Home / Browse projects / Mumbai Suburban, Maharashtra / Forefront Primeria

Registration lapsed No litigation declared Residential / Group Housing project

Forefront Primeria

By Forefront Private Limited

RG-MH-11161 · RERA P51800010015 · Last updated on MahaRERA portal: 28 Jul 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 2 complaints at MahaRERA
  • Completion date moved by 54 months
  • 7 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
1 of 11Construction stages donefurthest along: Basement (if any), 95%
34 of 58Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

Forefront Primeria is a Residential / Group Housing project by Forefront Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800010015 on 23 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 54 months from the original filing. 24 of the 58 units on this registration are recorded sold or booked, and 1 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameForefront Primeria
  • TypeResidential / Group Housing
  • Location
    • Sant Muktabai Road
    • Vile Parle
    • Greater Mumbai (M Corp.) (Part) (802794)
    • Mumbai
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800010015
  • ReraGenie IDRG-MH-11161

Builder

  • NameForefront Private Limited
  • Entity typeCompany

Key dates

10 months past promisethis monthRegisteredAug 2017First promiseJun 2021Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Aug 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2021)
  • Buildings1 building record
  • Documents filed61 files

Current status

41%24 of 58 units booked

Figures as on 28 Jul 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Forefront PrimeriaNA141258058

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

1 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 95%.

Forefront Primeria: 85% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)95%
Podiums (if any)0%
Plinth95%
Stilt Floor95%
Slabs of Super Structure95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 28 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes90%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes65%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed71

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots71
Closed/Covered63
Open Space8

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,589 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on16 Jun 2025

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI4492.98
Proposed, not sanctioned3,108 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch30 Navyug Society Krishna Kunj VLMehta Road Opp Sunflower Hospital JVPD Scheme Mumbai 400056

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPriyank Bhatt
ArchitectDilip kadam
EngineerS S Bhatt
Chartered AccountantS.S Padhi & Associates
Chartered AccountantMori & Associates Chartered Accountants
PartnerRole in project
Forefront Private Limited-

Extensions applied for7

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800009391Jun 2021 → Sep 2021

Reason as filed by the promoterRevised Concession Plan with respect to said project

EXT51800011674Jun 2021 → Sep 2022

Reason as filed by the promoterRevised Commencement Certificate upto top of 12 Floor of WIng A & B plus Fitness Centre on Terrace plus Overhead Water Tank and valid upto 02.11.2022

EXT51800013665Jun 2021 → Aug 2023

Reason as filed by the promoterThe Building is constructed 95 percent. Internal work is in the process. The project was delayed due to no proper permissions ontime. Therefore on basis of genuine reason, the consent as per the rules of MAHARERA Act is obtained

EXT51800012539Jun 2021 → Dec 2022

Reason as filed by the promoterAs per Commencement Certificate of Full building, We request the Hon'ble Authority to permit our application for project extension upto 30/12/2022

EXT51800019556Jun 2021 → Mar 2025

Reason as filed by the promoterThe Developer like to inform the Hon'ble Authority that the Building is completed in all respect except. Due to certain financial issues, The Developer require an extension of 5 months. In the interest of Justice and considering 22 families who have purchased flats in the subject Project. The Extension be given without consent of Allottees.The Developer further like to inform that due to his genuine reasons till date the Allottees have supported .

EXT51800017697Jun 2021 → Dec 2023

Reason as filed by the promoterThe Building is fully completed and further we have applied for Occupation Certificate which we shall recieve in due course of time. Further as required we have obtained consent of Allottes under Section 7(3) attached herewith.

EA17062501616Jun 2021 → Dec 2025

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. Given the circumstances, we kindly request an extension until 31/12/2025. to complete the project and fulfil all regulatory requirements

