Home / Browse projects / Pune, Maharashtra / EELA Phase-III

Completed No litigation declared Commercial project

EELA Phase-III

By M/s. Siddhashila Developers

RG-MH-14675 · RERA P52100024257 · Last updated on MahaRERA portal: 27 Dec 2023

Source: official MahaRERA filing

Red flags

  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2022Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 54 documents Report an error

EELA Phase-III is a Commercial project by M/s. Siddhashila Developers in Pune, Maharashtra, registered with MahaRERA as P52100024257 on 29 Jan 2020. The registration is recorded completed; possession was promised by 30 Jun 2022.

At a glance

Project

  • NameEELA Phase-III
  • TypeCommercial
  • Location
    • Marunji Punawale
    • Punawale
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100024257
  • ReraGenie IDRG-MH-14675

Builder

  • NameM/s. Siddhashila Developers
  • Entity typePartnership
  • PartnersMr Vilas Chaganlal Rathod, Mr Pritam Vilas Rathod
  • Other registrations2 more →
  • Completed3 of 3

Key dates

this monthRegisteredJan 2020PromisedJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Jan 2020
  • Promised completion30 Jun 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed54 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
THEIA BUSINESS PARKNA100000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

THEIA BUSINESS PARK: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Parking filed106

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots106
Closed/Covered87
Open Space19

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,261 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
Mr. Vilas Chaganlal RathodPune (M Corp.)Pune
Mrs. Shubhada Santosh SubhedarPune (M Corp.)Pune

Approvals and building plan

Permissible FSI4304.95
Proposed, not sanctioned4,305 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBranch Fort Mumbai

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAbhikalpan Architects & Planners
EngineerMr Sudhir K Kulkarni
Chartered AccountantCA Madhusudan Jhanwar
Chartered AccountantV A Dudhedia and Company
PartnerRole in project
M/s. Siddhashila Developers-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018004Jun 2022 → Dec 2023

Reason as filed by the promoter1. We are promoters of Eela Phase III- constructed by us on the land bearing S No. 34/2/1, Punawale. 2. Said project is registered on the Maharera Web Portal, under ReRA Act 2016 and rules made thereunder as on 08/09/2021 and is bearing project registration no. as (P52100024257). 3. That said 1st registration was valid from 29/01/2020 till 30/06/2022. 4. Thereafter due to Covid, ReRA registration of said project was further extended till 31/12/2022. 5. We have received completion certificate in respect of said Project as on 29/03/2023 and as such we were in the process of taking further extens

EXT52100012123Jun 2022 → Dec 2022

Reason as filed by the promoterWe could not be able to complete the remaining floors of the said project in time due to following reasons. (i) Covid 19 pandemic has impacted all sectors of country including Real Estates from time to time. Covid 19 has affected the Sales in real estate sector immensely. (ii) All the units in the said commercial building are built on the basis of requirements of prospective client/purchaser/s. presently all the Units in 2nd floor and above are unsold and in the bare shell form. On the basis of requirements of prospective client/purchaser/s same shall be converted to the furnished product. (ii

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Nov 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jun 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Jan 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 31 Mar 2023

Documents filed54

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form-4.pdf27 Dec 2023
Disclosure of sold/ booked inventoryFile: Form-3-18-12-2023.pdf18 Dec 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked.pdf18 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3-18-12-2023.pdf18 Dec 2023
Disclosure of sold/ booked inventoryFile: 20231211071111.pdf11 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 20231209053916.pdf9 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 20231209053646.pdf9 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form - 5 Eela Ph-III.pdf5 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: EX NA Order Finel.pdf28 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eela Phase-III (3).pdf7 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Eela Phase-III.pdf7 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Eela Phase-III 4.pdf7 Apr 2023
Disclosure of sold/ booked inventoryFile: Theia Sales Declaration-06-04-2023.pdf7 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Eela Phase-III (3).pdf7 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion - I Buildng (FINAL).pdf31 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT EELA PHASE-III 6-JAN-2023.pdf1 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Eela Phase-III.pdf30 Jan 2023
Disclosure of sold/ booked inventoryFile: Theia Eela Ph-III.pdf18 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1418-RERA-PH-III CERTIFICATE-280322.pdf6 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1418-RERA-PH-III CERTIFICATE-040722 (1).PDF6 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1418-RERA-PH-III CERTIFICATE-300922.pdf6 Jan 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Eela Phase-III.pdf6 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eela Phase-III From-2.pdf15 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Certificate.pdf15 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form-3 Eela Ph-III.pdf11 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Eela Phase-III.pdf11 Oct 2022
CERSAI detailsFile: SD CERSAI_Search_Report.pdf1 Jul 2022
Layout approvalFile: Sheet No 1_compressed.pdf28 Jun 2022
Copy of Layout Approval (in case of layout)File: Sheet No 1_compressed.pdf28 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: CC 11-02-2022.pdf28 Jun 2022
Proforma of Allotment letterFile: Revised_Theia Business Park Agreement_Draft before Completion with both logo.pdf27 Jun 2022
Proforma of Allotment letterFile: Revised_Theia Business Park Agreement draft after completion with both logo.pdf27 Jun 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion - I Buildng (Part).pdf27 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SCAN_20211223_184009516.pdf23 Dec 2021
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF Eela PH-III_compressed.pdf8 Oct 2021
Declaration about Commencement CertificateFile: SCAN_20210813_124449710.pdf13 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A PH-3 June-21.pdf13 Aug 2021
Disclosure of sold/ booked inventoryFile: Sales Diclaration - I Building.pdf13 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - Phase III 2019-20.pdf6 Aug 2021
Building plan approvalFile: Building Plan Approval 22-3-19.pdf22 Jan 2020
Building Plan Approval / NA Order for plotted developmentFile: Building Plan Approval 22-3-19.pdf22 Jan 2020
Declaration in FORM BFile: Form B of Pritam Rathod_rotated_compressed.pdf22 Jan 2020
Declaration in FORM BFile: Form B of Shubhada Subhedar_rotated_compressed.pdf22 Jan 2020
Declaration in FORM BFile: Form B of Vilas Rahod_rotated_compressed.pdf22 Jan 2020
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1418-RERA-PH-III CERTIFICATE-110120.PDF22 Jan 2020
Proforma of Allotment letterFile: RERA Agreement Draft Theia Commercial 18-10-2019.pdf22 Jan 2020
Layout approvalFile: Building Plan Approval 22-3-19.pdf26 Dec 2019
Copy of Layout Approval (in case of layout)File: Building Plan Approval 22-3-19.pdf26 Dec 2019
Commencement Certificates / NA Order for plotted developmentFile: 22-03-19 CC_compressed.pdf25 Dec 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III CA Certificate SD_compressed.pdf20 Dec 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-II Engineer-PH-III CERTIFICATE-281119_compressed.pdf19 Dec 2019
PAN CardFile: PAN_ Siddhashila Developers ACKFS6676C.pdf22 Nov 2019
Copy of the legal title reportFile: Title Report 19-10-2019_compressed.pdf22 Nov 2019
Details of encumbrancesFile: Mortgage Deed 2018-3.pdf22 Nov 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EELA Phase-III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Punawale13,700+ in Pune

2 kmEELA Phase-IIICompleted 115Lapsed / revoked 117Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 268 registered projects within 2 km.

Builder: M/s. Siddhashila Developers

M/s. Siddhashila Developers has 3 registrations on MahaRERA, including EELA Phase-I and EELA Phase-II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if EELA Phase-III is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EELA Phase-III?

The registered promoter entity is M/s. Siddhashila Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EELA Phase-III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for EELA Phase-III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EELA Phase-III?

The professionals named in the filing: Architect: Abhikalpan Architects & Planners; Engineer: Mr Sudhir K Kulkarni; Chartered Accountant: CA Madhusudan Jhanwar; Chartered Accountant: V A Dudhedia and Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EELA Phase-III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EELA Phase-III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EELA Phase-III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.