Registration lapsed No litigation declared Residential / Group Housing project

DREAMS RIVIERA

By ASHTAVINAYAK INFRA

RG-MH-04869 · RERA P52100020967 · Last updated on MahaRERA portal: 26 Mar 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 7 complaints at MahaRERA
  • Completion date moved by 56 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
7Complaints at MahaRERAon this registration
Jump to the 47 documents Report an error

DREAMS RIVIERA is a Residential / Group Housing project by ASHTAVINAYAK INFRA in Pune, Maharashtra, registered with MahaRERA as P52100020967 on 27 May 2019. Possession was promised by 31 Dec 2024 and is now 22 months past that date. The completion date has moved by 56 months from the original filing. 7 complaints are on record with the regulator.

At a glance

Project

  • NameDREAMS RIVIERA
  • TypeResidential / Group Housing
  • Location
    • Gat No 1161 Kavadadigaon Road Near Railway Gate No 4
    • Manjari Farm
    • Kadamwak Wasti
    • Haveli
    • Pune
    • 412307
  • Pincode412307
  • RERA no.P52100020967
  • ReraGenie IDRG-MH-04869

Builder

  • NameASHTAVINAYAK INFRA
  • Entity typePartnership
  • PartnersAvinash Vasantrao Sonawane, Raju Pandurang Said, Ashok Vasantrao Sonawane, Nutan Ashok Sonawane, Ranjeet Ashok Sonawane
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

22 months past promisethis monthRegisteredMay 2019First promiseApr 2020Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on27 May 2019
  • Promised completion31 Dec 2024
  • Revised completionRevised to 31 Dec 2024 (originally 30 Apr 2020)
  • Buildings1 building record
  • Documents filed47 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Dreams Rivira Wing BNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Dreams Rivira Wing B: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 26 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,500 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1342.36
Proposed, not sanctioned1,342 sq m
Buildings approved2
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHETTY COMPLEX GP 69 HERMAX CHOWK SAMBHAJI NAGAR PUNE 411019

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNAMRATA SONAWANE
Chartered AccountantYOGESHKUMAR THANVI
PartnerRole in project
ASHTAVINAYAK INFRA-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018126Apr 2020 → Jun 2024

Reason as filed by the promoterOur Project is out of the city so we have less booking for the same and due to Covid 19 Pandemic all raw material Price increased and due to less booking of flat so we have lack of funds and now we are complete all pending works and ready with the project.

EXT52100024133Apr 2020 → Dec 2024

Reason as filed by the promoterOccupancy Certificate not yet received

EXT52100003926Apr 2020 → Apr 2021

Reason as filed by the promoterDue to changes in promoter company and merger with ASHTAVINAYAK INFRA for further development of this project

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC005000000228484ABHIJEET Lahu KAVATHEKARMangesh Mhatarba Thorat14/03/2023
CC005000000238639Nitin Kundlik TemgireNitin Dnyaneshwar Kurkute05/04/2023
CC005000000259058Kalyan Jayraj JadhavMangesh Mhatarba Thorat01/08/2023
CC005000000259252Pooja Arjun KorhaleDinesh Kurkute03/08/2023
CC005000000259256Ashok Shrinivas KulkarniMangesh Mhatarba Thorat04/08/2023
CC005000000259265Ramesh MenchuNavnath Magar08/08/2023
CC12604284Sunny MenchuASHTAVINAYAK INFRA08/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Apr 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Apr 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 May 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 Mar 2025

Documents filed47

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf26 Mar 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf5 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf5 Jul 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf5 Jul 2024
Declaration in FORM BFile: FORM B.pdf25 Jun 2024
Certificates of CA (Form 3)File: form 3 AHSTAVINAYAK.pdf18 Jun 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.pdf7 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf7 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 5 23-24.pdf7 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM2A.pdf7 May 2024
Certificates of CA (Form 3)File: FORM 3.pdf7 May 2024
Certificates of CA (Form 3)File: FORM 3CA.pdf29 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A.pdf29 Mar 2024
OtherFile: ANNEXURE A.pdf29 Mar 2024
OtherFile: SELF DECLARATION.pdf29 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23.pdf19 Dec 2023
Declaration in FORM BFile: FORM B.pdf12 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2022.pdf12 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2023.pdf12 Dec 2023
Disclosure of sold/ booked inventoryFile: INVENTORY SOLD UNSOLD.pdf12 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22-23.pdf12 Dec 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: SOCIETY FORMATION CERTIFICATE.pdf8 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 19-20.pdf5 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 21-22.pdf5 Dec 2023
Declaration about Commencement CertificateFile: 07 Declaration of commencement.pdf21 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 02 FORM 2.pdf21 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 03 FORM 2A 20-21.pdf21 Oct 2021
Disclosure of sold/ booked inventoryFile: 06 Disclosure of inventory.pdf21 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 05 form 5 20-21.pdf21 Oct 2021
Proforma of Allotment letterFile: Agreement to sale_ RERA draft.pdf12 Mar 2020
PAN CardFile: PAN Ashtavinayak Infra.pdf1 Oct 2019
Declaration in FORM BFile: Form B RERA Ashtavinayak Infra.pdf1 Oct 2019
OtherFile: JV Agreement.pdf1 Oct 2019
Building plan approvalFile: PMRDA Drawing-min_compressed.pdf7 May 2019
Building Plan Approval (IOD)File: PMRDA Drawing-min_compressed.pdf7 May 2019
Certificates of CA (Form 3)File: CA Certicate (Compress).pdf7 May 2019
Proforma of Allotment letterFile: revera Apr B - RERA Draft Modified.pdf7 May 2019
Details of encumbrancesFile: Encumn.pdf3 May 2019
Layout approvalFile: PMRDA Drawing-min_compressed.pdf20 Apr 2019
Copy of Layout Approval (in case of layout)File: PMRDA Drawing-min_compressed.pdf20 Apr 2019
PAN CardFile: PAN CARD PANORAMA DEVELOPERS.pdf19 Apr 2019
Copy of the legal title reportFile: Legal Title Report.pdf19 Apr 2019
Commencement Certificates / NA Order for plotted developmentFile: PMRDA Development Permission.pdf19 Apr 2019
Declaration in FORM BFile: Form B 1 (Compresss).pdf19 Apr 2019
Declaration in FORM BFile: Form B 2 (Compress).pdf19 Apr 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architecture Certificate.pdf19 Apr 2019
OtherFile: GST.pdf19 Apr 2019

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 56 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DREAMS RIVIERA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Manjari Farm13,700+ in Pune

Builder: ASHTAVINAYAK INFRA

ASHTAVINAYAK INFRA has 2 registrations on MahaRERA, including DREAMS RIVIERA and DREAMS RIVIERA A WING. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that DREAMS RIVIERA shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DREAMS RIVIERA is delayed beyond 31 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DREAMS RIVIERA?

The registered promoter entity is ASHTAVINAYAK INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DREAMS RIVIERA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against DREAMS RIVIERA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for DREAMS RIVIERA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DREAMS RIVIERA?

The professionals named in the filing: Architect: NAMRATA SONAWANE; Chartered Accountant: YOGESHKUMAR THANVI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DREAMS RIVIERA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DREAMS RIVIERA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DREAMS RIVIERA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.