Home / Browse projects / Pune, Maharashtra / DISCOVERY PHASE - III

Registration lapsed No litigation declared Residential / Group Housing project

DISCOVERY PHASE - III

By S2 REALTY AND DEVELOPERS PRIVATE LIMITED

RG-MH-02110 · RERA P52100012273 · Last updated on MahaRERA portal: 29 Apr 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 25 months past the filed date
  • Completion date moved by 48 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2024Possession promised25 months past this date
24 of 33Construction stages doneacross 3 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 99 documents Report an error

DISCOVERY PHASE - III is a Residential / Group Housing project by S2 REALTY AND DEVELOPERS PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100012273 on 1 Sep 2017. Possession was promised by 30 Sep 2024 and is now 25 months past that date. The completion date has moved by 48 months from the original filing.

At a glance

Project

  • NameDISCOVERY PHASE - III
  • TypeResidential / Group Housing
  • Location
    • DELLA ADVENTURE ROAD
    • KUNENAMA
    • KUNEGAON
    • Kune N.m.
    • Mawal
    • Pune
    • 410401
  • Pincode410401
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100012273
  • ReraGenie IDRG-MH-02110

Builder

  • NameS2 REALTY AND DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45200MH2008PTC182883
  • GSTIN27AAECP7229F1ZC
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Managing DirectorSUJATA RAVI HEGDE
  • ChairpersonSUNIEL VEERAPPA SHETTY
  • Other registrations2 more →
  • Completed1 of 3
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

25 months past promisethis monthRegisteredSep 2017First promiseSep 2020Revised toSep 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Sep 2017
  • Promised completion30 Sep 2024
  • Revised completionRevised to 30 Sep 2024 (originally 30 Sep 2020)
  • Buildings3 building records
  • Documents filed99 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
VILLA NO 2NA20000
VILLA NO 4NA20000
VILLA NO 18NA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 29 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

24 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.

VILLA NO 273%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 473%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
VILLA NO 1873%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed3

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots3
Open Space3
BuildingOpen SpaceTotal
VILLA NO 211
VILLA NO 411
VILLA NO 1811

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,304 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1256.0
Proposed, not sanctioned1,256 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor G4A Welspun House Kamla City S B Marg Lower Parel

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectH B ARCHITECTS
EngineerU D CHANDE
Chartered AccountantIR SHETTY & ASSOCIATES
PartnerRole in project
S2 REALTY AND DEVELOPERS PRIVATE LIMITED-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100009956Sep 2020 → Sep 2022

Reason as filed by the promoterVillas in our project are constructed on the basis of booking amount received from Villa purchasers. Since we have not sold any villas in this Phase (PHASE III) and there are no allottees in this PHASE , construction work is delayed.

EXT52100008603Sep 2020 → Sep 2021

Reason as filed by the promoterVILLA IS CONSTRUCTED ON THE BASIS OF BOOKING AMOUNT RECIEVED FROM THE VILLA PURCHASERS . SINCE WE DID NOT SELL ANY VILLAS IN PHASE III TILL DATE , THE PROJECT GOT DELAYED.

EXT52100019543Sep 2020 → Sep 2024

Reason as filed by the promoterVillas in our Project are constructed on the basis of booking amount received from the the Allottees. Since 1 villa is still under construction we need extension.

EXT52100015464Sep 2020 → Mar 2024

Reason as filed by the promoterVillas in our Project are built based on the basis of booking amounts received from Villa Purchasers , Since we still have a villa to build and sell in this Phase we need to extend the completion date.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Jan 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 30 Jan 2025

