Home / Browse projects / Aurangabad, Maharashtra / Flora Phase II

Registration lapsed No litigation declared Residential / Group Housing project

Flora Phase II

By Tapadia Constructions Limited

RG-MH-59080 · RERA P51500029338 · Last updated on MahaRERA portal: 28 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 31 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Aurangabad registration emailed to you, free during the pilot beta.
Mar 2024Possession promised31 months past this date
54 of 66Construction stages doneacross 6 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 79 documents Report an error

Flora Phase II is a Residential / Group Housing project by Tapadia Constructions Limited in Aurangabad, Maharashtra, registered with MahaRERA as P51500029338 on 18 May 2021. Possession was promised by 31 Mar 2024 and is now 31 months past that date.

At a glance

Project

  • NameFlora Phase II
  • TypeResidential / Group Housing
  • Location
    • Aurangabad Pune Road
    • Tisgaon
    • Aurangabad
    • 431102
  • Pincode431102
  • RERA no.P51500029338
  • ReraGenie IDRG-MH-59080

Builder

  • NameTapadia Constructions Limited
  • Entity typeCompany
  • Other registrations3 more →
  • Completed3 of 4
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

31 months past promisethis monthRegisteredMay 2021PromisedMar 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on18 May 2021
  • Promised completion31 Mar 2024
  • Revised completionNone
  • Buildings6 building records
  • Documents filed79 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Row House A-73 To A-78NA20000
Row House A-79 To A-85NA20000
Row House A-86 To A-92NA20000
Row House A-93 To A99NA20000
Row House A-100 To A-106NA20000
Row House A-107 To A-113NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 28 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

54 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Podiums (if any), at 0%.

Row House A-73 To A-7882%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House A-79 To A-8582%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House A-86 To A-9282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House A-93 To A9982%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House A-100 To A-10682%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Row House A-107 To A-11382%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 28 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,123 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3884.34
Proposed, not sanctioned3,884 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchChikalthana Aurangabad

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSamil Architects
EngineerSamil Interiors
Chartered AccountantNarendra Navandar & company
PartnerRole in project
Tapadia Constructions Limited-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Apr 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 May 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Oct 2024

Documents filed79

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORA II FORM 1.pdf28 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: FORA II FORM 4 (1).pdf28 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FLORA II FORM 2.pdf28 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form - 4 Architect Certificate (1).pdf26 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form - 4 Architect Certificate.pdf13 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCUPUNCY SERTIFICATE FLORA II.pdf19 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC PLAN FLORA II -1 (2 files merged).pdf19 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dt-31-12-2021_0001.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dt-31-03-2022_0001.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dt-30-06-2022_0001.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dt-30-09-2022_0001.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dt-31-12-2022_0001.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dt-31-03-2023_0001.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dt-30-06-2023_0001.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dt-30-09-2023_0001.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dt-31-12-2023_0001.pdf18 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 Dt-31-03-2024_0001.pdf18 Jun 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate September 2021.pdf1 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate December 2021.pdf1 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate June 2022.pdf1 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate June 2022.pdf1 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: september 22.pdf1 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: december 22.pdf1 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: march 23.pdf1 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: june 23.pdf1 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: september 23.pdf1 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: december 23.pdf1 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: march 24.pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Inventory 30-09-2021.pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Inventory31-12-2021.pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Inventory31-03-2022.pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Inventory30-06-2022.pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Inventor30-09-2022.pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Inventory31-12-2022.pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Inventory 31-03-2023.pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Inventory 30-06-2023.pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Inventory30-09-2023.pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Inventory 31-12-2023.pdf1 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Inventory 31-03-2024.pdf1 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate October 2022.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate January 2023.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate April 2023.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate July 2023.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate October 2023 - converted.pdf17 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate December 2024 - converted.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate October 2022.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate January 2023.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate April2023.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate July 2023.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate October 2023.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate December 2024.pdf17 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Tapadiya Construction LTD - Form - 5 Date 23-12-2023_0001.pdf24 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SEP 21.pdf12 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 DEC 21.pdf12 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JUN 22.pdf12 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SEP 21.pdf12 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 DEC 21.pdf12 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 MAR 22.pdf12 Sep 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JUN 22.pdf12 Sep 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: scan Archi.pdf16 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: scan Eng.pdf16 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A (1).pdf16 Sep 2021
Disclosure of sold/ booked inventoryFile: Declaration of Sold.pdf16 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: Architects Certificate Tapadia Comstruction For CC of Flora 2.pdf15 May 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Tapadia Construction Flora 2.pdf15 May 2021
Declaration in FORM BFile: FORM B Final.pdf30 Apr 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA Cert Flora Phase II.pdf30 Apr 2021
Layout approvalFile: MYSCAN_20210424_0002.PDF26 Apr 2021
Building plan approvalFile: MYSCAN_20210424_0002.PDF26 Apr 2021
Building plan approvalFile: MYSCAN_20210424_0003.PDF26 Apr 2021
PAN CardFile: TCL PAN.pdf26 Apr 2021
Copy of the legal title reportFile: Search Report (3).pdf26 Apr 2021
Details of encumbrancesFile: Encumbrance Declaration.pdf26 Apr 2021
Copy of Layout Approval (in case of layout)File: MYSCAN_20210424_0002.PDF26 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20210424_0002.PDF26 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: MYSCAN_20210424_0003.PDF26 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: Flora Commencement Certificate.pdf26 Apr 2021
Proforma of Allotment letterFile: Allotment Letter Flora Phase II.pdf26 Apr 2021
Proforma of Allotment letterFile: DRAFT FLORA PHASE II APR 2021.pdf26 Apr 2021

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Flora Phase ITisgaon Aurangabad72CompletedJun 2018Late, Jun 2019

How this compares with Aurangabad

14%of Aurangabad projects moved their completion datethis one has not
32%of Aurangabad registrations have lapsed or been cancelledthis one is among them

Computed across the 1,400+ Aurangabad projects on ReraGenie, from their own filings.

Keep Flora Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Tisgaon1,400+ in Aurangabad

Builder: Tapadia Constructions Limited

TAPADIA CONSTRUCTIONS LIMITED has 4 registrations on MahaRERA, including FLORA PHASE I and NATH PARK. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.

Frequently asked questions

What does it mean that Flora Phase II shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Flora Phase II is delayed beyond 31 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Flora Phase II?

The registered promoter entity is Tapadia Constructions Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Flora Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Flora Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Flora Phase II?

The professionals named in the filing: Architect: Samil Architects; Engineer: Samil Interiors; Chartered Accountant: Narendra Navandar & company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Flora Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Flora Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Flora Phase II to a free account