Home / Browse projects / Dakshina Kannada, Karnataka / FORTUNE HILL SIDE

Registration approved No litigation declared Mixed Development project

FORTUNE HILL SIDE

By FORTUNE PROMOTERS

RG-KA-11288 · RERA PRM/KA/RERA/1257/334/PR/220622/005021 · Last updated on RERA Karnataka portal: 12 Oct 2026

Source: official RERA Karnataka filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
Dec 2025Possession promisedno revision filed
15 of 15Construction stages doneevery applicable stage filed complete
13 of 20Units unsoldnot recorded sold or booked
0Complaints at RERA Karnatakaon this registration
Jump to the 118 documents Report an error

FORTUNE HILL SIDE is a Mixed Development project by FORTUNE PROMOTERS in Dakshina Kannada, Karnataka, registered with RERA Karnataka as PRM/KA/RERA/1257/334/PR/220622/005021 on 22 Jun 2022. Possession is promised by 31 Dec 2025. 7 of the 20 units on this registration are recorded sold or booked, and 15 of 15 construction stages are filed complete.

At a glance

Project

  • NameFORTUNE HILL SIDE
  • TypeMixed Development
  • Location
    • Mangalore
    • Dakshina Kannada
    • 575008
  • Pincode575008
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PRM/KA/RERA/1257/334/PR/220622/005021
  • ReraGenie IDRG-KA-11288

Builder

  • NameFORTUNE PROMOTERS
  • Entity typePartnership Firm
  • GSTIN29AAEFF2896H1Z1
  • Authorized SignatoryMAHENDRA VARMA JAIN
  • Other registrations7 more →
  • Declared earlier projects7 →

Key dates

this monthRegisteredJun 2022PromisedDec 2025

Key facts

Registration and timeline

  • StatusRegistration approved
  • Registered on22 Jun 2022
  • Promised completion31 Dec 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed118 files

Current status

35%7 of 20 units booked
51.7%Of the estimated cost spent so far

Figures as on 12 Oct 2026, this project's latest RERA Karnataka filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
FORTUNE HILLSIDE-----20

The full filing

Everything below is from the project's own RERA Karnataka filing, free to read.

Construction progress by building1

As on 12 Oct 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 15 construction stages are filed complete.

Building: 100% average across the applicable activities

ActivityProgress
Earth work and other leveling preparation work100%
Foundation footing work100%
Upto Plinth Level100%
Sub-structure flooring (Parking Floor, more than one floor below general ground level)100%
Retaining wall (All types)100%
RCC or MS Framed structure100%
Masonry Construction100%
Plastering inside , outside & Ceiling100%
Joinery: Doors, Windows, Ventilators etc100%
Basic work of Water supply, Sanitary and Electrification100%
Dadoing, Skirting, Flooring, Tiles work (All types)100%
Railing and Grill fixing100%
Electrification, Water supply and Sanitary Finishing100%
Painting100%
Fire prevention and fire fighting fitting and fixture with networkNot applicable
Weather Proof work(tile,concrete)Not applicable
Wardrobe, Showcase, Kitchen cabinet, Puja workNot applicable
Elevation work100%
Internal and External work including landscapes as per sanctioned drawingsNot applicable

Progress on shared amenities40

As on 12 Oct 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Water SupplyYes100%
Sewage and Drainage SystemYes100%
Water conservation/rain water harvesting/recharge of ground waterYes100%
Energy managementNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Solid waste management and disposalNoNot applicable
Emergency Evacuation servicesNoNot applicable
Internal Roads & FootpathsNoNot applicable
Electricity supply transformer and substationYes100%
Storm water drainsNoNot applicable
Use of renewable energyNoNot applicable
Sewage Treatment Plant (STP)Yes100%
Parks & Tree plantingNoNot applicable
Street LightingNoNot applicable
ElectricityYes100%
Smart Home AutomationNoNot applicable
CCTV SurveillanceYes100%
Club HouseNoNot applicable
Community HallYes100%
Outdoor Sports facilityNoNot applicable
Indoor Sports facilityNoNot applicable
Swimming PoolNoNot applicable
GymYes100%
ParksNoNot applicable
Power BackupYes100%
Piped GasYes100%
Water and SanitationNoNot applicable
Air ConditioningNoNot applicable
StaircasesYes100%
LiftsYes100%
Corridor/LobbiesYes100%
Fire escapesYes100%
Common entrance and exit for the building/common portico/foyer/verandahNoNot applicable
BasementYes100%
TerraceYes100%
Outer WallYes100%
Open parking areasYes100%
Provision for lodging of management staff and security staffNoNot applicable
Water conservation and renewable energyNoNot applicable
Common storage spacesNoNot applicable

