Home / Browse projects / Palghar, Maharashtra / FIA TULIP

Registration lapsed No litigation declared Others project

FIA TULIP

By NIMISH LAXMICHAND PASAD

RG-MH-10212 · RERA P99000013698 · Last updated on MahaRERA portal: 13 Jul 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
20 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 31 documents Report an error

FIA TULIP is a Others project by NIMISH LAXMICHAND PASAD in Palghar, Maharashtra, registered with MahaRERA as P99000013698 on 23 Oct 2017. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameFIA TULIP
  • TypeOthers
  • Location
    • Mahim
    • Palghar
    • 401402
  • Pincode401402
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000013698
  • ReraGenie IDRG-MH-10212

Builder

  • NameNIMISH LAXMICHAND PASAD
  • Entity typeIndividual
  • Named personNIMISH LAXMICHAND PASAD
  • Other registrations14 more →
  • Completed14 of 15
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects8 →

Key dates

34 months past promisethis monthRegisteredOct 2017First promiseDec 2022Revised toDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Oct 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 30 Dec 2022)
  • Buildings2 building records
  • Documents filed31 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
FIA TULIP ANA60000
FIA TULIP A1NA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 13 Jul 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

20 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 0%.

FIA TULIP A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
FIA TULIP A191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 Jul 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed94

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots94
Closed/Covered28
Open Space66
BuildingClosed/CoveredOpen SpaceTotal
FIA TULIP A143347
FIA TULIP A1143347

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area947 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SWATI VINAY SANKHEBorivaliMumbai Suburban

Approvals and building plan

Permissible FSI1333.06
Proposed, not sanctioned1,333 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMAHIM ROAD PALGHAR

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNISHANT P PATIL
EngineerDARSH CONSULT YOGESH VAJA
PartnerRole in project
NIMISH LAXMICHAND PASAD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000016964Dec 2022 → Dec 2023

Reason as filed by the promoterDue to covid.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Sep 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Sep 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Sep 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 10 Aug 2021

Documents filed31

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: FIA TULIP_compressed.pdf13 Jul 2023
Disclosure of sold/ booked inventoryFile: SOLD UNSIOLD_0002.pdf7 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A TULIP.pdf23 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 2A TULIP.pdf23 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_0001.pdf22 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_0001.pdf22 Jun 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 A.pdf22 Jun 2023
Disclosure of sold/ booked inventoryFile: ilovepdf_merged.pdf22 Jun 2023
Certificates of CA (Form 3)File: FIA TULIP-FORM 3 (1).pdf22 Jun 2023
Disclosure of sold/ booked inventoryFile: TULIP_0001.pdf13 Nov 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Tulip Soc Cert.pdf17 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: TULIP ENGG_0001_compressed.pdf14 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC TULIP.pdf10 Aug 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Work Completion Certificate.pdf4 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FIA TULIP.pdf22 Mar 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FIA TULIP-from 05.pdf30 Oct 2019
Certificates of CA (Form 5)File: FORM 5 - Tulip.pdf15 Oct 2018
Proforma of Allotment letterFile: Agrement for sale.pdf1 Oct 2017
Building plan approvalFile: layout plan type A.pdf21 Sep 2017
Building plan approvalFile: layout plan - type a-1.pdf21 Sep 2017
Layout approvalFile: layout plan of tulip.pdf21 Sep 2017
Copy of Layout Approval (in case of layout)File: layout plan of tulip.pdf21 Sep 2017
Building Plan Approval (IOD)File: layout plan type A.pdf21 Sep 2017
Building Plan Approval (IOD)File: layout plan - type a-1.pdf21 Sep 2017
Commencement Certificates / NA Order for plotted developmentFile: tulip-cc.pdf21 Sep 2017
Certificates of CA (Form 3)File: CA CERTIFICATE TULIP.pdf11 Sep 2017
Proforma of Allotment letterFile: FIA TULIP ALLOTMENT LETTER pdf.pdf1 Sep 2017
Copy of the legal title reportFile: Legal Title Report.pdf30 Aug 2017
Declaration in FORM BFile: AFFIDAVIT TULIP (NIMISH SIR).pdf25 Jul 2017
PAN CardFile: NIMISH SIR PAN CARD201.pdf17 Jul 2017
Details of encumbrancesFile: Letter of encumbrance.pdf17 Jul 2017

Promoter's earlier projects8

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

7 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
FIA REGENCY - AMahim Road Palghar West8CompletedJun 2022Feb 2021
FIA EMERALDS NO 826 PLOT NO 43 VILLAGE MAHIM PALGHAR18CompletedDec 2021Jan 2019
FIA IMPERIAMahim Road Palghar West32CompletedApr 2021Nov 2019
FIA PRIDES NO 826 PLOT NO 123 NR SUNDRAM SCHOOL PALGHAR12CompletedDec 2018Dec 2017
FIA DAFFODILSS NO 831-2 PLOT NO 18 NR SUNDARAM SCHOOL PALGHAR24CompletedDec 2018Feb 2018
FIA ORCHIDPLOT NO 120 S N 826 NEAR SUNDARAM SCHOOL PALGHAR26CompletedMar 2016Feb 2016
FIA PRANGANPLOT NO 31 S N 826 NEAR SUNDARAM SCHOOL PALGHAR13CompletedDec 2014Late, Mar 2015
FIA PRATHAMPLOT NO 41 S N 826 NEAR SUNDARAM SCHOOL MAHIM ROAD PALGHAR11CompletedDec 2013Oct 2013

How this compares with Palghar

31%of Palghar projects moved their completion datethis one moved by 12 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep FIA TULIP on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mahim3,200+ in Palghar

2 kmFIA TULIPCompleted 14Lapsed / revoked 11Other 14Dot size: filed unitsN

Filed coordinates, straight-line distance. 39 registered projects within 2 km.

Builder: NIMISH LAXMICHAND PASAD

NIMISH LAXMICHAND PASAD has 15 registrations on MahaRERA, including FIA CONSTRUCTION COMPANY - FIA PRIDE and FIA EMERALD. Its filings disclose 8 earlier MahaRERA projects: declares 7 of 8 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that FIA TULIP shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if FIA TULIP is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of FIA TULIP?

The registered promoter entity is NIMISH LAXMICHAND PASAD, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in FIA TULIP?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for FIA TULIP?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at FIA TULIP?

The professionals named in the filing: Architect: NISHANT P PATIL; Engineer: DARSH CONSULT YOGESH VAJA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in FIA TULIP?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About FIA TULIP. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save FIA TULIP to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.