ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Empress Greens

Registered No litigation declared Residential / Group Housing project

Empress Greens

By Anand Landmarks

RG-MH-53519 · RERA P52100051728 · Last updated on MahaRERA portal: 30 Apr 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 51 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2030Possession promisedmoved 51 months from the original
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 90%
24 of 24Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

Empress Greens is a Residential / Group Housing project by Anand Landmarks in Pune, Maharashtra, registered with MahaRERA as P52100051728 on 27 Jun 2023. Possession is promised by 30 Jun 2030. The completion date has moved by 51 months from the original filing. 0 of the 24 units on this registration are recorded sold or booked, and 0 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameEmpress Greens
  • TypeResidential / Group Housing
  • Location
    • Uday Baug
    • Canal Road
    • wanwadi
    • Haveli
    • Pune
    • 411001
  • Pincode411001
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100051728
  • ReraGenie IDRG-MH-53519

Builder

  • NameAnand Landmarks
  • Entity typePartnership
  • PartnersManoj Ramdayal Asava, Kamlesh Shriniwas Khatod, Ajay Shrikant Mantri, Ramesh Khushalchand Mantri, Vinay Ghanshyamdas Rathi

Key dates

this monthRegisteredJun 2023First promiseMar 2026Revised toJun 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Jun 2023
  • Promised completion30 Jun 2030
  • Revised completionRevised to 30 Jun 2030 (originally 31 Mar 2026)
  • Buildings2 building records
  • Documents filed67 files

Current status

0%0 of 24 units booked
4.5%Work done, per cost certificate

Figures as on 30 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing - ANA7612012
Wing - BNA7612012

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 30 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 90%.

Wing - A8%
ActivityProgress
Excavation90%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing - B8%
ActivityProgress
Excavation90%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed24

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots24
Closed/Covered24
BuildingClosed/CoveredTotal
Wing - A1212
Wing - B1212

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,600 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPUNE MUNICIPAL CORPORATION
Permissible FSI9015.74
Proposed, not sanctioned4,232 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch648, Sri Associates, Kumtekar Road, Sadshiv Peth, Pune 411030
Estimated costRs 28.30 cr
Cost incurredRs 1.28 cr
Work done4.52%
BuildingWingEstimatedIncurred
Wing - ANARs 13.00 crRs 64.00 lakh
Wing - BNARs 13.00 crRs 64.00 lakh
-NARs 2.30 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAvinash Patil
EngineerShravan Shantaram Chauhan
EngineerGajanan Wadkar
Chartered AccountantSunil Shamrao Nimbalkar
Chartered AccountantPushpak B Mundada & Associates
PartnerRole in project
Anand Landmarks-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA23072621851Mar 2026 → Jun 2030

Reason as filed by the promoterDevelopment of the project could not commence due to a pending land dispute and ongoing legal proceedings before the competent authority/court. The litigation has created uncertainty regarding the development rights and possession of the project land. No flats/units have been sold, booked or allotted under the project. The Promoter is actively pursuing resolution of the dispute and intends to commence development immediately upon clearance of the land dispute. Therefore, Extension is sought to enable completion of the project within a revised timeline after resolution of the pending litigation

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000269461laxmikant laddaDevendra Rathi18/09/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Apr 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Apr 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Apr 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2030

