ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / ELEGANT AARIV

Completed No litigation declared Others project

ELEGANT AARIV

By Elegant Builtcon

RG-MH-49598 · RERA P52100050143 · Last updated on MahaRERA portal: 9 Jun 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Internal walls, 85%
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

ELEGANT AARIV is a Others project by Elegant Builtcon in Pune, Maharashtra, registered with MahaRERA as P52100050143 on 20 Mar 2023. The registration is recorded completed; possession was promised by 30 Jun 2025.

At a glance

Project

  • NameELEGANT AARIV
  • TypeOthers
  • Location
    • Behind D Mart Nandan Prospera Road
    • Behind Baner Laxman Nagar
    • Balewadi
    • Haveli
    • Pune
    • 411045
  • Pincode411045
  • RERA no.P52100050143
  • ReraGenie IDRG-MH-49598

Builder

  • NameElegant Builtcon
  • Entity typePartnership
  • PartnersSantosh Basavraj Kuntoji, Nitesh Prabhakar Padale

Key dates

this monthRegisteredMar 2023PromisedJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on20 Mar 2023
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING BNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 9 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 85%.

WING B: 70% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.35%

Progress on shared amenities15

As on 9 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed51

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots51
Closed/Covered10
Open Space41

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area600 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
Mohit Indar ChawlaAndheriMumbai Suburban
Inder Nihalchand ChawlaAndheriMumbai Suburban
Munish Haresh TahilianiMumbai CityMumbai City

Approvals and building plan

Permissible FSI1613.41
Proposed, not sanctioned1,613 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchS No 74/75 Shroff Suyash P K Shroff Road Baner Pune

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPiyush Bakul Parekh
EngineerBalaji Limbaji Waghmare
Chartered AccountantG S Tapdiya and Co
PartnerRole in project
Elegant Builtcon-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Feb 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Feb 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Feb 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 May 2025

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOC REG CERTIFICATE.pdf9 Jun 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PMC Email ScreenShot.pdf8 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Work_opt.pdf24 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate_opt.pdf24 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng Work Certificate_opt.pdf24 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure Sold Unsold Annexure_opt.pdf24 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: APPENDIX H_opt.pdf16 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect.pdf28 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf28 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng.pdf28 Jan 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Disclosure.pdf28 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Sept 24.pdf26 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Sept 24.pdf26 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Sept 24.pdf26 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure Of Sold Unsold Sept 24.pdf26 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Letter.pdf24 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate.pdf24 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure Sold Unsold.pdf24 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf24 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2 A Eng Certificate.pdf24 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2 A Eng Certificate.pdf24 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate.pdf11 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf17 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng Work Certificate.pdf17 Apr 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Disclosure.pdf17 Apr 2024
Building plan approvalFile: scan2240_opt.pdf3 Feb 2024
Building plan approvalFile: scan2241_opt.pdf3 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: scan2240_opt.pdf3 Feb 2024
Building Plan Approval / NA Order for plotted developmentFile: scan2241_opt.pdf3 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: Balewadi Chavla CC.pdf3 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1Arch Dec 23.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng Dec 23.pdf19 Jan 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Dec 23.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Dec 23.pdf19 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (31-12-23).pdf12 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure Sold Booked Inventry.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Letter.pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate_opt.pdf18 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Letter.pdf9 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 ENGINEER'S CERTIFICATE.pdf9 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate_opt.pdf9 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annexure F CA Certificate.pdf6 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Eng.pdf21 Jul 2023
Proforma of Agreement for saleFile: ilovepdf_merged (4).pdf27 Feb 2023
Deviation Report with respect to model copy of AgreementFile: No Deviation Letter for AFS.pdf27 Feb 2023
Copy of the legal title reportFile: Title Certificate_opt.pdf21 Feb 2023
Layout approvalFile: HPSC1106_opt.pdf3 Feb 2023
Copy of Layout Approval (in case of layout)File: HPSC1106_opt.pdf3 Feb 2023
Deviation Report with respect to Allotment letterFile: Elegant Builtcon.pdf3 Feb 2023
CERSAI detailsFile: Encumberance.pdf2 Feb 2023
Proforma of Allotment letterFile: Allottment Letter by Rera flat.pdf31 Jan 2023
Building plan approvalFile: HPSC1106_opt.pdf30 Jan 2023
Building plan approvalFile: HPSC1107_opt.pdf30 Jan 2023
PAN CardFile: Elegant PAN.pdf30 Jan 2023
Details of encumbrances concerned to FinanceFile: Encumberance.pdf30 Jan 2023
Details of encumbrances concerned to LegalFile: Encumberance.pdf30 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSC1106_opt.pdf30 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSC1107_opt.pdf30 Jan 2023
Commencement Certificates / NA Order for plotted developmentFile: C C.pdf30 Jan 2023
Declaration about Commencement CertificateFile: CC Declaration.pdf30 Jan 2023
Declaration in FORM BFile: Developers Form B Notary.pdf30 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect.pdf30 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer.pdf30 Jan 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Declaration.pdf30 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_opt.pdf30 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Arun Declaration.pdf30 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Nitesh Declaration.pdf30 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Santosh Declaration.pdf30 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Account Declaration.pdf30 Jan 2023

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ELEGANT AARIV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Behind Baner Laxman Nagar13,700+ in Pune

Builder: Elegant Builtcon

Elegant Builtcon has 1 registration on MahaRERA, including ELEGANT AARIV. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ELEGANT AARIV is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ELEGANT AARIV?

The registered promoter entity is Elegant Builtcon, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ELEGANT AARIV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ELEGANT AARIV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ELEGANT AARIV?

The professionals named in the filing: Architect: Piyush Bakul Parekh; Engineer: Balaji Limbaji Waghmare; Chartered Accountant: G S Tapdiya and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ELEGANT AARIV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ELEGANT AARIV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ELEGANT AARIV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.