Home / Browse projects / Ratnagiri, Maharashtra / DJ SkyLink
DJ SkyLink
RG-MH-30653 · RERA P52800031130 · Last updated on MahaRERA portal: 24 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 7 completed earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 7 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Ratnagiri registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DJ SkyLink is a Others project by Dinesh Mohanlal Jain in Ratnagiri, Maharashtra, registered with MahaRERA as P52800031130 on 5 Oct 2021. Possession is promised by 31 Dec 2027. 18 of the 73 units on this registration are recorded sold or booked, and 0 of 33 construction stages are filed complete.
At a glance
Project
- NameDJ SkyLink
- TypeOthers
- Location
- Nachane Road
- Nachane
- Ratnagiri (M Cl)
- Ratnagiri
- 415612
- Pincode415612
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52800031130
- ReraGenie IDRG-MH-30653
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on5 Oct 2021
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings3 building records
- Documents filed85 files
Current status
Figures as on 24 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing A | NA | 17 | 0 | 51 | 9 | 60 |
| Wing B | NA | 7 | 0 | 11 | 0 | 11 |
| Wing C | NA | 2 | 2 | 2 | 0 | 2 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.
Wing A0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing B0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing C0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed2
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing A | 1 | 1 |
| Wing B | 1 | 1 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Dinesh Jain | Ratnagiri (M Cl) | Ratnagiri |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Milind R Yadav |
| Engineer | Manoj S Joshi Joshi |
| Chartered Accountant | Rohit R Shah |
| Partner | Role in project |
|---|---|
| Dinesh Mohanlal Jain | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Sep 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Oct 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Oct 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2027
Documents filed85
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1 Arch March 26.pdf | 24 Apr 2026 |
| Form 2File: DJ Eng Cert Mar 2026.pdf | 24 Apr 2026 |
| Form 3File: FORM 3 Mar 26.pdf | 24 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Mar 26.pdf | 24 Apr 2026 |
| Form 1File: DJ SkyLink Form 1 Dec 25 (1).pdf | 6 Feb 2026 |
| Form 2File: DJ Eng Cert Dec 2025.pdf | 6 Feb 2026 |
| Form 3File: DJ SKYLINK- RERA FORM 3 31122025 SIGNED (1).pdf | 6 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Dec 25.pdf | 6 Feb 2026 |
| Form 1File: DJ Form 1 Sept 25.pdf | 31 Oct 2025 |
| Form 2File: DJ Form 2 Sept 25.pdf | 31 Oct 2025 |
| Form 3File: DJ Form 3 Sept 25.pdf | 31 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sept 25.pdf | 31 Oct 2025 |
| Form 1File: DJ Skylink Form 1 June 2025.pdf | 30 Oct 2025 |
| Form 2File: DJ Eng Cert June 2025.pdf | 30 Oct 2025 |
| Form 3File: DJ Form 3 June.pdf | 30 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold June 25.pdf | 30 Oct 2025 |
| Form 1File: D J Form 1 March 25.pdf | 29 Jul 2025 |
| Form 2File: Eng Cert March 2025.pdf | 29 Jul 2025 |
| Form 3File: FORM 3 March 2025.pdf | 29 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: DJ March Sold-Unsold.pdf | 29 Jul 2025 |
| Form 1File: D J Skylink Form 1 March 2025.pdf | 26 Jul 2025 |
| Form 2File: Eng Cert March 2025.pdf | 26 Jul 2025 |
| Form 3File: FORM 3 March 2025.pdf | 26 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: D J Sky Link March 2025 S&U.pdf | 26 Jul 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED 31122024.pdf | 6 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert Dec 2024.pdf | 2 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: D J Form 1 March 25.pdf | 22 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DJ Form 1 March 24.pdf | 19 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DJ Form 1 June 24.pdf | 19 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DJ Form 1 Sep 24.pdf | 19 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DJ Form 1 Dec 24.pdf | 19 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert March 2024.pdf | 19 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert June 2024.pdf | 19 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Cert Sept 2024.pdf | 19 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A DJ 23-24 WING B C.pdf | 19 Feb 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A DJ 23-24 A.pdf | 19 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED 31032024.pdf | 17 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED 30062024.pdf | 17 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED 30092024.pdf | 17 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 Signed 311223.pdf | 27 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A DJ 22-23.pdf | 14 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED DJ 310323.pdf | 14 Mar 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FROM 5 310323.pdf | 14 Mar 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SIGNED DJ NEW.pdf | 3 Feb 2024 |