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2024-2025)File: Empress Greens_FY 2024-25.pdf30 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A Empress Greens FY 2025-26.pdf30 Apr 2026
Withdrawal Update Form 1File: ARCHITECT CERTIFICATE (Form 1) Anand_Landmarks.pdf21 Apr 2026
Withdrawal Update Form 2File: Engineer Certificate Empress Green Form2.pdf21 Apr 2026
Withdrawal Update Form 3File: CA Certificate Empress Green Form 3.pdf21 Apr 2026
Withdrawal Update Form 1File: Architect Certificate Empress Greens Form 1.pdf20 Jan 2026
Withdrawal Update Form 2File: Engineers Certificate Empress Greens Form 2.pdf20 Jan 2026
Withdrawal Update Form 3File: CA Certificate Empress Greens Form3.pdf20 Jan 2026
Form 5 (FY 2024-2025)File: Empress Greens Audit Report 2024-25.pdf19 Nov 2025
Withdrawal Update Form 1File: Architect Certificate.pdf14 Nov 2025
Withdrawal Update Form 1File: Anand Landmarks Arch Certificate June 2025.pdf14 Nov 2025
Withdrawal Update Form 1File: Architect Certificate.pdf14 Nov 2025
Withdrawal Update Form 2File: Engineer Certificate.pdf14 Nov 2025
Withdrawal Update Form 2File: Engg Certificate June 2025.pdf14 Nov 2025
Withdrawal Update Form 2File: Engineer Certificate.pdf14 Nov 2025
Withdrawal Update Form 3File: CA Certificate.pdf14 Nov 2025
Withdrawal Update Form 3File: CA Certificate (Form 3)_Empress Green stamp and signed.pdf14 Nov 2025
Withdrawal Update Form 3File: CA Certificate.pdf14 Nov 2025
Form 1File: Anand Landmark Arch Certificate Dec 2024.pdf27 May 2025
Form 2File: Anand Landmarks Engg Certificate Dec 2024.pdf27 May 2025
Form 3File: Anand Landmarks CA Certificate Dec 2024.pdf27 May 2025
Disclosure of Sold and Booked InventoryFile: Empress Greens Sold Unsold Inventry Dec 2024.pdf27 May 2025
Form 1File: Anand Landmarks Arch Certificate March 2025.pdf27 May 2025
Form 2File: Anand Landmarks Engg Certificate March 2025.pdf27 May 2025
Form 3File: CA Certificate Anand Landmark March 2025.pdf27 May 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold Inventry Empress Greens March 2025.pdf27 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Anand Landmarks Arch Certificate March 2025.pdf21 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Anand Landmark March 2025.pdf21 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Anand Landmarks Engg Certificate March 2025.pdf21 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventry Empress Greens March 2025.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Anand Landmark Arch Certificate Dec 2024.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Anand Landmarks CA Certificate Dec 2024.pdf4 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Anand Landmarks Engg Certificate Dec 2024.pdf4 Feb 2025
Disclosure of sold/ booked inventoryFile: Empress Greens Sold Unsold Inventry Dec 2024.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Certificate Empress Greens.pdf7 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Empress Greens Engg Certificate.pdf7 Nov 2023
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD INVENTORY.pdf7 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_Empress Greens.pdf7 Nov 2023
Proforma of Agreement for saleFile: FINAL RERA ATS DATE-10-06-2023.pdf10 Jun 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE AJAY MANTRI.pdf24 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE DEVENDRA RATHI.pdf24 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE KAMLESH KHATOD.pdf24 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE MANOJ ASAWA.pdf24 May 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE RAMESH MANTRI.pdf24 May 2023
CERSAI detailsFile: CERSAI_Search_Report_200268411808_For_Asset_Based.pdf15 May 2023
CERSAI detailsFile: DECLARATION OF CERSAI REPORT.pdf15 May 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER ANAND LANDMARKS.pdf15 May 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK ACCOUNT DECLARATION.pdf10 May 2023
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT_ALLOTMENT LETTER.pdf10 May 2023
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT OF AGREEMENT.pdf10 May 2023
Copy of the legal title reportFile: LEGAL TITLE REPORT (FORMAT-A).pdf6 Apr 2023
Details of encumbrances concerned to FinanceFile: ENCUMBARANCE LETTER- FINANCE.pdf6 Apr 2023
Details of encumbrances concerned to FinanceFile: ENCUMBRANCE CERTIFICATE- LEGAL.pdf6 Apr 2023
Details of encumbrances concerned to LegalFile: ENCUMBARANCE LETTER- FINANCE.pdf6 Apr 2023
Details of encumbrances concerned to LegalFile: ENCUMBRANCE CERTIFICATE- LEGAL.pdf6 Apr 2023
Declaration about Commencement CertificateFile: DECLARATION ABOUT Commencement Cert(FORMAT-D).pdf6 Apr 2023
Declaration in FORM BFile: FORM-B (AFFIDAVIT CUM DECLARATON).pdf6 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE.pdf6 Apr 2023
Layout approvalFile: 1-3 Layout_compressed.pdf3 Apr 2023
Building plan approvalFile: 2-3 Wing A and B Floor Plans_compressed.pdf3 Apr 2023
Building plan approvalFile: 3-3 Section and Elevation_compressed.pdf3 Apr 2023
PAN CardFile: PAN ANAND LANDMARKS.pdf3 Apr 2023
Copy of Layout Approval (in case of layout)File: 1-3 Layout_compressed.pdf3 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: 2-3 Wing A and B Floor Plans_compressed.pdf3 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: 3-3 Section and Elevation_compressed.pdf3 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: CC-2493-22 (DATE-22-12-2022).pdf3 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf3 Apr 2023

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 51 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Empress Greens on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Canal Road13,700+ in Pune

2 kmEmpress GreensCompleted 16Lapsed / revoked 6Other 21Dot size: filed unitsN

Filed coordinates, straight-line distance. 43 registered projects within 2 km.

Builder: Anand Landmarks

Anand Landmarks has 1 registration on MahaRERA, including Empress Greens. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Empress Greens is delayed beyond 30 Jun 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Empress Greens?

The registered promoter entity is Anand Landmarks, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Empress Greens?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Empress Greens?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Empress Greens?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Empress Greens?

The professionals named in the filing: Architect: Avinash Patil; Engineer: Shravan Shantaram Chauhan; Engineer: Gajanan Wadkar; Chartered Accountant: Sunil Shamrao Nimbalkar; Chartered Accountant: Pushpak B Mundada & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Empress Greens?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Empress Greens. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Empress Greens to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.