Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2029Possession promisedno revision filed
6 of 11Construction stages donefurthest along: Staircases, 85%
14 of 14Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

Deepa is a Residential / Group Housing project by Akshay Group Promoters And Builders in Pune, Maharashtra, registered with MahaRERA as P52100077720 on 23 Oct 2024. Possession is promised by 20 Jun 2029. 0 of the 14 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete.

At a glance

Project

  • NameDeepa
  • TypeResidential / Group Housing
  • Location
    • Rambaug Colony
    • Kothrud
    • Haveli
    • Pune
    • 411038
  • Pincode411038
  • RERA no.P52100077720
  • ReraGenie IDRG-MH-19437

Builder

  • NameAkshay Group Promoters And Builders
  • Entity typePartnership
  • PartnersHasmukh Bafna, Mangilal Bafna

Key dates

this monthRegisteredOct 2024PromisedJun 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Oct 2024
  • Promised completion20 Jun 2029
  • Revised completionNone
  • Buildings1 building record
  • Documents filed73 files

Current status

0%0 of 14 units booked
72.1%Work done, per cost certificate

Figures as on 30 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DeepaNA5514014

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 85%.

Deepa: 77% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%

Progress on shared amenities15

As on 30 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed29

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots29
Closed/Covered29

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area508 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Feb 2026
LandownerVillageDistrict
Deepa Apartment CondominiumKothrudPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI2030.5
Proposed, not sanctioned1,135 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO.4, GROUND FLOOR, SR NO.12/8, VERTICAL ALCINIA, OPP. CORINTHIANS CLUB, NIBM ROAD, ANNEXE, PUNE, MAHARASHTRA-411060, TOLL FREE NO 18004194332
Estimated costRs 7.94 cr
Cost incurredRs 5.72 cr
Work done72.07%
BuildingWingEstimatedIncurred
DeepaNARs 7.94 crRs 5.72 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGroup Consultants
EngineerPrassana Bhumkar
EngineerAshutosh Nighut
EngineerShankar Bade
Chartered AccountantV.B. Jain & Associates
PartnerRole in project
Akshay Group Promoters And Builders-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Oct 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 20 Jun 2029

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 AGPB.pdf30 Apr 2026
Withdrawal Update Form 1File: FORM 1 AGPB.pdf30 Apr 2026
Withdrawal Update Form 1File: FORM 1 AGPB.pdf30 Apr 2026
Withdrawal Update Form 2File: FORM 2 AGPB.pdf30 Apr 2026
Withdrawal Update Form 2File: FORM 2 AGPB.pdf30 Apr 2026
Withdrawal Update Form 2File: FORM 2 AGPB.pdf30 Apr 2026
Withdrawal Update Form 3File: FORM 3 AGPB.pdf30 Apr 2026
Withdrawal Update Form 3File: FORM 3 AGPB.pdf30 Apr 2026
Withdrawal Update Form 3File: FORM 3 AGPB.pdf30 Apr 2026
Form 2A (FY 2024-2025)File: AGPB 2A.pdf6 Oct 2025
Form 5 (FY 2024-2025)File: AGPB FORM 5.pdf6 Oct 2025
Building plan approvalFile: Sanction 3_1.pdf25 Jul 2025
Building plan approvalFile: Sanction 3_2.pdf25 Jul 2025
Form 1File: FORM 1.pdf19 Jul 2025
Form 2File: FORM 2.pdf19 Jul 2025
Form 3File: FORM 3_compressed.pdf19 Jul 2025
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD.pdf19 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sold Unsold.pdf20 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2.pdf27 Jan 2025
Disclosure of sold/ booked inventoryFile: D1.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1.pdf27 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F3.pdf27 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F2.pdf27 Jan 2025
Disclosure of sold/ booked inventoryFile: D1.pdf27 Jan 2025
Proforma of Agreement for saleFile: Agreement Revised.pdf29 Oct 2024
Proforma of Agreement for saleFile: Agreement Revised.pdf29 Oct 2024
Proforma of Agreement for saleFile: Agreement Revised.pdf29 Oct 2024
Building plan approvalFile: Deepa Apartment 2nd Sanction_compressed.pdf26 Oct 2024
Building plan approvalFile: Deepa Apartment 2nd Sanction_compressed.pdf26 Oct 2024
Building plan approvalFile: Deepa Apartment 2nd Sanction_compressed.pdf26 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: Deepa Apartment 2nd Commencement Certificate.pdf26 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Deepa Apartment 2nd Sanction_compressed.pdf26 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: Deepa Apartment 2nd Commencement Certificate.pdf26 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Deepa Apartment 2nd Sanction_compressed.pdf26 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: Deepa Apartment 2nd Commencement Certificate.pdf26 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Deepa Apartment 2nd Sanction_compressed.pdf26 Oct 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Letter_Finance.pdf12 Oct 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Letter_Legal.pdf12 Oct 2024
Details of encumbrances concerned to LegalFile: Encumbrance Letter_Finance.pdf12 Oct 2024
Details of encumbrances concerned to LegalFile: Encumbrance Letter_Legal.pdf12 Oct 2024
Other - TechnicalFile: Letter Regarding Accounts Of The Landowner Condominium.pdf11 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA_Form3.pdf8 Oct 2024
CERSAI detailsFile: DECLARATION ABOUT CERSAI.pdf8 Oct 2024
Deviation Report with respect to model copy of AgreementFile: Deviations_Agreement For Sale_AGPB.pdf8 Oct 2024
Proforma of Agreement for saleFile: Agreement For Sale_AGPB.pdf8 Oct 2024
Building plan approvalFile: Sanction Plan.pdf7 Oct 2024
Layout approvalFile: Sanction Plan.pdf7 Oct 2024
PAN CardFile: FIRM PAN CARD (1).pdf7 Oct 2024
Copy of the legal title reportFile: Legal Title Report-2.pdf7 Oct 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Letter_Legal.pdf7 Oct 2024
Copy of Layout Approval (in case of layout)File: Sanction Plan.pdf7 Oct 2024
Proforma of Allotment letterFile: Allotment Letter_AKPB.pdf7 Oct 2024
Declaration in FORM BFile: Form B_AGPB.pdf7 Oct 2024
Declaration in FORM BFile: Form B_Deepa Apartment Condominium.pdf7 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect_Form1.pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer_Form2.pdf7 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: 01-CC (2).pdf7 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Sanction Plan.pdf7 Oct 2024
Declaration about Commencement CertificateFile: Declaration About Commencemnt Certificate.pdf7 Oct 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A_Declaration about RERA Designated Bank Accounts for Real Estate Projects.pdf7 Oct 2024
Deviation Report with respect to Allotment letterFile: Deviations_Allotment Letter_AKPB.pdf7 Oct 2024
Details of encumbrances concerned to LegalFile: Encumbrance Letter_Legal.pdf7 Oct 2024
Other - TechnicalFile: Annexure A.pdf7 Oct 2024
Other - TechnicalFile: Authority Letter.pdf7 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Of Interest_Hasmukh Bafna.pdf7 Oct 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Of Interest_Mangilal Bafna.pdf7 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B_Opening of RERA Designated Bank Accounts.pdf7 Oct 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure Of Secured Unsecured Finance.pdf7 Oct 2024

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Deepa on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Rambaug Colony13,700+ in Pune

Builder: Akshay Group Promoters And Builders

Akshay Group Promoters And Builders has 1 registration on MahaRERA, including Deepa. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Deepa is delayed beyond 20 Jun 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Deepa?

The registered promoter entity is Akshay Group Promoters And Builders, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Deepa?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Deepa?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Deepa?

The professionals named in the filing: Architect: Group Consultants; Engineer: Prassana Bhumkar; Engineer: Ashutosh Nighut; Engineer: Shankar Bade; Chartered Accountant: V.B. Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Deepa?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Deepa. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Deepa to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.