Devashree Park
RG-MH-66405 · RERA P51700015920 · Last updated on MahaRERA portal: 16 Feb 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 34 months past the filed date
- 2 complaints at MahaRERA
- Completion date moved by 21 months
- 3 extensions taken
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
- All 1 earlier projects delivered on promise
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Devashree Park is a Residential / Group Housing project by RAMESH SAWANT in Thane, Maharashtra, registered with MahaRERA as P51700015920 on 9 Apr 2018. Possession was promised by 31 Dec 2023 and is now 34 months past that date. The completion date has moved by 21 months from the original filing. 2 complaints are on record with the regulator.
At a glance
Project
- NameDevashree Park
- TypeResidential / Group Housing
- Location
- KOLSHET ROAD
- KOLSHET
- Thane (M Corp.)
- Thane
- 400607
- Pincode400607
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700015920
- ReraGenie IDRG-MH-66405
Builder
- NameRAMESH SAWANT
- Entity typeIndividual
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on9 Apr 2018
- Promised completion31 Dec 2023
- Revised completionRevised to 31 Dec 2023 (originally 30 Mar 2022)
- Buildings4 building records
- Documents filed57 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building A | NA | 1 | 0 | 0 | 0 | 0 |
| Building B | NA | 1 | 0 | 0 | 0 | 0 |
| Building D | NA | 0 | 0 | 0 | 0 | 0 |
| Row house | NA | 1 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 16 Feb 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
32 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Excavation, at 0%.
Building A100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building B100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building D0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row house91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 16 Feb 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 100% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ten Folds |
| Engineer | Nilesh R Phule |
| Partner | Role in project |
|---|---|
| RAMESH SAWANT | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to the Proprietor's health problems, there was a lack of control in handling and observing the construction work. Hence the proprietor wants to apply to extend the completion date of the project
Reason as filed by the promoterLack of material and labour resources, delay in approvals.
Reason as filed by the promoterThe completion date of the project is being extended due to Covid-19 and lock-down situation.
Complaints filed with MahaRERA2
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000397773 | RAMAKANT DYAWANPALLI | RAMESH SAWANT | 12/10/2023 |
| CC006000000591433 | Navin Kantilal Thakkar | Ms R W Sawant and Co | 06/08/2024 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 26 Mar 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 26 Mar 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Mar 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 26 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 6 Jan 2023
Documents filed57
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Disclosure of sold/ booked inventoryFile: sold unsold.pdf | 16 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Enginner Certificate form 2.pdf | 13 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bricwork_certificate_001.pdf | 7 Feb 2023 |
| Certificates of CA (Form 3)File: Form_3_2021-22.pdf | 6 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 2021-22.pdf | 6 Feb 2023 |
| Disclosure of sold/ booked inventoryFile: sold_unsold_2021-22.pdf | 18 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: sold_unsold_2021-22_.pdf | 18 Jan 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Architect's certificate of completion for plotted development.pdf | 6 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold as on 28-06-2022.pdf | 28 Jun 2022 |
| CERSAI detailsFile: Cersai details.pdf | 24 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: sold units 2018-19.pdf | 24 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: sold units 2019-20.pdf | 24 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: sold units 2020-21.pdf | 24 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: form 5 2018-19.pdf | 24 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 19-20.pdf | 24 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 20-21.pdf | 24 Jun 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 22 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A- 2020-21.pdf | 22 Jun 2022 |
