EKNATH ENCLAVE
By Gaurivinayak Builders and Developers Pvt Ltd
RG-MH-87234 · RERA P51700010989 · Last updated on MahaRERA portal: 27 Jun 2022
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 58 months past the filed date
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
EKNATH ENCLAVE is a Residential / Group Housing project by Gaurivinayak Builders and Developers Pvt Ltd in Thane, Maharashtra, registered with MahaRERA as P51700010989 on 31 Aug 2017. Possession was promised by 30 Dec 2021 and is now 58 months past that date. The completion date has moved by 24 months from the original filing.
At a glance
Project
- NameEKNATH ENCLAVE
- TypeResidential / Group Housing
- Location
- Tisgaon
- Kalyan
- Thane
- 421306
- Pincode421306
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700010989
- ReraGenie IDRG-MH-87234
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on31 Aug 2017
- Promised completion30 Dec 2021
- Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
- Buildings1 building record
- Documents filed17 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| EKNATH ENCLAVE | NA | 9 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 27 Jun 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 50%.
EKNATH ENCLAVE: 33% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 50% |
| Slabs of Super Structure | 17% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 27 Jun 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 20% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed1
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership7
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SANDEEP EKNATH GAIKWAD | Tisgaon | Thane |
| GAURAV EKNATH GAIKWAD | Tisgaon | Thane |
| Dattu Gajanan Gaikwad | Tisgaon | Thane |
| RAJENDRA RAMDAS GAIKWAD | Tisgaon | Thane |
| Prabhakar Ramdass Gaikwad | Tisgaon | Thane |
| BALAJI RAMDAS GAIKWAD | Tisgaon | Thane |
| JANKIBAI RAMDAS GAIKWAD | Tisgaon | Thane |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DILIP TAMBDAY |
| Engineer | MANOHAR PATIL |
| Partner | Role in project |
|---|---|
| Gauri Vinayak Builder and Developers Pvt Ltd | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe have applied for Extension due to delay on part of K.D.M.C in granting C.C ,resulting in overall delay & Suppliers of Materials(Steel,Cement) & Delay on Part of Labour Contractor for finalization of work & Overall Slowdown in Real Estate Sector
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 8 Aug 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 Aug 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 Aug 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Aug 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed17
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Declaration about Commencement CertificateFile: eknath dec cc.pdf | 27 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A 20.pdf | 27 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A 21.pdf | 27 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: EKNATH ENCLAVE.pdf | 28 Dec 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Ekanth Enclave.pdf | 13 Aug 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate eknat enclve.pdf | 13 Aug 2017 |
| Certificates of CA (Form 3)File: Eknath Ca certificate.pdf | 13 Aug 2017 |
| Proforma of Allotment letterFile: allotment letter.pdf | 13 Aug 2017 |
| Building plan approvalFile: manjuri adesh.pdf | 8 Aug 2017 |
| Layout approvalFile: zplan.PDF | 8 Aug 2017 |
| PAN CardFile: PAN CARD.pdf | 8 Aug 2017 |
| Copy of the legal title reportFile: title certificate.pdf | 8 Aug 2017 |
| Details of encumbrancesFile: Index II Eknath 02.pdf | 8 Aug 2017 |
| Copy of Layout Approval (in case of layout)File: zplan.PDF | 8 Aug 2017 |
| Building Plan Approval (IOD)File: manjuri adesh.pdf | 8 Aug 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: manjuri adesh.pdf | 8 Aug 2017 |
| Declaration in FORM BFile: Form B Eknath Enclave.pdf | 8 Aug 2017 |
Promoter's earlier projects9
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| VIGHNAHARTA CO-OP HSG.SOCIETYp51700055012 | Survey no 11 Hissa no 1, poona link road, Kalyan E, Tisgaon, Kalyan, Thane, 421306, MAHARASHTRA | - | - | Certificate Signed | Dec 2028 | Not due yet |
| ASHTAVINAYAK PARK CO-OP.HSG SOCIETY LTDp51700053952 | Survey no 8 Hissa no 5B, Tisgaon, Kalyan E, Tisgaon, Kalyan, Thane, 421306, MAHARASHTRA | - | - | Certificate Signed | Dec 2028 | Not due yet |
| METRO PRIDEp51700052871 | Gut No 2, KACHORE GAON, KALYAN, KACHORE, Kalyan, Thane, 421301, MAHARASHTRA | - | - | Certificate Signed | Dec 2027 | Not due yet |
| SHUBHAM MONOLITH D WINGp51700049500 | Survey no 30 Hissa no 15A, Survey no 31/1,2, and 19, kalyan E, KALYAN , Tisgaon, Kalyan, Thane, 421306, MAHARASHTRA | - | - | Certificate Signed | Dec 2026 | Not due yet |
| SHUBHAM MONOLITHP51700022647 | TISGAON, Thane | - | Oct 2019 | Certificate Signed | May 2024 | Not delivered |
| KASHISH GALAXY PHASE 1,2 | AT MALUJE KACHORE GAT NO 2 4 7 5 NARAYAN NAGAR KALYAN E | 316 | - | Completed | Dec 2016 | Dec 2016 |
| MITALI HEIGHTS | SURVEY NO 29 HISSA NO 43 16 17 | 117 | - | Completed | Nov 2015 | Nov 2015 |
| SHUBHAM COMPLEX -2 | AT MAUJE TISGAON SURVEY NO 30 HISSA NO 12 13 GAVLI NAGAR KALYAN E | 76 | - | Completed | Mar 2015 | Mar 2015 |
| SOHAN TOWER | SURVEY NO 31 HISSA NO 12 GAVALI NAGAR TISGAON KALYAN E | 94 | - | Completed | Jun 2014 | Jun 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 11 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 17 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep EKNATH ENCLAVE on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Tisgaon7,600+ in Thane
Filed coordinates, straight-line distance. 180 registered projects within 2 km.
Kohinoor Eden
KGI REALTY PRIVATE LIMITED
Olympia City Phase 1
Balaji Rattan Lifespaces
Krishna Trident
Sonawane Infrastructure Private Limited
Rai s Heaven
RAI RESIDENCY Private Limited
Metro Grande Tower C and D
West Pioneer Properties India Pvt Ltd
SEASON SAHARA BUILDING NO 4 AND 5
SAMARTH SAI BUILDERS & DEVELOPERS
See every Thane project, with the district possession charts
Builder: Gaurivinayak Builders and Developers Pvt Ltd
Gaurivinayak Builders and Developers Pvt Ltd has 12 registrations on MahaRERA, including BISTURIBAI TOWER and EKNATH ENCLAVE. Its filings disclose 9 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that EKNATH ENCLAVE shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if EKNATH ENCLAVE is delayed beyond 30 Dec 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of EKNATH ENCLAVE?
The registered promoter entity is Gaurivinayak Builders and Developers Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in EKNATH ENCLAVE?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for EKNATH ENCLAVE?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at EKNATH ENCLAVE?
The professionals named in the filing: Architect: DILIP TAMBDAY; Engineer: MANOHAR PATIL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in EKNATH ENCLAVE?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.