ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Dhvanil Harmony

Registered No litigation declared Residential / Group Housing project

Dhvanil Harmony

By Dhvanil Associates LLP

RG-MH-56524 · RERA PR1260002502288 · Last updated on MahaRERA portal: 15 Jun 2026

Source: official MahaRERA filing

Red flags

  • Rs 35.00 crore secured on the land, in favour of SMFG INDIA HOME FINANCE COMPANY LIMITED
  • Allotment letter deviates from the model form

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2030Possession promisedno revision filed
4 of 44Construction stages doneacross 4 buildings; furthest along: Basement (if any), 20%
171 of 182Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 13 documents Report an error

Dhvanil Harmony is a Residential / Group Housing project by Dhvanil Associates LLP in Pune, Maharashtra, registered with MahaRERA as PR1260002502288 on 9 Feb 2026. Possession is promised by 30 Jun 2030. 11 of the 182 units on this registration are recorded sold or booked, and 4 of 44 construction stages are filed complete.

At a glance

Project

  • NameDhvanil Harmony
  • TypeResidential / Group Housing
  • Location
    • Manjri BK
    • Haveli
    • Pune
    • MANJARI Bk
    • Haveli
    • Pune
    • 412307
  • Pincode412307
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR1260002502288
  • ReraGenie IDRG-MH-56524

Builder

  • NameDhvanil Associates LLP
  • Entity typeLimited Liability Partnership
  • LLPINAAW-9977
  • GSTIN27AASFD4196L2ZM
  • Designated PartnersAnkit Dineshbhai Patel, Biren Kantibhai Patel, Deepkumar Jagdishbhai Patel, Sachin Dineshbhai Patel

Key dates

this monthRegisteredFeb 2026PromisedJun 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Feb 2026
  • Promised completion30 Jun 2030
  • Revised completionNone
  • Buildings4 building records
  • Documents filed13 files

Current status

6%11 of 182 units booked
3.0%Work done, per cost certificate

Figures as on 15 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA5322022
Wing BNA5324024
Wing CNA16141100110
Wing EWSNA161426026

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 15 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Basement (if any), at 20%.

Wing A9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing C11%
ActivityProgress
Excavation100%
Basement (if any)20%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing EWS9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 15 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNo0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNo0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed288

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots288
Closed/Covered288
BuildingClosed/CoveredTotal
Wing A3535
Wing B3838
Wing C174174
Wing EWS4141

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area7,300 sq m
Land owned byNot the promoter
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofSMFG INDIA HOME FINANCE COMPANY LIMITED
Secured amountRs 35.00 crore
CERSAI search filedYes
Declared on14 Jul 2026
LandownerVillageDistrict
Dattatray Maruti GhuleMANJARI BkPune
Suresh Maruti GhuleHadapsarPune
Kailas Maruti GhuleMANJARI BkPune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI14508.5
Proposed, not sanctioned14,508 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchARYAN CENTRE, OPP : VAIBHAV THEATRE PUNE SOLAPUR ROAD, HADAPSAR
Estimated costRs 69.43 cr
Cost incurredRs 2.08 cr
Work done3.0%
BuildingWingEstimatedIncurred
Wing CNARs 19.78 crRs 63.69 lakh
Wing ANARs 19.78 crRs 53.00 lakh
Wing BNARs 19.78 crRs 53.00 lakh
Wing EWSNARs 5.35 crRs 38.79 lakh
-NARs 4.74 cr-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAtit Admulwar
EngineerDnyaneshwar Pawar
Chartered AccountantBankim Patel & Associates
PartnerRole in project
Dhvanil Associates LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalNot on the file

    The planning authority's approval of how the plots and buildings sit on the land.

  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 May 2026
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2030

Documents filed13

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1.pdf15 Jun 2026
Withdrawal Update Form 2File: FORM 2.pdf15 Jun 2026
Withdrawal Update Form 3File: form 3 final (2).pdf15 Jun 2026
Building plan approvalFile: Highlighted Layout 10-09-25.pdf7 May 2026
Building plan approvalFile: Plan 02.pdf23 Jan 2026
Building plan approvalFile: Plan 03.pdf23 Jan 2026
Building plan approvalFile: Plan 04.pdf23 Jan 2026
Building plan approvalFile: Plan 05.pdf23 Jan 2026
Building plan approvalFile: Plan 06.pdf23 Jan 2026
Building plan approvalFile: Plan 07.pdf23 Jan 2026
Building plan approvalFile: Plan 08.pdf23 Jan 2026
Building plan approvalFile: Plan 09.pdf23 Jan 2026
Declaration and undertaking (Annexure A)File: Declaration Cum Undertaking001.pdf18 Dec 2025

How this compares with Pune

6%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Dhvanil Harmony on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Haveli, Pune13,700+ in Pune

2 kmDhvanil HarmonyCompleted 13Lapsed / revoked 7Other 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 45 registered projects within 2 km.

Builder: Dhvanil Associates LLP

Dhvanil Associates LLP has 1 registration on MahaRERA, including Dhvanil Harmony. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Dhvanil Harmony is delayed beyond 30 Jun 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Dhvanil Harmony?

The registered promoter entity is Dhvanil Associates LLP, a limited liability partnership as per the filing. Its LLPIN AAW-9977 and GSTIN 27AASFD4196L2ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Dhvanil Harmony?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Dhvanil Harmony?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Dhvanil Harmony?

The professionals named in the filing: Architect: Atit Admulwar; Engineer: Dnyaneshwar Pawar; Chartered Accountant: Bankim Patel & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Dhvanil Harmony?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Dhvanil Harmony. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Dhvanil Harmony to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.