Documents filed99

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 99 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1 Phase III 0711202429 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase III.pdf25 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf25 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Form 2 Phase III.pdf17 Apr 2025
Declaration in FORM BFile: Form B.pdf24 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf24 Feb 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1Phase III 31122024.pdf30 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: Rera phase III-completion Certificate (1).pdf30 Jan 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: VILLA NO 2.pdf30 Jan 2025
Certificates of CA (Form 3)File: Form 3 Phase III 30092024.pdf22 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase III 30092024.pdf22 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 Phase III.pdf22 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Phase III.pdf29 Oct 2024
Certificates of CA (Form 3)File: Form 3 -Phase III.pdf14 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase III.pdf19 Jul 2024
Declaration in FORM BFile: Declaration -Form B.pdf30 Apr 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD.pdf30 Apr 2024
Deviation Report with respect to Allotment letterFile: Allotment Letter Deviation RERA.pdf30 Apr 2024
Deviation Report with respect to model copy of AgreementFile: Agreement with deviation highlighted - For RERA.pdf30 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Phase III Form 2 310324.pdf25 Apr 2024
Certificates of CA (Form 3)File: Phase III Form 3 31032024.pdf24 Apr 2024
Certificates of CA (Form 3)File: Phase III Form 3 310324.pdf22 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Phase III Form -1.pdf18 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Phase III Form 2A.pdf18 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Phase III-Form 1.pdf17 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Phase III-Form 2.pdf17 Jan 2024
Certificates of CA (Form 3)File: PHASE-III Form 3.pdf17 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Phase III Form 1.pdf26 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Phase III Form 2.pdf26 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Phase III Form 2A 310323.pdf26 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Phase III-Form 5-310323.pdf26 Oct 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC.pdf23 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Phase III.pdf16 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 PHASE III 3132023.pdf16 Oct 2023
Declaration in FORM BFile: Form B.pdf13 Oct 2023
Disclosure of sold/ booked inventoryFile: Disclosure of sold.pdf13 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1 Phase III as on 30062023.pdf14 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 PHASE III as on 30062023.pdf14 Sep 2023
Certificates of CA (Form 3)File: CA Certificate - Phase - III as on 30062023.pdf14 Sep 2023
Certificates of CA (Form 3)File: Phase III.pdf5 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 PHASE III 31122022.pdf5 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Phase III 31032023.pdf5 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase III 31122022.pdf5 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase III 31032023.pdf5 Jun 2023
Certificates of CA (Form 3)File: Form 3 Phase III 31122022.pdf5 Jun 2023
Certificates of CA (Form 3)File: Form 3 3062022.pdf17 Feb 2023
Certificates of CA (Form 3)File: Form 3 3092022.pdf17 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: From 1 PHASE III 3062022.pdf10 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 PHASE III 300922.pdf10 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 PHASE III 300622.pdf10 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 PHASE III 300922.pdf10 Feb 2023
Copy of the legal title reportFile: Supplementary Title Report.pdf11 Jan 2023
Details of encumbrances concerned to FinanceFile: Non Encumbrance -III.pdf11 Jan 2023
Details of encumbrances concerned to FinanceFile: Non Encumbrance -III Finance.pdf11 Jan 2023
Details of encumbrances concerned to FinanceFile: Non Encumbrance -III Finance.pdf11 Jan 2023
Details of encumbrances concerned to LegalFile: Non Encumbrance -III.pdf11 Jan 2023
Details of encumbrances concerned to LegalFile: Non Encumbrance -III Finance.pdf11 Jan 2023
Details of encumbrances concerned to LegalFile: Non Encumbrance -III Finance.pdf11 Jan 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold - Phase III.pdf11 Jan 2023
CERSAI detailsFile: Undertaking Cersai - Phase III.pdf11 Jan 2023
Certificates of CA (Form 3)File: Form 3 FY 19-20.pdf11 Jan 2023
Certificates of CA (Form 3)File: Form -3 FY 20-21.pdf11 Jan 2023
Certificates of CA (Form 3)File: Form -3 FY 21-22.pdf11 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A- Suniel shetty Phase III.pdf11 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A -Sujata Hegde Phase III.pdf11 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A -PV Shetty Phase III.pdf11 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A- Monisha Shetty Phase III.pdf11 Jan 2023
Proforma of Agreement for saleFile: Standard Agreement for Sale - Discovery(RERA) - Draft.pdf11 Jan 2023
Proforma of Allotment letterFile: Allotment Letter Discovery.pdf11 Jan 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration about Seperate Bank Account.pdf11 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-FY 19-20.pdf5 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-FY 20-21.pdf5 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2-FY 21-22.pdf5 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A-FY 21-22.pdf5 Jan 2023
Certificates of CA (Form 3)File: Form 2-FY 19-20.pdf5 Jan 2023
Certificates of CA (Form 3)File: Form 2-FY 20-21.pdf5 Jan 2023
Certificates of CA (Form 3)File: Form 2-FY 21-22.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form -5-FY-20-21-Phase III.pdf5 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form -5-FY 21-22-Phase III.pdf5 Jan 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
DISCOVERY PHASE - 1Discovery Project Kunenama Village Taluka Maval District Pune 41040113CompletedJun 2017May 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 48 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DISCOVERY PHASE - III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KUNENAMA, KUNEGAON13,700+ in Pune

2 kmDISCOVERY PHASE - IIICompleted 3Lapsed / revoked 4Other 4Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: S2 REALTY AND DEVELOPERS PRIVATE LIMITED

S2 REALTY AND DEVELOPERS PRIVATE LIMITED has 3 registrations on MahaRERA, including DISCOVERY PHASE - II and DISCOVERY PHASE - III. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that DISCOVERY PHASE - III shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if DISCOVERY PHASE - III is delayed beyond 30 Sep 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DISCOVERY PHASE - III?

The registered promoter entity is S2 REALTY AND DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its CIN U45200MH2008PTC182883 and GSTIN 27AAECP7229F1ZC can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DISCOVERY PHASE - III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DISCOVERY PHASE - III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DISCOVERY PHASE - III?

The professionals named in the filing: Architect: H B ARCHITECTS; Engineer: U D CHANDE; Chartered Accountant: IR SHETTY & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DISCOVERY PHASE - III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DISCOVERY PHASE - III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DISCOVERY PHASE - III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.