| Certificates of CA (Form 3)File: Form_3_2019_20_Signed[2].pdf | 21 Jun 2022 |
| Certificates of CA (Form 3)File: Form_3_2020_21_Signed[1].pdf | 21 Jun 2022 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 16 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Engineer Certificate July 2020 to March 2020.pdf | 16 Jun 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate Apr 2020 to March 2021.pdf | 16 Jun 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate_11052021.pdf | 15 Jun 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate_28092021.pdf | 15 Jun 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate_18122021.pdf | 15 Jun 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate_25022022.pdf | 15 Jun 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate_17032022.pdf | 15 Jun 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate_20052022.pdf | 15 Jun 2022 |
| OtherFile: Architect Certificate- Form 4.pdf | 3 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 31 Jul 2021 |
| Certificates of CA (Form 3)File: CHARTERED ACCOUNTANT'S CERTIFICATE.pdf | 23 Apr 2020 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Quality Assurance Certificate (Form 2A).pdf | 23 Aug 2019 |
| OtherFile: Resignation letter of Architecture.pdf | 21 Aug 2019 |
| OtherFile: Apointment letter of Architecture.pdf | 21 Aug 2019 |
| OtherFile: Acceptance letter of Architecture.pdf | 21 Aug 2019 |
| Engineers Certificate on Quality Assurance (Form 2A)File: Quality Assurance (Form 2A).pdf | 8 Aug 2019 |
| Certificates of CA (Form 3)File: CA_Certificate.pdf | 4 Apr 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: R_W_SAWANT_ENGINEER_CERTIFICATE.pdf | 3 Apr 2018 |
| Building plan approvalFile: CC_compressed.pdf | 26 Mar 2018 |
| Layout approvalFile: Layout_1_compressed.pdf | 26 Mar 2018 |
| Layout approvalFile: Layout_2_4.pdf | 26 Mar 2018 |
| Layout approvalFile: LAYOUT_5_6.pdf | 26 Mar 2018 |
| Layout approvalFile: Layout_7_8.pdf | 26 Mar 2018 |
| PAN CardFile: PAN CARD.pdf | 26 Mar 2018 |
| Copy of the legal title reportFile: Title Certificate 1.pdf | 26 Mar 2018 |
| Copy of the legal title reportFile: Supplementary Title.pdf | 26 Mar 2018 |
| Details of encumbrancesFile: litication cetificate 001.pdf | 26 Mar 2018 |
| Copy of Layout Approval (in case of layout)File: Layout_1_compressed.pdf | 26 Mar 2018 |
| Copy of Layout Approval (in case of layout)File: Layout_2_4.pdf | 26 Mar 2018 |
| Copy of Layout Approval (in case of layout)File: LAYOUT_5_6.pdf | 26 Mar 2018 |
| Copy of Layout Approval (in case of layout)File: Layout_7_8.pdf | 26 Mar 2018 |
| Building Plan Approval (IOD)File: CC_compressed.pdf | 26 Mar 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC_compressed.pdf | 26 Mar 2018 |
| Declaration in FORM BFile: DECLARARTION IN FORM B.pdf | 26 Mar 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate.pdf | 26 Mar 2018 |
| Proforma of Allotment letterFile: RERA Allottment letter Devashre Park.pdf | 26 Mar 2018 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| DEVASHREE PARK | Kolshet Road kolshet Thane west 400607 | 6 | Completed | Feb 2016 | Feb 2016 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 57 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Devashree Park on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KOLSHET7,600+ in Thane
Filed coordinates, straight-line distance. 142 registered projects within 2 km.
Hiranandani Westgate Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Forestville - Phase 1
Oberoi Realty Limited
DOSTI WEST COUNTY - PHASE 4- DOSTI PINE
DOSTI ENTERPRISES
Y SQUARE
SHREE MALLINATH ENTERPRISE LLP
Primera
Agile Real Estate Dev Private Limited
UNIQUE VISTAS MHADA BUILDINGNO. 4 5 6 7
MADHU HARSHAD DOSHI
See every Thane project, with the district possession charts
Builder: RAMESH SAWANT
RAMESH SAWANT has 1 registration on MahaRERA, including Devashree Park. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Devashree Park shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Devashree Park is delayed beyond 31 Dec 2023?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Devashree Park?
The registered promoter entity is RAMESH SAWANT, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Devashree Park?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Devashree Park?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Devashree Park?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Devashree Park?
The professionals named in the filing: Architect: Ten Folds; Engineer: Nilesh R Phule. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Devashree Park?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.