ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / EARTH 1 BY VTP LUXE PHASE 2

Registered Litigation declared Residential / Group Housing project

EARTH 1 BY VTP LUXE PHASE 2

By MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.

RG-MH-90396 · RERA P52100051025 · Last updated on MahaRERA portal: 19 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 3 complaints at MahaRERA
  • Rs 375.00 crore secured on the land, in favour of PIRAMAL FIANANCE LIMITED

Clear

  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Oct 2028Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 34%
33 of 280Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 119 documents Report an error

EARTH 1 BY VTP LUXE PHASE 2 is a Residential / Group Housing project by MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD. in Pune, Maharashtra, registered with MahaRERA as P52100051025 on 22 May 2023. Possession is promised by 27 Oct 2028. 247 of the 280 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameEARTH 1 BY VTP LUXE PHASE 2
  • TypeResidential / Group Housing
  • Location
    • Mahalunge Maan Road
    • Mahalunge
    • Mulshi
    • Pune
    • 411045
  • Pincode411045
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100051025
  • ReraGenie IDRG-MH-90396

Builder

  • NameMAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.
  • Entity typeCompany
  • DirectorsAYUSH JHANWAR, SUMIT RAMESH DIWANE
  • Other registrations2 more →

Key dates

this monthRegisteredMay 2023PromisedOct 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 May 2023
  • Promised completion27 Oct 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed119 files

Current status

88%247 of 280 units booked
10.7%Work done, per cost certificate

Figures as on 19 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower - 7NA38352800280

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 34%.

Tower - 7: 40% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure34%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises9%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 19 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed16

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots16
Closed/Covered1
Open Space15

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,554 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofPIRAMAL FIANANCE LIMITED
Secured amountRs 375.00 crore
CERSAI search filedYes
Declared on21 Aug 2025

Approvals and building plan

Sanctioning authorityPUNE METROPOLITAN REGIONAL DEVELOPMENT AUTHORITY
Permissible FSI33364.67
Proposed, not sanctioned33,365 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBhandarkar Road, Pune
Estimated costRs 137.82 cr
Cost incurredRs 14.69 cr
Work done10.66%
BuildingWingEstimatedIncurred
Tower - 7NARs 124.04 crRs 13.78 cr
-NARs 13.78 crRs 90.56 lakh

Certifying professionals and partners12

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectANA CONSORTIUM PVT LTD
ArchitectVKe
ArchitectVk arch
EngineerPRITEE MAHADIK
EngineerDeepak Kamat
EngineerRajesh Maslekar
EngineerDeepak Kulkarni
EngineerVINAY ABHYANKAR
Chartered AccountantSAC & Co LLP
Chartered AccountantV. T & ASSOCIATES
Chartered AccountantV. T AND ASSOCIATES
Chartered AccountantPriyanka Chordiya & Associates
PartnerRole in project
MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.-

Litigation declared2

CaseCourtStatus
1387/2012Civil Judge Senior DivisionOngoing
1387/20124th ADDITIONAL JUD SMALL CAUSES CT AND JT. CJSD JMFC PUNEOngoing

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12502556Ishwarlal JadhavMAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.25/07/2025
CC12503492MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.MRS SANGITA SANTOSH NIMBALKAR (ALLOTTEE)30/09/2025
CC12603567MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.ABHISHEK SHARMA (Allottee)09/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Dec 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 27 Oct 2028

