Home / Browse projects / Thane, Maharashtra / EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD
EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD
RG-MH-64409 · RERA P51700016111 · Last updated on MahaRERA portal: 6 Nov 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 31 months past the filed date
- 4 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD is a Others project by Sripad Vallabh Ventures in Thane, Maharashtra, registered with MahaRERA as P51700016111 on 17 Apr 2018. Possession was promised by 29 Mar 2024 and is now 31 months past that date. The completion date has moved by 12 months from the original filing. 4 complaints are on record with the regulator.
At a glance
Project
- NameEASHAN DATTAPRASAD CO OP HSG SOCIETY LTD
- TypeOthers
- Location
- GHANTALI ROAD
- NAUPADA
- Thane (M Corp.)
- Thane
- 400602
- Pincode400602
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700016111
- ReraGenie IDRG-MH-64409
Builder
- NameSripad Vallabh Ventures
- Entity typePartnership
- PartnersPrafulla Shashikant Vaidya, Prashant Sudhir Khadilkar
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on17 Apr 2018
- Promised completion29 Mar 2024
- Revised completionRevised to 29 Mar 2024 (originally 30 Mar 2023)
- Buildings1 building record
- Documents filed98 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| EASHAN CO OP HSG SOCIETY LTD PROPOSED | NA | 17 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
EASHAN CO OP HSG SOCIETY LTD PROPOSED: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 6 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed16
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DESIGN CONSORTIUM ARCHITECTS I PVT LTD |
| Engineer | AJAY MAHALE |
| Partner | Role in project |
|---|---|
| Sripad Vallabh Ventures | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. At the outset, we would like to apprise you about the huge impact of the ongoing Covid 19 pandemic on the real estate industry. Most of our prospective customers are from Thane and Mumbai and continuous lockdown restrictions had impacted our sales and construction activity due to lack of mobility for customers. Further, non-availability or scarce labour was another constraint we were facing due to the pandemic. Now that the Covid wave has subsided, still the impact of it does have a lasting impact of the project cycle. 2. The captioned project comprises of 1 building which is complete to th
Complaints filed with MahaRERA4
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000398012 | JITENDRA RAGHUVANSHI | M/s Sripad Vallabh Ventures | 29/10/2023 |
| CC12503394 | VINAYAK BHISE | Sripad Vallabh Ventures | 22/09/2025 |
| CC12503395 | Pravin Pandit | Sripad Vallabh Ventures | 22/09/2025 |
| CC12503396 | Onkar Ghaisas | Sripad Vallabh Ventures | 22/09/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Feb 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Apr 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 20 Apr 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 20 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 2 Mar 2024
Documents filed98
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 98 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: Form_4.pdf | 6 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form_5.pdf | 15 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate_for_completion.pdf | 4 Mar 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_CERTIFICATE_I.pdf | 2 Mar 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC_CERTIFICATE_II.pdf | 2 Mar 2024 |
| Certificates of CA (Form 3)File: CA_Certificate_Form_3.pdf | 9 Feb 2024 |
| Certificates of CA (Form 3)File: CA_Certificate_Form_3.pdf | 9 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate.pdf | 6 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate.pdf | 6 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate.pdf | 6 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate.pdf | 6 Feb 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineer_Quality_Assurance_Certificate.pdf | 6 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate.pdf | 13 Oct 2023 |
| Certificates of CA (Form 3)File: CA-Certificate.pdf | 29 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate.pdf | 9 Aug 2023 |
| Certificates of CA (Form 3)File: CA_Certificate.pdf | 9 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate.pdf | 11 May 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: 01 - Sripad Vallabh Ventues - Form - 05 - FY - 2018-19.pdf | 27 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 02 - Sripad Vallabh Ventures - FORM - 05 - FY - 2019-20.pdf | 27 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 03 - Sripad Vallabh Ventures - FORM - 05 - FY - 2020-21.pdf | 27 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 04 - Sripad Vallabh Ventures - FORM - 05 - FY - 2021-22.pdf | 27 Apr 2023 |
| Declaration about Commencement CertificateFile: Sripad Vallabh Ventures - Declaration about CC.pdf | 26 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Sripad Vallabh Ventures - Form 2A.pdf | 26 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Sripad Vallabh Ventures - Declaration about Sold - Booked Inven.pdf | 26 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 05_FY_ 2020_21.pdf | 23 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM_05_FY_2021_22.pdf | 23 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate.pdf | 21 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate as on 31032022.pdf | 14 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate as on 30092022.pdf | 14 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA CA Certificate as on 31122022.pdf | 14 Feb 2023 |
