Red flags

  • Completion date moved by 39 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 39 months from the original
10 of 33Construction stages doneacross 3 buildings; furthest along: Stilt Floor, 85%
84 of 154Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 112 documents Report an error

FATIMA ENCLAVE- A & B is a Others project by RAIS AZIZ QURESHI in Thane, Maharashtra, registered with MahaRERA as P51700019003 on 28 Dec 2018. Possession is promised by 31 Mar 2027. The completion date has moved by 39 months from the original filing. 70 of the 154 units on this registration are recorded sold or booked, and 10 of 33 construction stages are filed complete.

At a glance

Project

  • NameFATIMA ENCLAVE- A & B
  • TypeOthers
  • Location
    • KAUSA MUMBRA
    • THANE
    • Thane (M Corp.)
    • 400612
  • Pincode400612
  • RERA no.P51700019003
  • ReraGenie IDRG-MH-87529

Builder

  • NameRAIS AZIZ QURESHI
  • Entity typeIndividual
  • Other registrations2 more →

Key dates

this monthRegisteredDec 2018First promiseDec 2023Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on28 Dec 2018
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 30 Dec 2023)
  • Buildings3 building records
  • Documents filed112 files

Current status

45%70 of 154 units booked

Figures as on 7 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ROW HOUSENA11101
A WINGNA9721627
B WINGNA212011214126

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 7 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 85%.

ROW HOUSE57%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor85%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.20%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A WING54%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor85%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B WING54%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor85%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 7 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed25

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots25
Closed/Covered2
Open Space23
BuildingClosed/CoveredOpen SpaceTotal
A WING11112
B WING11213

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,471 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on11 Jun 2025

Approvals and building plan

Sanctioning authorityTHANE MUNICIPAL CORPORATION, THANE
Permissible FSI6525.57
Proposed, not sanctioned3,444 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSURME PLAZA MUMBRA

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVINAY PATIL & ASSOCIATES
ArchitectANWAY VINAY PATIL
Chartered AccountantHEENA BASHMAKH
Chartered AccountantKARAN SURENDRA SINGH
Chartered AccountantHEENA NADEEM PAWASKAR
PartnerRole in project
RAIS AZIZ QURESHI-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700018824Dec 2023 → Dec 2024

Reason as filed by the promoterDue to technical issues in environment clearance, permissions and further CC , Construction stopped because of financial issues & Overall industry slowdown during the period. Now construction work started at the site & is in full swing.

EXT51700025710Dec 2023 → Dec 2025

Reason as filed by the promoterDear Sir/Ma’am, I, Mr. Rais Qureshi, hereby declare the following with respect to the project “FATIMA ENCLAVE - A & B” bearing registration number P51700019003 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the full RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying for the Occu

EA07032620135Dec 2023 → Mar 2027

Reason as filed by the promoterThe Promoter respectfully submits that the real estate project could not be completed within the originally registered timeline due to certain unavoidable circumstances that were beyond the reasonable control of the Promoter. The project execution was affected by delays in obtaining certain statutory approvals, procedural compliances with various local authorities, and time taken for regulatory processes required during different stages of construction. Further, the progress of construction activities was impacted due to intermittent shortage of skilled and unskilled labour at the project site

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Dec 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Dec 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Dec 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed112