| Layout approvalFile: 2021-07-09 New Blue Print 2.pdf | 26 Oct 2023 |
| Building plan approvalFile: 2021-07-09 New Blue Print 1.pdf | 26 Oct 2023 |
| Building plan approvalFile: 2021-07-09 New Blue Print 2.pdf | 26 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 2021-07-09 New Blue Print 2.pdf | 26 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 2021-07-09 New Blue Print 1.pdf | 26 Oct 2023 |
| Building Plan Approval / NA Order for plotted developmentFile: 2021-07-09 New Blue Print 2.pdf | 26 Oct 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: DJ New Building Permission 24-11-21.pdf | 26 Oct 2023 |
| Layout approvalFile: 2021-07-09 New Blue Print 1.pdf | 25 Oct 2023 |
| Copy of Layout Approval (in case of layout)File: 2021-07-09 New Blue Print 1.pdf | 25 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: From - 2A.pdf | 1 Mar 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 27 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 DJ.pdf | 27 Feb 2023 |
| Proforma of Agreement for saleFile: Sathekhat DJ.pdf | 27 Feb 2023 |
| Copy of the legal title reportFile: Format A.pdf | 27 Sep 2021 |
| Details of encumbrancesFile: LTR.pdf | 15 Sep 2021 |
| Layout approvalFile: Blue Print 1.pdf | 9 Sep 2021 |
| Layout approvalFile: Blue Print 2.pdf | 9 Sep 2021 |
| Building plan approvalFile: Blue Print 1.pdf | 9 Sep 2021 |
| Building plan approvalFile: Blue Print 2.pdf | 9 Sep 2021 |
| Building plan approvalFile: NA Order.pdf | 9 Sep 2021 |
| PAN CardFile: Dinesh Jain - Pan Card.pdf | 9 Sep 2021 |
| Copy of the legal title reportFile: Search Report-compressed.pdf | 9 Sep 2021 |
| Details of encumbrancesFile: Search Report-compressed.pdf | 9 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: Blue Print 1.pdf | 9 Sep 2021 |
| Copy of Layout Approval (in case of layout)File: Blue Print 2.pdf | 9 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Blue Print 1.pdf | 9 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: Blue Print 2.pdf | 9 Sep 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: NA Order.pdf | 9 Sep 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Bandhkam Permission.pdf | 9 Sep 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order.pdf | 9 Sep 2021 |
| Declaration about Commencement CertificateFile: Decleration About Commencement Certificate.pdf | 9 Sep 2021 |
| Declaration in FORM BFile: Form B.pdf | 9 Sep 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert.pdf | 9 Sep 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert.pdf | 9 Sep 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Cert.pdf | 9 Sep 2021 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 9 Sep 2021 |
Promoter's earlier projects9
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Rajlaxmi SankulP52800054042 | Times Mall, Ratnagiri | 35 | Dec 2023 | Ongoing | Dec 2028 | Not due yet |
| Shreejee Ocean ViewP52800055303 | Ganpatipule, Ratnagiri | 59 | Mar 2024 | Ongoing | Mar 2028 | Not due yet |
| DJ SkyLink | Nachane Ratnagiri | 71 | - | Ongoing | Jan 2027 | Jan 2027 |
| Nalini Vasant Vihar | Nivkhol Ratnagiri | 38 | - | Completed | Jan 2024 | May 2023 |
| Saraswati | Abhyudya Nagar Ratnagiri | 47 | - | Completed | Nov 2023 | Jan 2019 |
| Shashank Paradise | Mandovi Ratnagiri | 21 | - | Completed | Mar 2023 | Oct 2019 |
| Khedekar Sankul | Shere Naka Ratnagiri | 33 | - | Completed | Jan 2023 | Jun 2022 |
| Nirmal Paradise | Karwanchiwadi Ratnagiri | 24 | - | Completed | Apr 2022 | May 2021 |
| Siddheshwar Heights | Joshi Paland Ratnagiri | 37 | - | Completed | Nov 2015 | Nov 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Ratnagiri
Computed across the 1,100+ Ratnagiri projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 7 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 85 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep DJ SkyLink on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Nachane1,100+ in Ratnagiri
Filed coordinates, straight-line distance. 104 registered projects within 2 km.
Navkar Enclave
Evergreen Associates
Kalpavriksha Heritage
Kalpavriksha Builders & Developers
LAXMI KEHSAV NAGAR PHASE II
DEEPAK YASHWANT SALVI
THE WIND
Arihant Vastu Nirman Pvt. Ltd
THE WOODLAND
Siddhivinayak Realty
AKAR VANAJU ESTATE
AKAR INFRASTRUCTURE
See every Ratnagiri project, with the district possession charts
Builder: Dinesh Mohanlal Jain
Dinesh Mohanlal Jain has 8 registrations on MahaRERA, including Saraswati Sankul and NIRMAL PARADISE. Its filings disclose 9 earlier MahaRERA projects: declares 7 of 7 past projects completed on time. Read the full track record. See more projects on the Ratnagiri district page.
Frequently asked questions
What are my rights if DJ SkyLink is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DJ SkyLink?
The registered promoter entity is Dinesh Mohanlal Jain, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DJ SkyLink?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DJ SkyLink?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DJ SkyLink?
The professionals named in the filing: Architect: Milind R Yadav; Engineer: Manoj S Joshi Joshi; Chartered Accountant: Rohit R Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DJ SkyLink?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback