Home / Browse projects / Pune, Maharashtra / DSK NABHANGAN

Registration lapsed No litigation declared Residential / Group Housing project

DSK NABHANGAN

By DSKULKARNIANDCOMPANY

RG-MH-23882 · RERA P52100005152 · Last updated on MahaRERA portal: 31 Jul 2017

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 54 months past the filed date
  • 25 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Apr 2022Possession promised54 months past this date
4 of 55Construction stages doneacross 5 buildings; furthest along: Basement (if any), 50%
25Complaints at MahaRERAon this registration
Jump to the 22 documents Report an error

DSK NABHANGAN is a Residential / Group Housing project by DSKULKARNIANDCOMPANY in Pune, Maharashtra, registered with MahaRERA as P52100005152 on 10 Aug 2017. Possession was promised by 30 Apr 2022 and is now 54 months past that date. 25 complaints are on record with the regulator.

At a glance

Project

  • NameDSK NABHANGAN
  • TypeResidential / Group Housing
  • Location
    • Dhayari (Part)
    • Haveli
    • Pune
    • 411041
  • Pincode411041
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100005152
  • ReraGenie IDRG-MH-23882

Builder

  • NameDSKULKARNIANDCOMPANY
  • Entity typePartnership
  • PartnerHEMANTI DEEPAK KULKARNI
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

54 months past promisethis monthRegisteredAug 2017PromisedApr 2022

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 Aug 2017
  • Promised completion30 Apr 2022
  • Revised completionNone
  • Buildings5 building records
  • Documents filed22 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA150000
BNA150000
CNA150000
DNA150000
ENA150000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 31 Jul 2017, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Basement (if any), at 50%.

A4%
ActivityProgress
Excavation40%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B18%
ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C18%
ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D18%
ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E16%
ActivityProgress
Excavation100%
Basement (if any)40%
Podiums (if any)0%
Plinth40%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 31 Jul 2017, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes70%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed294

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots294
Closed/Covered230
Open Space64
BuildingClosed/CoveredOpen SpaceTotal
A401252
B451257
C471259
D501262
E481664

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area10,996 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI30980.46
Proposed, not sanctioned30,980 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBajirao Road, Pune

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMandvi Wala Qutub & Asso
PartnerRole in project
DSKULKARNIANDCOMPANY-

Complaints filed with MahaRERA25

Case no.ComplainantRespondentFiled
CC005000000022854DR MR APPASAHEB SARJERAO KAKADE AND DR MRS RAJASHRI APPASAHEB KAKADEM/S D S KULKANRI AND COMPANAY05/06/2019
CC005000000022143VAIBHAV ARVIND RANED. S. KULKARNI & COMPANY20/10/2018
CC005000000022030GOPICHAND YAMANAPPA WAGHMAREDSKULKARNIANDCOMPANY17/09/2018
CC005000000011889No progress in Building ProjectD S Kulkarni and Company01/09/2018
CC005000000022022Dr.Phalke Deepak BaburaoD S Kulkarni & company12/09/2018
CC005000000011934Khopkar milind shrikantD S Kulkarni20/08/2018
CC005000000011983SwapnilD S Kulkarni & Company14/09/2018
CC005000000011896Aditya Sitaram GoreDSKULKARNIANDCOMPANY20/08/2018
CC005000000011981ABHIMANYU RAMCHANDRA KARKHANISD.S. KULKARNI & COMPANY01/09/2018
CC005000000022062RAHUL DILIP DESHMUKHDSK Kulkarny & company24/09/2018
CC005000000012001VIDYADHAR BHATDSKULKARNIANDCOMPANY05/09/2018
CC005000000012006Nutan MandkeD.S.Kulkarni and Company06/09/2018
CC005000000022118Sandip Dinkarrao SapkalD S Kulkarni02/02/2019
CC005000000022013PRASHANT MADHUKAR GUDHATEHEMANTI DEEPAK KULKARNI11/09/2018
CC005000000022070Saket ParekarDS Kulkarni & Company21/10/2018
CC005000000022071Dr. Eknath Dhondiba MaleD S Kulkarni & Company ltd.25/09/2018
CC005000000022078RAJENDRA KERABA SALOKHE & ASMITA RAJENDRA SALOKHED.S.Kulkarni & Company07/10/2018
CC005000000022080Shivaji MaleD.S.KULKARNI DEVELOPERS LTD.16/10/2018
CC005000000022121Vidyadhar KoreHemanti Deepak Kulkarni08/10/2018
CC005000000022151VISHAL RAGHUNATH NAIKARED S Kulakarni and Company17/10/2018
CC005000000022232CHANDRAKANT VITTHAL DESHMUKHD S KULKARNI PVT LTD10/11/2018
CC005000000022491Mansing ChavanDeepak Sakharam Kulkarni22/01/2019
CC005000000023115Vasudev Narayan BhatDS Kulkerni and dev.09/06/2019
CC005000000106817Sudhir GhuseD.S.Kulkarni and Company09/07/2022
CC005000000259065Purnima Chetan SambhusD S Kulkarni and company27/06/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed22

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Building plan approvalFile: 12.pdf31 Jul 2017
Building plan approvalFile: 15.pdf31 Jul 2017
Building plan approvalFile: 17.pdf31 Jul 2017
Building plan approvalFile: 19.pdf31 Jul 2017
Building plan approvalFile: 21.pdf31 Jul 2017
Building plan approvalFile: 22.pdf31 Jul 2017
Layout approvalFile: 1.pdf31 Jul 2017
Copy of the legal title reportFile: TITLE REPORT.pdf31 Jul 2017
Details of encumbrancesFile: Scan Nabhangan.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: 1.pdf31 Jul 2017
Building Plan Approval (IOD)File: 12.pdf31 Jul 2017
Building Plan Approval (IOD)File: 15.pdf31 Jul 2017
Building Plan Approval (IOD)File: 17.pdf31 Jul 2017
Building Plan Approval (IOD)File: 19.pdf31 Jul 2017
Building Plan Approval (IOD)File: 21.pdf31 Jul 2017
Building Plan Approval (IOD)File: 22.pdf31 Jul 2017
Declaration in FORM BFile: Form B_DSK Nabhangan_DSKAC.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate.pdf31 Jul 2017
Certificates of CA (Form 3)File: DSK Nabhangan CA Certificate.pdf31 Jul 2017
Proforma of Allotment letterFile: Allotment RERA.pdf31 Jul 2017
Proforma of Allotment letterFile: agreement - dsk vishwa nabhangan.pdf31 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DSK NABHANGAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dhayari (Part)13,700+ in Pune

2 kmDSK NABHANGANCompleted 17Lapsed / revoked 6Other 2Dot size: filed unitsN

Filed coordinates, straight-line distance. 25 registered projects within 2 km.

Builder: DSKULKARNIANDCOMPANY

DSKULKARNIANDCOMPANY has 2 registrations on MahaRERA, including DSK CHAITRABAN and DSK NABHANGAN. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that DSK NABHANGAN shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DSK NABHANGAN is delayed beyond 30 Apr 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DSK NABHANGAN?

The registered promoter entity is DSKULKARNIANDCOMPANY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DSK NABHANGAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DSK NABHANGAN?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DSK NABHANGAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DSK NABHANGAN?

The professionals named in the filing: Architect: Mandvi Wala Qutub & Asso. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DSK NABHANGAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DSK NABHANGAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DSK NABHANGAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.