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 112 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: form 1 a and bw ing.pdf7 Mar 2026
Withdrawal Update Form 1File: form 1 a and bw ing.pdf7 Mar 2026
Withdrawal Update Form 2File: Rera Certificate.pdf7 Mar 2026
Withdrawal Update Form 2File: Rera Certificate.pdf7 Mar 2026
Withdrawal Update Form 3File: form 3 a.pdf7 Mar 2026
Withdrawal Update Form 3File: form 3 a.pdf7 Mar 2026
Form 5 (FY 2018-2019)File: FORM 5.pdf21 Jun 2025
Form 5 (FY 2019-2020)File: form 5 19-20.pdf21 Jun 2025
Form 5 (FY 2020-2021)File: FORM 5.pdf21 Jun 2025
Form 5 (FY 2021-2022)File: Form 5 .pdf21 Jun 2025
Form 5 (FY 2022-2023)File: FORM 5.pdf21 Jun 2025
Form 5 (FY 2023-2024)File: Form 5 New.pdf21 Jun 2025
Form 1File: FORM 1.pdf18 Jun 2025
Form 2File: BLDG B form 2.pdf18 Jun 2025
Form 3File: FORM 3 B WING.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: FATIMA ENCLAVE B-WING.pdf18 Jun 2025
Form 1File: FORM 1 B.pdf18 Jun 2025
Form 2File: FORM 2 B.pdf18 Jun 2025
Form 3File: FORM 3 B WING.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: circular B wing scan.pdf18 Jun 2025
Form 1File: Form1 B.pdf18 Jun 2025
Form 2File: FORM 2 FATIMA BLDG B.pdf18 Jun 2025
Form 3File: FORM 3 B WING.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: B BLDG.pdf18 Jun 2025
Form 1File: FORM 1.pdf18 Jun 2025
Form 2File: FORM 2 B WING SIGNED.pdf18 Jun 2025
Form 3File: FORM 3 B.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: CIRCULAR B BLDG.pdf18 Jun 2025
Form 1File: FORM 1 B.pdf18 Jun 2025
Form 2File: BLDG B form 2.pdf18 Jun 2025
Form 3File: FORM 3 B.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: B WING.pdf18 Jun 2025
Form 1File: form 1.pdf18 Jun 2025
Form 2File: FORM 2 B.pdf18 Jun 2025
Form 3File: FORM 3 B.pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: FATIMA ENCLAVE B WING.pdf18 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Building A.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Building B SIGNED.pdf16 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 B WING SIGNED.pdf16 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A A AND B.pdf16 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A A AND B SIGNED.pdf16 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A A AND B DEC SIGNED.pdf16 Apr 2025
Other - TechnicalFile: CPM F AB.pdf30 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Latest.pdf29 Mar 2025
Certificates of CA (Form 3)File: Form 3 Latest.pdf29 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 19-20.pdf29 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20).pdf29 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21).pdf29 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A 20-21.pdf29 Mar 2025
Disclosure of sold/ booked inventoryFile: Circular 29 Final.pdf29 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf29 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf29 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A 22-23.pdf29 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23).pdf29 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 23-24.pdf29 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24).pdf29 Mar 2025
Declaration in FORM BFile: Form B Fatima.pdf28 Mar 2025
Certificates of CA (Form 3)File: FORM 3 B WING NEW_SIGNED.pdf28 Mar 2025
CERSAI detailsFile: CERSAI_Search_Report_200341887119_For_Asset_Based_Search_25_02_2025_13_48_18_641.pdf28 Feb 2025
Certificates of CA (Form 3)File: FORM 3 B-signed.pdf27 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: B Wing.pdf25 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: C wing.pdf25 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: C wing.pdf25 Feb 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest.pdf24 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 B-Signed.pdf13 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FATIMA BLDG B-signed.pdf13 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A B.pdf13 Feb 2025
Disclosure of sold/ booked inventoryFile: B BLDG.pdf30 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 scan.pdf30 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 B OCT.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 B.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 B.pdf25 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 B WING.pdf25 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A B.pdf25 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 B.pdf7 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a B.pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: BLDG B form 2.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 B.pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: BLDG B form 2.pdf7 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a B.pdf7 Oct 2024

How this compares with Thane

45%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 39 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep FATIMA ENCLAVE- A & B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near THANE7,600+ in Thane

Builder: RAIS AZIZ QURESHI

RAIS AZIZ QURESHI has 3 registrations on MahaRERA, including FATIMA ENCLAVE- A & B and FATIMA ENCLAVE- D WING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if FATIMA ENCLAVE- A & B is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of FATIMA ENCLAVE- A & B?

The registered promoter entity is RAIS AZIZ QURESHI, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in FATIMA ENCLAVE- A & B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for FATIMA ENCLAVE- A & B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at FATIMA ENCLAVE- A & B?

The professionals named in the filing: Architect: VINAY PATIL & ASSOCIATES; Architect: ANWAY VINAY PATIL; Chartered Accountant: HEENA BASHMAKH; Chartered Accountant: KARAN SURENDRA SINGH; Chartered Accountant: HEENA NADEEM PAWASKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in FATIMA ENCLAVE- A & B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About FATIMA ENCLAVE- A & B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save FATIMA ENCLAVE- A & B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.