| Certificates of CA (Form 3)File: RERA CA Certificate as on 31032022.pdf | 14 Feb 2023 |
| Certificates of CA (Form 3)File: RERA CA Certificate as on 30092022.pdf | 14 Feb 2023 |
| Certificates of CA (Form 3)File: RERA CA Certificate as on 31122022.pdf | 14 Feb 2023 |
| Certificates of CA (Form 3)File: CA_Certificate_ Form_3.pdf | 8 Feb 2023 |
| Certificates of CA (Form 3)File: CA_Certificate_Form_3.pdf | 8 Feb 2023 |
| Certificates of CA (Form 3)File: CA_Certificate_Form_3.pdf | 8 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate.pdf | 18 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate.pdf | 18 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Architect_Form_2A.pdf | 21 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate.pdf | 18 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate.pdf | 18 Oct 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate.pdf | 29 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate.pdf | 29 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate.pdf | 29 Jul 2022 |
| Building plan approvalFile: All_Floor_Compact_Plan.pdf | 20 Apr 2022 |
| Building plan approvalFile: Ground_1st_Flr_Plan.pdf | 20 Apr 2022 |
| Building plan approvalFile: Below_Gr_Flr,2nd,3rd,4th_to_6th,8th_to_11th_13th_to_15th.pdf | 20 Apr 2022 |
| Building plan approvalFile: 7th_12th_Refugee_Flr_16th_Flr_Terrace_Flr_Plan.pdf | 20 Apr 2022 |
| Building Plan Approval (IOD)File: All_Floor_Compact_Plan.pdf | 20 Apr 2022 |
| Building Plan Approval (IOD)File: Ground_1st_Flr_Plan.pdf | 20 Apr 2022 |
| Building Plan Approval (IOD)File: Below_Gr_Flr,2nd,3rd,4th_to_6th,8th_to_11th_13th_to_15th.pdf | 20 Apr 2022 |
| Building Plan Approval (IOD)File: 7th_12th_Refugee_Flr_16th_Flr_Terrace_Flr_Plan.pdf | 20 Apr 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: EASHAN_Project_Final_CC.pdf | 20 Apr 2022 |
| Copy of the legal title reportFile: Title_Report.pdf | 10 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate.pdf | 10 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate as on 31 12 2021.pdf | 10 Feb 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate.pdf | 10 Feb 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate as on 31 12 2021.pdf | 10 Feb 2022 |
| Certificates of CA (Form 3)File: Certificate_of_CA.pdf | 10 Feb 2022 |
| Certificates of CA (Form 3)File: RERA CA Certificate as on 31 12 2021 NEW.pdf | 10 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Certificate_30062021.pdf | 22 Jul 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Certificate_30062021.pdf | 22 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form - 5 - CA Certificate 2018-19.pdf | 22 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form - 5 CA Cerificate 2019-20.pdf | 22 Jul 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: 02 Revised New CC Dated 24 01 2020.pdf | 19 Jan 2021 |
| Building plan approvalFile: New CC Plan - 1.pdf | 18 Jan 2021 |
| Building plan approvalFile: New CC Plan - 2.pdf | 18 Jan 2021 |
| Building plan approvalFile: New CC Plan - 3.pdf | 18 Jan 2021 |
| Building plan approvalFile: New CC Plan - 4.pdf | 18 Jan 2021 |
| Building Plan Approval (IOD)File: New CC Plan - 1.pdf | 18 Jan 2021 |
| Building Plan Approval (IOD)File: New CC Plan - 2.pdf | 18 Jan 2021 |
| Building Plan Approval (IOD)File: New CC Plan - 3.pdf | 18 Jan 2021 |
| Building Plan Approval (IOD)File: New CC Plan - 4.pdf | 18 Jan 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Revised Architect Certificate as on 30092020.pdf | 16 Jan 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Revised Engineer Certificate 30092020.pdf | 16 Jan 2021 |
| Certificates of CA (Form 3)File: SripadVallabh 31 03 2020.pdf | 16 Jan 2021 |
| Certificates of CA (Form 3)File: SripadVallabh 30 09 2020.pdf | 16 Jan 2021 |
| Certificates of CA (Form 3)File: SripadVallabh 30 09 2020.pdf | 16 Jan 2021 |
| Certificates of CA (Form 3)File: SripadVallabh 30 06 2020.pdf | 16 Jan 2021 |
| Layout approvalFile: FINAL LAYOUT DP REMARKS.pdf | 14 Apr 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 98 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NAUPADA7,600+ in Thane
Filed coordinates, straight-line distance. 323 registered projects within 2 km.
Stellar
Trimity Realty LLP
SAMRIN HERITAGE
SAMRIN INFRA PRIVATE LIMITED
L&T Realty Vayam Tower 3
ELANTE PROPERTIES PRIVATE LIMITED, J S K E
L&T Realty Vayam Tower 4
ELANTE PROPERTIES PRIVATE LIMITED, J S K E
Codename LIT Tower A
Camrose Realtors Private Limited
Codename LIT Tower B
Camrose Realtors Private Limited
See every Thane project, with the district possession charts
Builder: Sripad Vallabh Ventures
Sripad Vallabh Ventures has 1 registration on MahaRERA, including EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD is delayed beyond 29 Mar 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD?
The registered promoter entity is Sripad Vallabh Ventures, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD?
The professionals named in the filing: Architect: DESIGN CONSORTIUM ARCHITECTS I PVT LTD; Engineer: AJAY MAHALE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in EASHAN DATTAPRASAD CO OP HSG SOCIETY LTD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback