Home / Browse projects / DUDHWALA COMPLEX-PHASE 2

Completed No litigation declared Residential / Group Housing project

DUDHWALA COMPLEX-PHASE 2

By ROCK CORNER DEVELOPER PRIVATE LIMITED

RG-MH-25841 · RERA P51900003621 · Last updated on MahaRERA portal: 10 May 2024

Source: official MahaRERA filing

Red flags

  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Jun 2022Possession promisedregistration recorded completed
15 of 22Construction stages doneacross 2 buildings; furthest along: Podiums (if any), 98%
0Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

DUDHWALA COMPLEX-PHASE 2 is a Residential / Group Housing project by ROCK CORNER DEVELOPER PRIVATE LIMITED in BOMBAY CENTRAL, 400008, registered with MahaRERA as P51900003621 on 6 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2022. The completion date has moved by 18 months from the original filing.

At a glance

Project

  • NameDUDHWALA COMPLEX-PHASE 2
  • TypeResidential / Group Housing
  • Location
    • BELASIS ROAD
    • BOMBAY CENTRAL
    • 400008
  • Pincode400008
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900003621
  • ReraGenie IDRG-MH-25841

Builder

  • NameROCK CORNER DEVELOPER PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorIMTIYAZ PATEL

Key dates

this monthRegisteredAug 2017First promiseDec 2020Revised toJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on6 Aug 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 31 Dec 2020)
  • Buildings2 building records
  • Documents filed62 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ID ORIGINSNA190000
B WINGNA180000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 10 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Podiums (if any), at 98%.

ID ORIGINS100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B WING98%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)98%
Plinth100%
Stilt Floor98%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises97%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.96%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.92%

Progress on shared amenities15

As on 10 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes50%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed71

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots71
Closed/Covered20
Open Space51
BuildingClosed/CoveredOpen SpaceTotal
ID ORIGINS114556
B WING9615

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area9,378 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI8388.0
Proposed, not sanctioned7,202 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDR NAIR ROAD OPP MUMBAI CENTRAL STATION MUMBAI 400 008

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectD. H. PATEL
ArchitectHiren S. Thakkar of M/s H S Thakkar & Associates
EngineerMahimtura Consultants Pvt Ltd
PartnerRole in project
ROCK CORNER DEVELOPER PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900005803Dec 2020 → Dec 2021

Reason as filed by the promoterThe Project is delayed for reasons beyond our control

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Mar 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Mar 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_ROCK CORNER_ upto 31-12-2022.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_ROCK CORNER _upto 31-03-2023.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_ROCK CORNER_upto 30-06-2023.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_ROCK CORNER_upto 30-09-2023.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_Rock upto 31-03-2024pdf.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Form 2A.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Form 2A.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Rock Corner_ upto 31-12-2022.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Rock Corner_ upto 31-03-2023.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Rock_ upto 30-09-2023.pdf10 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer_Rock_ upto 30-06-20231.pdf10 May 2024
Certificates of CA (Form 3)File: CA_ROCK_upto 30-06-2023.pdf10 May 2024
Certificates of CA (Form 3)File: CA_ROCK_upto 30-09-2023.pdf10 May 2024
Certificates of CA (Form 3)File: CA_ROCK_upto 31-12-2023.pdf10 May 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_DWG30092022.pdf8 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ROCK Rera Upto Sept 2022.pdf8 May 2023
Form 2AFile: Eng Certificate_Dudhwala_Complex_2021 (1).pdf12 Dec 2022
Form 2AFile: Eng Certificate_Dudhwala_Complex_2022 (1).pdf12 Dec 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Rock Corner - Form 5.pdf28 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ROCKARCH2812020.pdf21 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: rock_arch_10420_compressed.pdf21 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rock_arch_11121_compressed.pdf21 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ROCKENGG_28012020.pdf21 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: rock_engg_100420_compressed.pdf21 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rock_engg_11121_compressed (1).pdf21 Jan 2021
Certificates of CA (Form 3)File: ROCK30619.pdf21 Jul 2020
Certificates of CA (Form 3)File: ROCK30919.pdf21 Jul 2020
Proforma of Allotment letterFile: Flat Sale Agreement.pdf11 Mar 2020
Building plan approvalFile: Annexure- A - Amended approval letter.pdf3 Mar 2020
Building Plan Approval (IOD)File: Annexure- A - Amended approval letter.pdf3 Mar 2020
Commencement Certificates / NA Order for plotted developmentFile: Annexure -B Further CC.pdf3 Mar 2020
Form 2AFile: ENGG_ROCK_RERA_NEW.pdf29 Jan 2020
Certificates of CA (Form 3)File: rera_acct_rock_form3.pdf20 Nov 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: rock form 5.pdf6 Nov 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ROCK_eNGG_Sept2019-compressed.pdf4 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RCDPL_Architect_Certificate_Dt_11-10-2019_COMP.pdf1 Nov 2019
Architect’s Certificate on Completion of Project (Form 4)File: RCDPL_Architect_Certificate_Dt_11-10-2019_COMP.pdf1 Nov 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1__Architect_Certificate_Rockcorner-compressed.pdf22 Aug 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg_Cert_Rock_june19.pdf22 Aug 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect_CetificateROCK_compressed.pdf17 Aug 2019
Certificates of CA (Form 3)File: CA CERT-compressed.pdf17 Aug 2019
Certificates of CA (Form 3)File: ca_rock_rera1.pdf8 Aug 2019
Certificates of CA (Form 3)File: ca_rock_rera1.pdf3 Jun 2019
Form 2AFile: Rock_form2-compressed.pdf29 Apr 2019
Form 2AFile: Form 2.pdf22 Feb 2019
Certificates of CA (Form 5)File: Form 5.pdf22 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate_30102017.pdf14 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_6112017.PDF14 Nov 2017
Building plan approvalFile: IOD (2).pdf30 Jul 2017
Layout approvalFile: amended layout.pdf30 Jul 2017
Copy of Layout Approval (in case of layout)File: amended layout.pdf30 Jul 2017
Building Plan Approval (IOD)File: IOD (2).pdf30 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCH-ROC.pdf30 Jul 2017
OtherFile: annex--rock.pdf30 Jul 2017
PAN CardFile: Rock Corner PAN Card.pdf29 Jul 2017
Copy of the legal title reportFile: Title Certificate Dudhwala Complex.PDF29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf29 Jul 2017
Certificates of CA (Form 3)File: Final CA Certificate.pdf29 Jul 2017
Proforma of Allotment letterFile: afs dec.pdf29 Jul 2017
Details of encumbrancesFile: ENCUMBRANCES.pdf28 Jul 2017
Declaration in FORM BFile: form b-rock.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGG CERT FORM 2 Dudhwala Complex.pdf28 Jul 2017

Keep DUDHWALA COMPLEX-PHASE 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near BOMBAY CENTRAL

2 kmDUDHWALA COMPLEX-PHASE 2Completed 11Lapsed / revoked 19Other 29Dot size: filed unitsN

Filed coordinates, straight-line distance. 59 registered projects within 2 km.

Builder: ROCK CORNER DEVELOPER PRIVATE LIMITED

ROCK CORNER DEVELOPER PRIVATE LIMITED has 1 registration on MahaRERA, including DUDHWALA COMPLEX-PHASE 2. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if DUDHWALA COMPLEX-PHASE 2 is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DUDHWALA COMPLEX-PHASE 2?

The registered promoter entity is ROCK CORNER DEVELOPER PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DUDHWALA COMPLEX-PHASE 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DUDHWALA COMPLEX-PHASE 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DUDHWALA COMPLEX-PHASE 2?

The professionals named in the filing: Architect: D. H. PATEL; Architect: Hiren S. Thakkar of M/s H S Thakkar & Associates; Engineer: Mahimtura Consultants Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DUDHWALA COMPLEX-PHASE 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DUDHWALA COMPLEX-PHASE 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DUDHWALA COMPLEX-PHASE 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.