Documents filed119

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: VTP Earth 1 FORM RERA 2A Phase 2.pdf19 Jun 2026
Withdrawal Update Form 1File: FORM-1 EARTH PHASE 2.pdf14 Apr 2026
Withdrawal Update Form 2File: FORM-2 EARTH 1 BY VTP LUXE PHASE 2.pdf14 Apr 2026
Withdrawal Update Form 3File: FORM 3 EARTH1 PHASE 2.pdf14 Apr 2026
Withdrawal Update Form 1File: RERA FORM-1 EARTH1 PHASE 2.pdf20 Jan 2026
Withdrawal Update Form 2File: Earth1 Phase 2 Form 2.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 Earth 1 by VTP Luxe Phase 2_11zon.pdf20 Jan 2026
Withdrawal Update Form 1File: FORM 1 EARTH1 PHASE 2.pdf16 Oct 2025
Withdrawal Update Form 2File: FORM 2- EARTH 1 PHASE 2.pdf16 Oct 2025
Withdrawal Update Form 3File: FORM 3 EARTH 1 PHASE 2.pdf16 Oct 2025
Form 5 (FY 2024-2025)File: FORM 5- EARTH 1 PHASE 2.pdf8 Sep 2025
Form 2A (FY 2024-2025)File: FORM 2A EARTH 1 BY VTP LUXE PHASE 2.pdf24 Jun 2025
Form 1File: FORM 1 EARTH 1 PHASE 2 31032025.pdf22 May 2025
Form 2File: Form 2 Earth 1 PHase 2.pdf22 May 2025
Form 3File: FORM 3 EARTH 1 PHASE 2 31032025_compressed.pdf22 May 2025
Disclosure of Sold and Booked InventoryFile: EARTH 1 PH2 31032025.pdf22 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH 1 PHASE 2.pdf19 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Earth 1 PHase 2.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EARTH 1 PHASE 2 31032025.pdf12 Apr 2025
Disclosure of sold/ booked inventoryFile: EARTH 1 PH2 31032025.pdf4 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH 1 PH 2 31122024.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EARTH 1 PHASE 2.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH 1 PH 2 31122024.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EARTH 1 PHASE 2.pdf16 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH 1 PH 2 31122024.pdf16 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EARTH 1 PHASE 2.pdf16 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EARTH 1 PHASE 2 31122024.pdf10 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EARTH 1 PHASE 2 31122024.pdf10 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EARTH 1 PHASE 2 31122024.pdf10 Jan 2025
Disclosure of sold/ booked inventoryFile: EARTH 1 PHASE 2 31122024.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: EARTH 1 PHASE 2 31122024.pdf9 Jan 2025
Disclosure of sold/ booked inventoryFile: EARTH 1 PHASE 2 31122024.pdf9 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH 1 PHASE 2 30092024.pdf6 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH 1 PHASE 2 30092024.pdf6 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH 1 PHASE 2 30092024.pdf6 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EARTH 1 PH 2 30092024.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH 1PHASE 2_compressed.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EARTH 1 PH 2 30092024.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH 1PHASE 2_compressed.pdf18 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH 1PHASE 2_compressed.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EARTH 1 PH 2 30092024.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EARTH 1 PH 2 30092024.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EARTH 1 PH 2 30092024.pdf16 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EARTH 1 PH 2 30092024.pdf16 Oct 2024
Disclosure of sold/ booked inventoryFile: EARTH1 PHASE2 30092024.pdf10 Oct 2024
Disclosure of sold/ booked inventoryFile: EARTH1 PHASE2 30092024.pdf10 Oct 2024
Disclosure of sold/ booked inventoryFile: EARTH1 PHASE2 30092024.pdf10 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 3 Earth 1 By Vtp Luxe Phase 2 31-03-2024_compressed.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 3 Earth 1 By Vtp Luxe Phase 2 31-03-2024_compressed.pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 3 Earth 1 By Vtp Luxe Phase 2 31-03-2024_compressed.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EARTH 1 PHASE 2 30062024.pdf27 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EARTH 1 PH 2 05072024.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EARTH 1 PHASE 2 05072024.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH1 PHASE 2 30062024.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: EARTH 1 PHASE 2 30062024.pdf8 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 310524 Earth 1-P 2.pdf6 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3-EARTH-1-PHASE-2.pdf6 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2- EARTH1 PHASE2- 30062024.pdf5 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: EARTH 1 PHASE 2.pdf16 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EARTH 1 PHASE 2 31032024.pdf6 May 2024
Disclosure of sold/ booked inventoryFile: INVENTORY EARTH 1 PHASE 2 31032024.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EARTH 1 PHASE 2 31032024.pdf30 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH 1 PHASE 2 31032024.pdf30 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 EARTH 1 PHASE 2 31122023.pdf8 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 EARTH 1 PHASE 2 31122023.pdf27 Feb 2024
Disclosure of sold/ booked inventoryFile: INVENTORY EARTH 1 PHASE 2 31122023.pdf9 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 EARTH 1 PHASE 2 31122023.pdf22 Jan 2024
Building plan approvalFile: Tower 7 Refuge area and terrace floor plan.pdf9 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: Tower 7 Refuge area and terrace floor plan.pdf9 Dec 2023
Declaration about Commencement CertificateFile: EARTH 1 PHASE 2 CC DECLARATION.pdf9 Dec 2023
Proforma of Agreement for saleFile: Amended AFS_Earth 1 by VTP Luxe Phase 2.pdf9 Dec 2023
Building plan approvalFile: Tower 7 First Floor plan.pdf2 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: Tower 7 First Floor plan.pdf2 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Phase-2.pdf2 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Earth 1 by Vtp Luxe phase 2_ 27-10-2023_compressed.pdf2 Nov 2023
Layout approvalFile: EARTH ONE BY VTP LUXE PHASE 2.pdf31 Oct 2023
Details of encumbrances concerned to FinanceFile: FE - Earth 1 Ph 2 - 30102023.pdf31 Oct 2023
Details of encumbrances concerned to LegalFile: FE - Earth 1 Ph 2 - 30102023.pdf31 Oct 2023
Copy of Layout Approval (in case of layout)File: EARTH ONE BY VTP LUXE PHASE 2.pdf31 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: 231020 - CC_compressed.pdf31 Oct 2023

How this compares with Pune

88%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep EARTH 1 BY VTP LUXE PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mahalunge13,700+ in Pune

2 kmEARTH 1 BY VTP LUXE PHASCompleted 24Lapsed / revoked 10Other 37Dot size: filed unitsN

Filed coordinates, straight-line distance. 71 registered projects within 2 km.

Builder: MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD.

MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD. has 3 registrations on MahaRERA, including EARTH 1 BY VTP LUXE PHASE 1 and EARTH 1 BY VTP LUXE PHASE 2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if EARTH 1 BY VTP LUXE PHASE 2 is delayed beyond 27 Oct 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of EARTH 1 BY VTP LUXE PHASE 2?

The registered promoter entity is MAHALUNGE REAL ESTATE DEVELOPERS PVT. LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in EARTH 1 BY VTP LUXE PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against EARTH 1 BY VTP LUXE PHASE 2?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for EARTH 1 BY VTP LUXE PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at EARTH 1 BY VTP LUXE PHASE 2?

The professionals named in the filing: Architect: ANA CONSORTIUM PVT LTD; Architect: VKe; Architect: Vk arch; Engineer: PRITEE MAHADIK; Engineer: Deepak Kamat; Engineer: Rajesh Maslekar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in EARTH 1 BY VTP LUXE PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About EARTH 1 BY VTP LUXE PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save EARTH 1 BY VTP LUXE PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.