Land and ownership1

This page carries no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area781 sq m
Named landowners1
LandownerVillageDistrict
FORTUNE PROMOTERS--

Project account and cost

70 percent of buyer money must sit in the project account, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Estimated costRs 8.19 cr
Cost incurredRs 4.23 cr
Spent of the estimate51.67%
Cost lineEstimatedIncurred
Estimated Cost of Construction as certified by EngineerRs 7.00 crRs 3.94 cr
Principal sum and interest payable to financial institutions-Money Lenders on construction funding or money borrowed for constructionRs 78.00 lakh-
On-site expenditure-Consultants FeesRs 23.00 lakhRs 29.25 lakh
On-site expenditure-Site OverheadRs 17.50 lakh-

Certifying professionals and partners3

Certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGUULSHAN ROY
EngineerH ANAND BHAT
Chartered AccountantUMESH RAO

Complaints filed with RERA Karnataka

No complaints on record against this registration.

Documents filed118

As listed on the registration, under the names the promoter filed them with; the newest 80 of 118 are shown. The files themselves are available at source: search the registration number PRM/KA/RERA/1257/334/PR/220622/005021 on the RERA Karnataka portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
SOLD UNSOLD UNITSFile: sold unsold unit.pdf12 Oct 2026
CA KYCFile: CA KYC.pdf12 Oct 2026
Q1 2026-27 Form-4 Certificate issued by Chartered AccountantFile: Form 4- CA Certificate-Q1 2026-27.pdf4 Jul 2026
Q1 2026-27 Form-5 Certificate issued by ArchitectFile: Form 5-Architects Cft-Q1 2026-27.pdf4 Jul 2026
Q1 2026-27 Form-6 Certificate issued by Structural EngineerFile: form 6 & revised estimation.pdf4 Jul 2026
Q4 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4-CA Certificate-Hillside-Q4 2025-26.pdf23 May 2026
Q4 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5-Architects Cft-Q4 2025-26.pdf23 May 2026
Q4 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6-Enginner Cft-Hillside Q4 25-26.pdf23 May 2026
Q3 2025-26 Form-4 Certificate issued by Chartered AccountantFile: Form 4-CA Report-Fortune Hillside-Q3 2025-26.pdf20 Feb 2026
Q3 2025-26 Form-5 Certificate issued by ArchitectFile: Form 5-Architects Cft-Hillside-Q3 2025-26.pdf20 Feb 2026
Q3 2025-26 Form-6 Certificate issued by Structural EngineerFile: Form 6-Engineer Cft-Hillside-Q3 2025-26.pdf20 Feb 2026
water nocFile: NOC -Water.jpg9 Jun 2022
power nocFile: NOC -Mescom.pdf9 Jun 2022
power noc fee receiptFile: mescom fee receipt.pdf9 Jun 2022
proforma AOSFile: proforma AOS.pdf9 Jun 2022
STP DRAWINGFile: STP.jpg9 Jun 2022
CLARIFICATIONFile: CLARIFICATION.pdf9 Jun 2022
RTC, survey 114/15C-
Mutation, survey 114/15C-
Encumbrance Certificate, survey 114/15C-
Conversion/Alienation Order, survey 114/15C-
Sale/Title/Gift Deed, survey 114/15C-
Khatha, survey 114/15C-
Registration CertificateFile: Firm Registration.pdf-
Partnership DeedFile: Partnership Deed_compressed.pdf-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Partner Details-
Certificate issued by CA Form 1File: Form 1-CA Certificate.pdf-
Certificate issued by Architect Form 2File: Form 2 -Architects Cft.pdf-
Certificate issued by Engineer Form 3File: Form 3-Engineer Cft.pdf-
Project Chartered Accountant-
Project Engineer-
Project Architect-
AffidavitFile: litigation affidavit.pdf-
Certificate from Chartered AccountFile: Form 1-CA Certificate.pdf-
Balance Sheet 2020 - 2021File: Balance Sheet 20-21.jpg-
Balance Sheet 2019 - 2020File: Balance Sheet 19-20.pdf-
Balance Sheet 2018 - 2019File: Balance Sheet 2018-19.pdf-
Audited Profit and Loss Statement 2020 - 2021File: P_L Statement 20-21.jpg-
Audited Profit and Loss Statement 2019 - 2020File: P_L Statement 19-20.pdf-
Audited Profit and Loss Statement 2018 - 2019File: P_L Statement 2018-19.pdf-
Cash Flow Statement 2020 - 2021File: UDIN No 2020-21.jpg-
Cash Flow Statement 2019 - 2020File: Cash Flow 19-20.pdf-
Auditor's Report 2020 - 2021File: Audit Report 20-21.pdf-
Auditor's Report 2019 - 2020File: Audit Report 19-20.pdf-
Auditor's Report 2018 - 2019File: Audit Report 2018-19.pdf-
Income Tax Return Acknowledgement 2020 - 2021File: Tax Acknowledgement 20-21.jpg-
Income Tax Return Acknowledgement 2019 - 2020File: ITR Acknowledgement 19-20.pdf-
Income Tax Return Acknowledgement 2018 - 2019File: ITR Acknowledgement 2018-19.pdf-
Building Licence-
sanction plan-
Single Layout-
sanction plan-
sanction plan-
Single Layout-
Specifications-
Plan 1-
Plan 2-
Stability Certficate-
title deed-
Conversion-
Conversion-
proforms AOS-
Proforma allotment letter-
broucher-
form b-
affidavit 3(1)-
NOC -Mescom-
NOC -Water-
Unnamed document-
Unnamed document-
Fire NOC_compressed-
Unnamed document-
Pollution NOC-

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date1 declared completed, no finish date filed
ProjectLocationStatusPromisedDelivered
FORTUNE HIGHWAY-2IN, S.NO.44/A1A AND S.NO.44/A1A OF MARPADY VILLAGE,MANGALORE TALUK,D.KOngoingDec 2025Not delivered
FORTUNE CENTERS.NO 227/3 C1P1 MUDAR VILLAGE, KARKALA TALUKCompleted-No date filed

How this compares with Dakshina Kannada

35%of this project is bookeddistrict median 38%
30%of Dakshina Kannada projects moved their completion datethis one has not
0%of Dakshina Kannada registrations are shown as withdrawn or revokedthis one is not

Computed across the 620+ Dakshina Kannada projects on ReraGenie, from their own filings.

Keep FORTUNE HILL SIDE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

Other projects near Dakshina Kannada620+ in Dakshina Kannada

2 kmFORTUNE HILL SIDEOther 11Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: FORTUNE PROMOTERS

FORTUNE PROMOTERS has 8 registrations on RERA Karnataka, including FORTUNE HILL SIDE and FORTUNE GALAXY. Its filings declare 7 earlier projects, 2 of them declared completed. Read the full track record. See more projects on the Dakshina Kannada district page.

Frequently asked questions

What are my rights if FORTUNE HILL SIDE is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, at the rate the state's RERA rules prescribe, or exit and claim a full refund with interest. Claims are filed as complaints with RERA Karnataka.

How do I verify and contact the developer of FORTUNE HILL SIDE?

The registered promoter entity is FORTUNE PROMOTERS, a partnership firm as per the filing. Its GSTIN 29AAEFF2896H1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's RERA Karnataka listing and in its filed documents.

Is my payment protected in FORTUNE HILL SIDE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

Who certifies construction progress at FORTUNE HILL SIDE?

The professionals named in the filing: Architect: GUULSHAN ROY; Engineer: H ANAND BHAT; Chartered Accountant: UMESH RAO. Their certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in FORTUNE HILL SIDE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area; that the agreement follows the model agreement under the state's RERA rules, with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on RERA Karnataka, and we read every report.

Report an error Share feedback

Report an error or share feedback

About FORTUNE HILL SIDE. Everything on this page comes from what the promoter filed on RERA Karnataka, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save FORTUNE HILL SIDE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.