ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Elanor - Tower 1

Registered Litigation declared Residential / Group Housing project

Elanor - Tower 1

By LODHA DEVELOPERS LIMITED

RG-MH-35194 · RERA P51700046312 · Last updated on MahaRERA portal: 29 Sep 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • Completion date moved by 46 months
  • 3 extensions taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Apr 2032Possession promisedmoved 46 months from the original
0 of 11Construction stages donefurthest along: Excavation, 95%
1 of 1Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 135 documents Report an error

Elanor - Tower 1 is a Residential / Group Housing project by LODHA DEVELOPERS LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700046312 on 22 Jun 2022. Possession is promised by 30 Apr 2032. The completion date has moved by 46 months from the original filing. 0 of the 1 unit on this registration is recorded sold or booked, and 0 of 11 construction stages are filed complete.

At a glance

Project

  • NameElanor - Tower 1
  • TypeResidential / Group Housing
  • Location
    • Dhokali
    • Thane (M Corp.)
    • Thane
    • 400607
  • Pincode400607
  • RERA no.P51700046312
  • ReraGenie IDRG-MH-35194

Builder

  • NameLODHA DEVELOPERS LIMITED
  • Entity typeCompany
  • CINL45200MH1995PLC093041
  • GSTIN27AAACL1490J1ZG
  • MdAbhishek Mangalprabhat Lodha
  • Other registrations178 more →
  • Completed16 of 179
  • No longer live3 lapsed, de-registered or revoked
  • Past their filed date3
  • Declared earlier projects22 →

Key dates

this monthRegisteredJun 2022First promiseJun 2028Revised toApr 2032

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Jun 2022
  • Promised completion30 Apr 2032
  • Revised completionRevised to 30 Apr 2032 (originally 30 Jun 2028)
  • Buildings1 building record
  • Documents filed135 files

Current status

0%0 of 1 units booked
3.6%Work done, per cost certificate

Figures as on 29 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A2 Tower - 1NA10101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 95%.

A2 Tower - 1: 12% average across the applicable activities

ActivityProgress
Excavation95%
Basement (if any)0%
Podiums (if any)0%
Plinth35%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area835 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Jun 2025

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI163.54
Proposed, not sanctioned164 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Bombay Hub, Z Wing, Kamla Mill Compound, Senapati Bapat Marg, Lower Parel, Mumbai.400013, Maharashtra
Estimated costRs 151.63 cr
Cost incurredRs 5.45 cr
Work done3.59%
BuildingWingEstimatedIncurred
A2 Tower - 1NARs 98.56 crRs 3.54 cr
-NARs 53.07 crRs 1.91 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVini
ArchitectPradeep Kamble
EngineerSandeep Patil
EngineerMEHUL KAIVANT SHAH
Chartered AccountantChirag Sarvaiya
Chartered AccountantM S K A & Associates
PartnerRole in project
LODHA DEVELOPERS LIMITED-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P51700046312/WarJun 2028 → Apr 2032

Reason as filed by the promoterNA

EXT51700027478Jun 2028 → Dec 2030

Reason as filed by the promoterDue to management decisions and planning, there was a delay in launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As of Now ,at the time of extension request no allotees in this project.

EA12022619815Jun 2028 → Dec 2031

Reason as filed by the promoterDue to management decisions and planning, there was a delay in launching the project even after obtaining the RERA number, which resulted in a late start of construction work. As of Now ,at the time of extension request no allotees in this project.

Litigation declared1

CaseCourtStatus
1737/2016-Ongoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Dec 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2032

