ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Drushti Sapphire

Registration lapsed No litigation declared Others project

Drushti Sapphire

By Drushti Realtors Pvt Ltd

RG-MH-84559 · RERA P51800032434 · Last updated on MahaRERA portal: 20 Feb 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 18 months past the filed date
  • 6 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Apr 2025Possession promised18 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 90%
6Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

Drushti Sapphire is a Others project by Drushti Realtors Pvt Ltd in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800032434 on 4 Jan 2022. Possession was promised by 30 Apr 2025 and is now 18 months past that date. 6 complaints are on record with the regulator.

At a glance

Project

  • NameDrushti Sapphire
  • TypeOthers
  • Location
    • A S Gawde Marg
    • Ghatkopar East
    • Kurla
    • Mumbai Suburban
    • 400075
  • Pincode400075
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800032434
  • ReraGenie IDRG-MH-84559

Builder

  • NameDrushti Realtors Pvt Ltd
  • Entity typeCompany
  • DirectorsAshok Haridas Jagdale, Ashok Haridas Jagdale, Ashok Haridas Jagdale
  • Declared earlier projects2 →

Key dates

18 months past promisethis monthRegisteredJan 2022PromisedApr 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on4 Jan 2022
  • Promised completion30 Apr 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Drushti SapphireNA2020000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.

Drushti Sapphire: 55% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises35%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.25%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.40%

Progress on shared amenities15

As on 20 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes1%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes40%
Solid Waste Management And DisposalYes40%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes25%
Fire protection and fire safety requirementsYes30%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,804 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Trishul CHS LTDKurlaMumbai Suburban

Approvals and building plan

Sanctioning authorityBuilding Permission cell Greater Mumbai
Permissible FSI22969.0
Proposed, not sanctioned10,076 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVILE PARLE EAST

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYBM Consultants
EngineerSatish Shinde
EngineerGangaram Sahani
Chartered AccountantRNA Associates
Chartered AccountantKMA & Co
PartnerRole in project
Drushti Realtors Pvt Ltd-

Litigation declared1

CaseCourtStatus
271/2020City Civil CourtTo be disposed off

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000429184Mahendra AgaleDrushti Realtors Pvt Ltd10/02/2024
CC006000000480047Ashish Shivshankar YadavDrushti Realtors Private Limited11/04/2024
CC12400312Padma Bhagwat BagulDrushti Realtors Pvt Ltd03/10/2024
CC12500973Drushti Realtors Pvt LtdPANTNAGAR TRISHUL CHS LTD20/03/2025
CC12504638URMI MAHESH DEVANIDrushti Realtors Pvt Ltd26/12/2025
CC12600052Yogesh Dattatray ShewdeDrushti Realtors Pvt Ltd04/01/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Dec 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Dec 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Jan 2025

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 - June 2023.pdf20 Feb 2026
Form 2File: Form 2 - June 23.pdf20 Feb 2026
Form 3File: Form 3 - June 23.pdf20 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure - June 23.pdf20 Feb 2026
Form 1File: Architects Certificate 30-9-23 SPACERA_.pdf28 Jan 2026
Form 2File: Form 2 - Sept 23.pdf28 Jan 2026
Form 3File: Form 3 - Sept 23.pdf28 Jan 2026
Disclosure of Sold and Booked InventoryFile: Inventory.pdf28 Jan 2026
Form 1File: Form 1 - March 24.pdf28 Jan 2026
Form 2File: Form 2 - March 24.pdf28 Jan 2026
Form 3File: Form 3 - March 24.pdf28 Jan 2026
Disclosure of Sold and Booked InventoryFile: Inventory - March 24.pdf28 Jan 2026
Form 1File: Form 1 - June 24.pdf28 Jan 2026
Form 2File: Form 2 - June 24.pdf28 Jan 2026
Form 3File: Form 3 - June 24.pdf28 Jan 2026
Disclosure of Sold and Booked InventoryFile: Inventory - June 24.pdf28 Jan 2026
Form 1File: Form 1 - Dec 23.pdf28 Jan 2026
Form 2File: Form 2 - December 23.pdf28 Jan 2026
Form 3File: Form 3 - December 23.pdf28 Jan 2026
Disclosure of Sold and Booked InventoryFile: Inventory - December 23.pdf28 Jan 2026
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 RERA.pdf21 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Full OC Copy Trishul D-03-06-2024.pdf30 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Trishul part OC 06-03-24_0001.pdf30 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A- Sapphire.pdf30 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: Architect Certificate 19-12-2024.pdf19 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf12 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf4 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf4 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf4 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31-3-23.pdf16 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31-3-23.pdf16 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 31-3-23.pdf16 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: From 3 31-3-23_.pdf16 May 2023
Proforma of Agreement for saleFile: Drushti Sapphire Draft.pdf3 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 (1).pdf22 Feb 2023
PAN CardFile: DRPL Pan Card.pdf27 Dec 2021
Declaration in FORM BFile: AFFIDAVIT RERA_0001-compressed.pdf24 Dec 2021
Copy of the legal title reportFile: Drushti legal title repo.pdf23 Dec 2021
Proforma of Allotment letterFile: RERA Agreement for Sale - Final - 20-12-2021PDF_compressed.pdf22 Dec 2021
Building plan approvalFile: Trishul IOD_compressed.pdf10 Dec 2021
Layout approvalFile: layout approval.pdf10 Dec 2021
Details of encumbrancesFile: DRPL encumbrance.pdf10 Dec 2021
Copy of Layout Approval (in case of layout)File: layout approval.pdf10 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: Trishul IOD_compressed.pdf10 Dec 2021
Commencement Certificates / NA Order for plotted developmentFile: Trishul C C copy date 13- jul -2021.pdf10 Dec 2021
Declaration about Commencement CertificateFile: Form D.pdf10 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: arch cert DRPL_compressed.pdf10 Dec 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: IMG_1.pdf10 Dec 2021
CERSAI detailsFile: CERSAI_Search_Report_200226332108_For_Asset_Based_Search_21_12_2021_17_56_02_704-1.pdf10 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 sapphire.pdf10 Dec 2021
Proforma of Allotment letterFile: DRPL allotment.pdf10 Dec 2021

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
EMBASSYNext to Acharya atre Maidan CTS 192 1pt Pant nagar Ghatkopar East Mumbai 400075126CompletedMar 2020Mar 2020
Varun TowerVarun Tower Opposite Shivaji Technical School Pant nagar Ghatkopar East54CompletedMay 2016Late, Aug 2016

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Drushti Sapphire on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ghatkopar East6,700+ in Mumbai Suburban

2 kmDrushti SapphireCompleted 123Lapsed / revoked 70Other 117Dot size: filed unitsN

Filed coordinates, straight-line distance. 310 registered projects within 2 km.

Builder: Drushti Realtors Pvt Ltd

Drushti Realtors Pvt Ltd has 1 registration on MahaRERA, including Drushti Sapphire. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Drushti Sapphire shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Drushti Sapphire is delayed beyond 30 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Drushti Sapphire?

The registered promoter entity is Drushti Realtors Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Drushti Sapphire?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Drushti Sapphire?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Drushti Sapphire?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Drushti Sapphire?

The professionals named in the filing: Architect: YBM Consultants; Engineer: Satish Shinde; Engineer: Gangaram Sahani; Chartered Accountant: RNA Associates; Chartered Accountant: KMA & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Drushti Sapphire?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Drushti Sapphire. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Drushti Sapphire to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.