Home / Browse projects / Thane, Maharashtra / DEV DRASHTI EMPIRE PHASE 1

Registered No litigation declared Others project

DEV DRASHTI EMPIRE PHASE 1

By SHRI HARI REALTY

RG-MH-03277 · RERA P51700020837 · Last updated on MahaRERA portal: 13 Aug 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 32 months
  • 2 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 32 months from the original
9 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
112 of 235Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 133 documents Report an error

DEV DRASHTI EMPIRE PHASE 1 is a Others project by SHRI HARI REALTY in Thane, Maharashtra, registered with MahaRERA as P51700020837 on 15 May 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 32 months from the original filing. 123 of the 235 units on this registration are recorded sold or booked, and 9 of 22 construction stages are filed complete.

At a glance

Project

  • NameDEV DRASHTI EMPIRE PHASE 1
  • TypeOthers
  • Location
    • THANE
    • MIRA BHAYANDER
    • Bhiwandi (M Corp.)
    • Bhiwandi
    • 421302
  • Pincode421302
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700020837
  • ReraGenie IDRG-MH-03277

Builder

  • NameSHRI HARI REALTY
  • Entity typePartnership
  • PartnersNIMESH S THAKKAR, TARUNA NIMESH THAKKAR

Key dates

this monthRegisteredMay 2019First promiseApr 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 May 2019
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Apr 2024)
  • Buildings2 building records
  • Documents filed133 files

Current status

52%123 of 235 units booked
59.6%Work done, per cost certificate

Figures as on 13 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA191814026166
WING BNA181869069

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 13 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

WING A82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes65%
Street LightingYes65%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes75%
Energy managemcntYes75%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes85%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed22

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots22
Open Space22
BuildingOpen SpaceTotal
WING A1111
WING B1111

Land and ownership5

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area3,775 sq m
Land owned byThe promoter
Named landowners5
LandownerVillageDistrict
CHHATRAPATI R CHOUDHARYBhiwandi (M Corp.)Thane
ASHOK RAMCHANDRA PATILBhiwandi (M Corp.)Thane
SHYAM RAMU CHAUDHARY AND OTHERSBhiwandi (M Corp.)Thane
SHRI HARI REALTYMira-Bhayandar (M Corp.)Thane
GURU DAYAL SINGH HIRABhiwandi (M Corp.)Thane

Approvals and building plan

Sanctioning authorityBhiwandi-Nizampur City Municipal Corporation
Permissible FSI9850.74
Proposed, not sanctioned9,851 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchWODEHOUSE ROAD COLABA
Estimated costRs 82.66 cr
Cost incurredRs 49.30 cr
Work done59.64%
BuildingWingEstimatedIncurred
WING ANARs 44.68 crRs 44.68 cr
-NARs 21.73 crRs 4.62 cr
WING BNARs 16.25 cr-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRavish Ab. R. Dhuru
EngineerR R Associates
Chartered AccountantNikita Khemka
PartnerRole in project
SHRI HARI REALTY-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019552Apr 2024 → Apr 2025

Reason as filed by the promoterDue to shortage of marital not able to complete project please grant us extension for 12 months

EA08072502004Apr 2024 → Dec 2026

Reason as filed by the promoterWe request an extension of the project's MahaRERA registration as several critical works under Interior Services and External Development are still in progress and are scheduled for phased completion up to December 2026, as per the detailed PERT chart submitted. While the structural and finishing works were largely completed by March 2024, the remaining work - including electrical meter room installation, rainwater harvesting system, landscaping, driveway, compound lighting, and other external service provisions - require additional time due to: Sequencing of technical and finishing stages, De

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 May 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 13 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 May 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 6 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed133

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 133 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Arct Dec 25.pdf13 Aug 2026
Withdrawal Update Form 1File: Arct March-26.pdf13 Aug 2026
Withdrawal Update Form 1File: Arct June-26.pdf13 Aug 2026
Withdrawal Update Form 2File: Engr Dec 25.pdf13 Aug 2026
Withdrawal Update Form 2File: Engr March-26.pdf13 Aug 2026
Withdrawal Update Form 2File: Engr Jne - 26.pdf13 Aug 2026
Withdrawal Update Form 3File: Form 3 OCt to Dec 25 (2).pdf13 Aug 2026
Withdrawal Update Form 3File: FORM 3 SHR.pdf13 Aug 2026
Withdrawal Update Form 3File: FORM 3 Dev Drashti Empire April to june 26_compressed.pdf13 Aug 2026
Withdrawal Update Form 1File: FORM 1.PDF30 Apr 2026
Withdrawal Update Form 2File: FORM 2.PDF30 Apr 2026
Withdrawal Update Form 3File: FORM 3_compressed.pdf30 Apr 2026
Withdrawal Update Form 1File: FORM 1 (4).PDF19 Feb 2026
Withdrawal Update Form 2File: FORM 2 (3).PDF19 Feb 2026
Withdrawal Update Form 3File: formmmmmmmmm3.pdf19 Feb 2026
Withdrawal Update Form 1File: FORM 1 (4).PDF18 Feb 2026
Withdrawal Update Form 2File: FORM 2 (3).PDF18 Feb 2026
Withdrawal Update Form 3File: form 3.pdf18 Feb 2026
Withdrawal Update Form 1File: form 1.pdf19 Jan 2026
Withdrawal Update Form 2File: form 2.pdf19 Jan 2026
Withdrawal Update Form 3File: form 3.pdf19 Jan 2026
Form 2A (FY 2019-2020)File: form 2a 19-20.pdf17 Jul 2025
Form 2A (FY 2020-2021)File: form 2a 20-21.pdf17 Jul 2025
Form 2A (FY 2021-2022)File: form 2a 21-22.pdf17 Jul 2025
Form 2A (FY 2022-2023)File: form 2a 22-23.pdf17 Jul 2025
Form 2A (FY 2023-2024)File: form 2a 23-24.pdf17 Jul 2025
Form 2A (FY 2024-2025)File: form 2a 24-25.pdf17 Jul 2025
Form 3File: nimesh form3.pdf15 Jul 2025
Form 2File: form2.pdf15 Jul 2025
Form 1File: form1.pdf15 Jul 2025
Disclosure of Sold and Booked InventoryFile: INVENTORY DISCLOSURE_compressed.pdf15 Jul 2025
Certificates of CA (Form 3)File: FORM 3 310325 SHR.pdf10 May 2025
Disclosure of sold/ booked inventoryFile: INVENTORY DISCLOSURE 310325.pdf10 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: CA FORM 5 FY 2425 SHR.PDF10 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 june 24.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 sep 24.pdf29 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 dec 24.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enigneer Jun 24 promotor sign.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Sept 24 promotor sign.pdf29 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Dec 24 promotor sign.pdf29 Jan 2025
Certificates of CA (Form 3)File: FORM-3SHR Revised (1).pdf27 Jan 2025
Certificates of CA (Form 3)File: form 3 dec 24.pdf27 Jan 2025
Certificates of CA (Form 3)File: form 3 july to sep 24.pdf24 Jan 2025
Certificates of CA (Form 3)File: form 3.pdf15 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf16 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf16 May 2024
Disclosure of sold/ booked inventoryFile: Inventory Disclosure - March -2024.pdf8 Apr 2024
Certificates of CA (Form 3)File: FORM 3 revised.pdf6 Feb 2024
Certificates of CA (Form 3)File: FORM-3 - Shri Hari Realty DEC23.pdf15 Jan 2024
Certificates of CA (Form 3)File: FRORM-3 09 23 REVISED.pdf30 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf11 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf11 Oct 2023
Certificates of CA (Form 3)File: shr form 3 30sep 23 rev.pdf9 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT MARCH 2023.PDF30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH CERT JUNE 2023.PDF30 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT MARCH 2023.pdf30 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGG CERT JUNE 2023.PDF30 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Shri Hari Realty Form 5.pdf18 Sep 2023
Certificates of CA (Form 3)File: FORM 3.pdf18 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: form 2A 20-21.PDF1 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A 21-22.pdf1 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 FY19-20.pdf1 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Dec 22 (1).pdf19 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Dec 22.pdf19 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERTIFICATE FORM 2 revisesd.pdf12 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SHR-ARCHITECT CERT.pdf6 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 31032022.pdf30 Sep 2022
Commencement Certificates / NA Order for plotted developmentFile: REVISED CC.pdf6 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect form 1.pdf19 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer form 2.pdf19 Jul 2022
Disclosure of sold/ booked inventoryFile: Inventory Disclosure.pdf25 Apr 2022
Declaration about Commencement CertificateFile: Rera-declaration cc.pdf23 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report_200203221879_For_Debtor_Based_Search_05_11_2020_18_52_58_911.pdf23 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf21 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT FORM 1.pdf19 Apr 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER FORM 2.pdf19 Apr 2022
Layout approvalFile: Sheet 1.pdf13 Apr 2022
Layout approvalFile: Sheet 2.pdf13 Apr 2022
Layout approvalFile: Sheet 3.pdf13 Apr 2022
Layout approvalFile: Sheet 4.pdf13 Apr 2022

How this compares with Thane

52%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 32 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DEV DRASHTI EMPIRE PHASE 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MIRA BHAYANDER7,600+ in Thane

2 kmDEV DRASHTI EMPIRE PHASECompleted 29Lapsed / revoked 24Other 35Dot size: filed unitsN

Filed coordinates, straight-line distance. 88 registered projects within 2 km.

Builder: SHRI HARI REALTY

SHRI HARI REALTY has 1 registration on MahaRERA, including DEV DRASHTI EMPIRE PHASE 1. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if DEV DRASHTI EMPIRE PHASE 1 is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DEV DRASHTI EMPIRE PHASE 1?

The registered promoter entity is SHRI HARI REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DEV DRASHTI EMPIRE PHASE 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DEV DRASHTI EMPIRE PHASE 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DEV DRASHTI EMPIRE PHASE 1?

The professionals named in the filing: Architect: Ravish Ab. R. Dhuru; Engineer: R R Associates; Chartered Accountant: Nikita Khemka. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DEV DRASHTI EMPIRE PHASE 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DEV DRASHTI EMPIRE PHASE 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DEV DRASHTI EMPIRE PHASE 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.