Documents filed135

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 135 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: Elanor - Tower 1.pdf29 Sep 2026
Withdrawal Update Form 1File: Form1 - Elanor - Tower 1 - P51700046312.pdf18 Jul 2026
Withdrawal Update Form 2File: Form 2.pdf18 Jul 2026
Withdrawal Update Form 3File: Form 3.pdf18 Jul 2026
Form 2A (FY 2025-2026)File: FORM 2A - ELANOR TOWER-1.pdf30 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf19 May 2026
Withdrawal Update Form 1File: Form 1.pdf19 May 2026
Withdrawal Update Form 2File: Form 2.pdf19 May 2026
Withdrawal Update Form 2File: Form 2.pdf19 May 2026
Withdrawal Update Form 3File: Form 3.pdf19 May 2026
Withdrawal Update Form 3File: Form 3.pdf19 May 2026
Withdrawal Update Form 1File: Form-1 Kolshet A2 T-1 Dec-25.pdf23 Jan 2026
Withdrawal Update Form 2File: Form 2 -Lodha Kolshet (A2) - Tower 1.pdf23 Jan 2026
Withdrawal Update Form 3File: Form 3 -Lodha Kolshet (A2) - Tower 1.pdf23 Jan 2026
Layout approvalFile: Demarcation plan 1.pdf22 Dec 2025
Form 1File: Form 1 (March 23).pdf15 Dec 2025
Form 2File: Form 2 (March 23).pdf15 Dec 2025
Form 3File: Form 3 (March 23).pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold (March 23).pdf15 Dec 2025
Form 1File: Form 1 ( June 23).pdf15 Dec 2025
Form 2File: Form 2 (June 23).pdf15 Dec 2025
Form 3File: Form 3 (June 23).pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold (June 23).pdf15 Dec 2025
Form 1File: Form 1 (Sep 23).pdf15 Dec 2025
Form 2File: Form 2 ( Sep 23).pdf15 Dec 2025
Form 3File: Form 3 ( Sep 23).pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold (Sep 23).pdf15 Dec 2025
Form 1File: Form 1 (Dec 23).pdf15 Dec 2025
Form 2File: Form 2 ( Dec 23).pdf15 Dec 2025
Form 3File: Form 3 ( Dec 23).pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold (Dec 23).pdf15 Dec 2025
Form 1File: Form 1( March 24).pdf15 Dec 2025
Form 2File: Form 2( March 24).pdf15 Dec 2025
Form 3File: Form 3( March 24).pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold ( March 24).pdf15 Dec 2025
Form 1File: Form 1( June 24).pdf15 Dec 2025
Form 2File: Form 2( June 24).pdf15 Dec 2025
Form 3File: Form 3( June 24).pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsol ( June 24).pdf15 Dec 2025
Form 1File: Form 1( Sep 24).pdf15 Dec 2025
Form 2File: Form 2( Sep 24).pdf15 Dec 2025
Form 3File: Form 3 ( Sep 24).pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold (Sep 24).pdf15 Dec 2025
Form 1File: Form 1( Dec 24).pdf15 Dec 2025
Form 2File: Form 2( Dec 24).pdf15 Dec 2025
Form 3File: Form 3( Dec 24).pdf15 Dec 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold (Dec 24.pdf15 Dec 2025
Layout approvalFile: S05_0083_14 - elanor Layout and Bilding plan.pdf30 Nov 2025
Withdrawal Update Form 1File: Form1 - P51700046312 - Lodha Kolshet (A2) - Tower 1.pdf25 Oct 2025
Withdrawal Update Form 2File: Lodha Kolshet (A2) - Tower 1_Form 2.pdf25 Oct 2025
Withdrawal Update Form 3File: Form 3-A2-Tower-1ff.pdf25 Oct 2025
Form 5 (FY 2024-2025)File: Lodha Kolshet A2 - Tower 1.pdf13 Oct 2025
Form 2A (FY 2024-2025)File: Kolshet A2-Tower1.pdf24 Sep 2025
Form 1File: Lodha Kolshet (A2) - Tower 1 (Form 1).pdf18 Jun 2025
Form 2File: Lodha Kolshet (A2) - Tower 1( Form 2 ).pdf18 Jun 2025
Form 3File: Lodha Kolshet (A2) - Tower 1 - ( Form 3).pdf18 Jun 2025
Disclosure of Sold and Booked InventoryFile: Lodha Kolshet (A2) - Tower 1 ( Disclosure of Sold ).pdf18 Jun 2025
Layout approvalFile: Claraint Plot A2-T1_rotated-compressed.pdf3 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: A2 Tower 1 Form 3_compressed.pdf17 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 a2.pdf17 Mar 2025
Other - TechnicalFile: P51700046312_FileName_2.pdf17 Mar 2025
Declaration in FORM BFile: Lodha Kolshet (A2) Tower 1 rs 500.pdf28 Feb 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Tower 1 Format A.pdf28 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2 3 - June22.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2 3 - Sep22.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2 3 - Dec22.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2 3 - March23.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 2 3 - June23.pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 5 Architect’s Certificate of Percentage of Completion of Work (Form 1) (3).pdf4 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 1 2 3 - June23.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 2 3 - Dec24.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 2 3 - Sep24.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 2 3 - June24.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 2 3 - March24.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 2 3 - Dec23.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 2 3 - Sep23.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 1 2 3 - March23.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 1 2 3 - Dec22.pdf4 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 1 2 3 - Sep22.pdf4 Feb 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Liana BP51700033964Dombivali, Thane140Mar 2022CompletedFeb 2026Jun 2024

How this compares with Thane

0%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 46 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Elanor - Tower 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dhokali7,600+ in Thane

Builder: LODHA DEVELOPERS LIMITED

LODHA DEVELOPERS LIMITED has 179 registrations on MahaRERA, including Lodha Adrina and Mhatre Compound. Its filings disclose 22 earlier MahaRERA projects: declares 9 of 10 past projects completed on time. Litigation is declared on 39 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Elanor - Tower 1 is delayed beyond 30 Apr 2032?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Elanor - Tower 1?

The registered promoter entity is LODHA DEVELOPERS LIMITED, a company as per the filing. Its CIN L45200MH1995PLC093041 and GSTIN 27AAACL1490J1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Elanor - Tower 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Elanor - Tower 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Elanor - Tower 1?

The professionals named in the filing: Architect: Vini; Architect: Pradeep Kamble; Engineer: Sandeep Patil; Engineer: MEHUL KAIVANT SHAH; Chartered Accountant: Chirag Sarvaiya; Chartered Accountant: M S K A & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Elanor - Tower 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Elanor - Tower 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Elanor - Tower 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.