Corporation
Permissible FSI415.0
Proposed, not sanctioned382 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAUNDH 411007

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAHUL KALBHOR
EngineerTIRUVILLE CONSTRUCTIONS
Chartered Accountantca bhushan jadhav
PartnerRole in project
FUTURE HOMES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100017258Aug 2023 → Mar 2025

Reason as filed by the promoterSir, We partners of Future Homes applied for RERA Registration on 19/11/2022 of our project Future Elite and got registration certificate on 23/06/2023 with completion date of 25/08/2023. We are not able to complete the project in 2 months thats why we are applying for RERA Extension under 7(3). All the units in the project are unsold. Consent attached for your referance.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 4 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_30062024.pdf9 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_30092024.pdf9 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 300624 Form 3 Future Homes.pdf25 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 300924 Form 3 Future Homes.pdf25 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 300624 Form 3 Future Homes.pdf25 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 (2).pdf25 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30062023 Form 2 Engineer Certificate.pdf3 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30092023 Form 2 Engineer Certificate.pdf3 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31122023 Form 2 Engineer Certificate.pdf3 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31032024 Form 2 Engineer Certificate.pdf3 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30062023.pdf17 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30092023 Form 2 Engineer Certificate Future Elite.pdf17 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 31122023 Form 2 Engineer Certificate Future Elite.pdf17 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31032024.pdf17 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 30092023.pdf17 Jun 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31122023.pdf17 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30062023 Form 2 Engineer Certificate Future Elite.pdf17 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 30092023 Form 2 Engineer Certificate Future Elite.pdf17 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31122023 Form 2 Engineer Certificate Future Elite.pdf17 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 31032024 Form 2 Engineer Certificate Future Elite.pdf17 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Future Elite Form 2A.pdf17 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 300623 Form 3 Future Homes.pdf17 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 300923 Form 3 Future Homes.pdf17 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 311223 Form 3 Future Homes.pdf17 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 310324 Form 3 Future Homes.pdf17 Jun 2024
Declaration in FORM BFile: Affidavit cum declaration.pdf1 Aug 2023
Disclosure of sold/ booked inventoryFile: Disclosure Sold Unsold.pdf1 Aug 2023
Declaration about Commencement CertificateFile: future arch.pdf2 Jun 2023
Declaration about Commencement CertificateFile: bhalerao.pdf2 Jun 2023
Other - TechnicalFile: future arch.pdf2 Jun 2023
Other - TechnicalFile: bhalerao.pdf2 Jun 2023
Other - TechnicalFile: imgw-301123847-2.pdf14 Mar 2023
Copy of the legal title reportFile: Adobe Scan 13 Mar 2023.pdf23 Feb 2023
Declaration about Commencement CertificateFile: declaration d.pdf22 Feb 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ilovepdf_merged (2).pdf22 Feb 2023
Other - LegalFile: legal.pdf22 Feb 2023
Other - LegalFile: ilovepdf_merged (3).pdf22 Feb 2023
Details of encumbrances concerned to FinanceFile: Non encumbrance certificate.pdf21 Feb 2023
Details of encumbrances concerned to LegalFile: Non encumbrance certificate.pdf21 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certificate_compressed.pdf21 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A - Future.pdf21 Feb 2023
Other - LegalFile: future-letter-request-reg-no.pdf21 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginner certificate 2023.pdf15 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5.pdf14 Feb 2023
CERSAI detailsFile: CERSAI_Search_Report_200261667781_For_Asset_Based_Search_01_03_2023_00_16_59_979.pdf14 Feb 2023
Proforma of Agreement for saleFile: afs future.pdf14 Feb 2023
Deviation Report with respect to Allotment letterFile: DEVIATION-OF-ALLOTMENT-LETTER.pdf14 Feb 2023
Deviation Report with respect to model copy of AgreementFile: deviation-of-afs.pdf14 Feb 2023
Proforma of Allotment letterFile: allotment letter final.pdf9 Dec 2022
Layout approvalFile: imgw-301123847.pdf4 Aug 2022
Building plan approvalFile: imgw-301123814.pdf4 Aug 2022
PAN CardFile: PAN CARD FIRM.pdf4 Aug 2022
Details of encumbrances concerned to FinanceFile: ENCUMBRANCES DECLARATION.pdf4 Aug 2022
Details of encumbrances concerned to LegalFile: ENCUMBRANCES DECLARATION.pdf4 Aug 2022
Copy of Layout Approval (in case of layout)File: imgw-301123847.pdf4 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: imgw-301123814.pdf4 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: SKM_C250i23030111570.pdf4 Aug 2022
Declaration in FORM BFile: Adobe Scan 9 Jun 2023.pdf4 Aug 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 19 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep FUTURE ELITE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WAKAD13,700+ in Pune

2 kmFUTURE ELITECompleted 53Lapsed / revoked 26Other 57Dot size: filed unitsN

Filed coordinates, straight-line distance. 136 registered projects within 2 km.

Builder: FUTURE HOMES

FUTURE HOMES has 1 registration on MahaRERA, including FUTURE ELITE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that FUTURE ELITE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if FUTURE ELITE is delayed beyond 31 Mar 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of FUTURE ELITE?

The registered promoter entity is FUTURE HOMES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in FUTURE ELITE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for FUTURE ELITE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at FUTURE ELITE?

The professionals named in the filing: Architect: RAHUL KALBHOR; Engineer: TIRUVILLE CONSTRUCTIONS; Chartered Accountant: ca bhushan jadhav. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in FUTURE ELITE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About FUTURE ELITE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save FUTURE ELITE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.