ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Dhaval CHSL

Completed No litigation declared Residential / Group Housing project

Dhaval CHSL

By Shree Ranchod Developers

RG-MH-66207 · RERA P51800046109 · Last updated on MahaRERA portal: 22 Oct 2024

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
May 2025Possession promisedregistration recorded completed
4 of 11Construction stages donefurthest along: Staircases, 90%
2Complaints at MahaRERAon this registration
Jump to the 45 documents Report an error

Dhaval CHSL is a Residential / Group Housing project by Shree Ranchod Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800046109 on 20 Jun 2022. The registration is recorded completed; possession was promised by 31 May 2025. 2 complaints are on record with the regulator.

At a glance

Project

  • NameDhaval CHSL
  • TypeResidential / Group Housing
  • Location
    • N L Cross Road
    • Malad West
    • Borivali
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • RERA no.P51800046109
  • ReraGenie IDRG-MH-66207

Builder

  • NameShree Ranchod Developers
  • Entity typePartnership
  • GSTIN27ABGFS9836H1ZM
  • PartnersPooja Kunthesh Chheda, Kunthesh Pravin Chheda

Key dates

this monthRegisteredJun 2022PromisedMay 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on20 Jun 2022
  • Promised completion31 May 2025
  • Revised completionNone
  • Buildings1 building record
  • Documents filed45 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Dhaval CHSLNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Oct 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.

Dhaval CHSL: 61% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure77%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities18

As on 22 Oct 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
GymnasiumYes0%
Society OfficeYes0%
Stilt ParkingYes0%

Parking filed20

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots20
Closed/Covered20

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area846 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI2285.55
Proposed, not sanctioned2,282 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSV Road, Andheri West, Mumbai - 400058

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKulin Patrawala
EngineerAshok Kumar Akbari
Chartered AccountantGBCA & Associates LLP
Chartered AccountantKiran Khimshiya & Co
PartnerRole in project
Shree Ranchod Developers-

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12500622Shree Ranchod DevelopersHarshala Jayendra Raut22/02/2025
CC12501191Harshala Jayendra RautShree Ranchod Developers09/04/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Jun 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 May 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jun 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 21 Oct 2024

Documents filed45

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf22 Oct 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate.pdf21 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_Engineer Certificate.pdf23 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dhaval CHSL -Mar'24.pdf23 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 declaration.pdf23 May 2024
Commencement Certificates / NA Order for plotted developmentFile: CC Revalidation.pdf17 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf17 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_Engineer Certificate.pdf15 May 2024
Disclosure of sold/ booked inventoryFile: Disclosure Sold Unsold Letter.pdf15 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 - October 23.pdf18 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - Ranchod Developers.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf17 Jul 2023
Proforma of Agreement for saleFile: Draft Agreement.pdf29 Jun 2023
Deviation Report with respect to model copy of AgreementFile: Deviation from Agreement to Sell.pdf29 Jun 2023
Building plan approvalFile: IOD 1 - Distort.pdf16 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD 1 - Distort.pdf16 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 5 to 9.pdf16 Jun 2022
Proforma of Allotment letterFile: Model Form of Allottment letter - Dhaval CHSL (1).pdf16 Jun 2022
Building plan approvalFile: Sanction Plan 1.pdf15 Jun 2022
Building plan approvalFile: IOD 2.pdf15 Jun 2022
Building plan approvalFile: IOD 3.pdf15 Jun 2022
Building plan approvalFile: IOD 4.pdf15 Jun 2022
Building plan approvalFile: IOD 5.pdf15 Jun 2022
Building plan approvalFile: IOD 6.pdf15 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: Sanction Plan 1.pdf15 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD 2.pdf15 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD 3.pdf15 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD 4.pdf15 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD 5.pdf15 Jun 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD 6.pdf15 Jun 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 1 to 4.pdf15 Jun 2022
Proforma of Allotment letterFile: Model Agreement for Sale.pdf15 Jun 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf13 Jun 2022
Copy of the legal title reportFile: Legal Title Report Declaration.pdf6 Jun 2022
Copy of the legal title reportFile: Title Report - Annexure A.pdf6 Jun 2022
CERSAI detailsFile: CERSAI Declaration and Report.pdf25 May 2022
Layout approvalFile: Layout Declaration.pdf24 May 2022
Building plan approvalFile: IOD.pdf24 May 2022
Details of encumbrancesFile: Encumbrance Certificate.pdf24 May 2022
Copy of Layout Approval (in case of layout)File: Layout Declaration.pdf24 May 2022
Building Plan Approval / NA Order for plotted developmentFile: IOD.pdf24 May 2022
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf24 May 2022
Declaration about Commencement CertificateFile: DECLARATION CC.pdf24 May 2022
Declaration in FORM BFile: Form B - Declaration.pdf24 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 May 2022

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Dhaval CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Malad West6,700+ in Mumbai Suburban

Builder: Shree Ranchod Developers

Shree Ranchod Developers has 1 registration on MahaRERA, including Dhaval CHSL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Dhaval CHSL is delayed beyond 31 May 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Dhaval CHSL?

The registered promoter entity is Shree Ranchod Developers, a partnership as per the filing. Its GSTIN 27ABGFS9836H1ZM can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Dhaval CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Dhaval CHSL?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Dhaval CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Dhaval CHSL?

The professionals named in the filing: Architect: Kulin Patrawala; Engineer: Ashok Kumar Akbari; Chartered Accountant: GBCA & Associates LLP; Chartered Accountant: Kiran Khimshiya & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Dhaval CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Dhaval CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Dhaval CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.