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000023293Rujuta ThatteForefront Pvt. Ltd16/02/2018
CC006000000591416Brijesh Manubhai RathodForefront Private Limited03/08/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Jun 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2019-2020)File: FORM 2A 2019-2020.pdf28 Jul 2025
Form 2A (FY 2020-2021)File: FORM 2A 2020-2021.pdf28 Jul 2025
Form 2A (FY 2021-2022)File: FORM 2A 2021-2022.pdf28 Jul 2025
Form 2A (FY 2022-2023)File: FORM 2A 2022-2023.pdf28 Jul 2025
Form 2A (FY 2023-2024)File: FORM 2A 2023-2024.pdf28 Jul 2025
Form 2A (FY 2024-2025)File: FORM 2A 2024-2025.pdf28 Jul 2025
Form 5 (FY 2017-2018)File: Form 5 FY 2018-19 MORI.pdf2 Jul 2025
Form 1File: Form 1 March 2025.pdf17 Jun 2025
Form 2File: Form 2 March 2025.pdf17 Jun 2025
Form 3File: Form 3 March 2025.pdf17 Jun 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 Mar 2025.pdf17 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 March 2025.pdf12 Jun 2025
Certificates of CA (Form 3)File: Form 3 March 2025.pdf12 Jun 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 March 2025.pdf12 Jun 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Primeria (1).pdf11 Jun 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Primeria (2).pdf11 Jun 2024
Certificates of CA (Form 3)File: CA Certificate Form-3_FPL 31-03-2023.pdf11 Jun 2024
Declaration about Commencement CertificateFile: DeclaratIon about CC_Primeria.pdf10 Oct 2023
Declaration in FORM BFile: Affidavit cum Declaration_Primeria RERA.pdf10 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT AREA CERTIFICATE PRIMERIA.pdf10 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Units_RERA.pdf10 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineer Certificate_Primeria_2019.pdf9 Oct 2023
Proforma of Agreement for saleFile: Agreement for Sale Primeria.pdf9 Oct 2023
Declaration about Commencement CertificateFile: RERA EXTENSION LETTER.pdf29 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1_Form_1_ Forefront_Primeria_FY_19_20.pdf29 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1_Form_1_ Forefront_Primeria_FY_20_21.pdf29 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1_Form_1_ Forefront_Primeria_FY_21_22.pdf29 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2_Form_2_ Forefront_Primeria_FY_19_20.pdf29 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2_Form_2_ Forefront_Primeria_FY_20_21.pdf29 Sep 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2_Form_2_ Forefront_Primeria_FY_21_22.pdf29 Sep 2022
Disclosure of sold/ booked inventoryFile: RERA EXTENSION LETTER.pdf29 Sep 2022
CERSAI detailsFile: RERA EXTENSION LETTER.pdf29 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 3_Form_5_ Forefront_Primeria_FY_18_19.pdf29 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 3_Form_5_ Forefront_Primeria_FY_19_20.pdf29 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 3_Form_5_ Forefront_Primeria_FY_20_21.pdf29 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Certificates of Architect Form 1.pdf19 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificates of Engineer Form 2.pdf19 Dec 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf28 Feb 2019
Certificates of CA (Form 3)File: Form 3.pdf28 Feb 2019
Commencement Certificates / NA Order for plotted developmentFile: 11th floor further cc primeria.pdf24 Dec 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: Registration Certificate.PDF24 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf15 Dec 2018
Building plan approvalFile: 11th 12th Floor IOD.pdf2 Jun 2018
Building Plan Approval (IOD)File: 11th 12th Floor IOD.pdf2 Jun 2018
Building plan approvalFile: Amended-Issue-letter (1).pdf5 Apr 2018
Building Plan Approval (IOD)File: Amended-Issue-letter (1).pdf5 Apr 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencment Certificate 03-10-2017.pdf5 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Certificate of Engineer.pdf5 Apr 2018
Layout approvalFile: Plans - 1st page.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Plans - 1st page.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 2035009_furthercc_signed.pdf29 Jul 2017
Declaration in FORM BFile: Form B - FPL.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Primeria.pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate - Primeria-ilovepdf-compressed.pdf29 Jul 2017
Certificates of CA (Form 3)File: Form 3 - Primeria.pdf29 Jul 2017
Proforma of Allotment letterFile: Agreement undertaking-Primeria.pdf29 Jul 2017
Details of encumbrancesFile: Encumbrances_Forefront Primeria.pdf18 Jul 2017
Building plan approvalFile: IOD.pdf17 Jul 2017
PAN CardFile: Pan Card.pdf17 Jul 2017
Copy of the legal title reportFile: Title Certificate 27th Sept 2016-ilovepdf-compressed.pdf17 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf17 Jul 2017

How this compares with Mumbai Suburban

41%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 54 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Forefront Primeria on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vile Parle6,700+ in Mumbai Suburban

2 kmForefront PrimeriaCompleted 157Lapsed / revoked 77Other 141Dot size: filed unitsN

Filed coordinates, straight-line distance. 375 registered projects within 2 km.

Builder: Forefront Private Limited

Forefront Private Limited has 1 registration on MahaRERA, including Forefront Primeria. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Forefront Primeria shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Forefront Primeria is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Forefront Primeria?

The registered promoter entity is Forefront Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Forefront Primeria?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Forefront Primeria?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Forefront Primeria?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Forefront Primeria?

The professionals named in the filing: Architect: Priyank Bhatt; Architect: Dilip kadam; Engineer: S S Bhatt; Chartered Accountant: S.S Padhi & Associates; Chartered Accountant: Mori & Associates Chartered Accountants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Forefront Primeria?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Forefront Primeria. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Forefront Primeria to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.