ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / DATTAVIHAR

Completed No litigation declared Residential / Group Housing project

DATTAVIHAR

By SHARDA VASTU NIRMITEE PVT. LTD.

RG-MH-30662 · RERA P51700030923 · Last updated on MahaRERA portal: 29 Nov 2024

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2024Possession promisedregistration recorded completed
7 of 11Construction stages donefurthest along: Installation of Lifts, 80%
0Complaints at MahaRERAon this registration
Jump to the 103 documents Report an error

DATTAVIHAR is a Residential / Group Housing project by SHARDA VASTU NIRMITEE PVT. LTD. in Thane, Maharashtra, registered with MahaRERA as P51700030923 on 29 Sep 2021. The registration is recorded completed; possession was promised by 31 Mar 2024.

At a glance

Project

  • NameDATTAVIHAR
  • TypeResidential / Group Housing
  • Location
    • SHIVAJI NAGAR ROAD
    • THANE
    • Thane (M Corp.)
    • 400602
  • Pincode400602
  • RERA no.P51700030923
  • ReraGenie IDRG-MH-30662

Builder

  • NameSHARDA VASTU NIRMITEE PVT. LTD.
  • Entity typeCompany
  • CINU45400MH2010PTC209309
  • DirectorsANKIT HEMENDRA SHAH, MAHESH MAVJI SHARDA
  • Managing DirectorHEMENDRA MAVJI SHAH
  • Other registrations5 more →
  • Completed4 of 6
  • Past their filed date1
  • Declared earlier projects3 →

Key dates

this monthRegisteredSep 2021PromisedMar 2024Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Sep 2021
  • Promised completion31 Mar 2024
  • Revised completionNone
  • Buildings1 building record
  • Documents filed103 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
DATTAVIHARNA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 29 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 80%.

DATTAVIHAR: 71% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 29 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed31

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots31
Closed/Covered31

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,130 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SHREE DATTAVIHAR CHS LTD.Thane (M Corp.)Thane

Approvals and building plan

Sanctioning authorityThane Municiple Corporation
Permissible FSI4017.18
Proposed, not sanctioned4,017 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchM G ROAD

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGodbole Mukadam & Associates
EngineerR.C. Tipnis
Chartered AccountantShet & Associates
Chartered AccountantA K O R D & Co
Chartered AccountantRoshan Gawde & Co
PartnerRole in project
SHARDA VASTU NIRMITEE PVT. LTD.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019244Mar 2024 → Mar 2025

Reason as filed by the promoter1). As per the 1st Approval under the prevailing development control rules, the project was proposed and approved as Stilt + 7th Upper floors having in all 35 flats. 2). After implementation of UDCPR , the project has been proposed and approved as Stilt + 8th upper Floors having in all 56 Flats. The necessary details are already submitted to MAHARERA authority. The delay is because of increased floors and numbers of flats i.e size of the project..

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 15 Sep 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Sep 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Sep 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 29 Nov 2024

Documents filed103

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4_Completion Certificate_Dattvihar.pdf29 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC PDF.pdf29 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final Form 5_FY 23-24_DV_compressed.pdf9 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_Q1.pdf24 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_FY 2023-24.PDF24 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final_Dattavihar_Form 3_Q1_FY 24-25.pdf24 Jul 2024
Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf22 Jul 2024
Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf22 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - SIGNED.pdf22 Jul 2024
CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf22 Jul 2024
CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_Q4.pdf6 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3_Q4.pdf6 May 2024
Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf2 May 2024
Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf2 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_Q4.pdf2 May 2024
Disclosure of sold/ booked inventoryFile: REVISED_Annexure B-Disclosure of Sold or Unsold Inventory.pdf2 May 2024
CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf2 May 2024
CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf2 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Dattavihar_Q3_compressed.pdf24 Jan 2024
Details of encumbrances concerned to FinanceFile: 3 - Annexure K-Non-Encumbrance Concerned to Finance.pdf23 Jan 2024
Details of encumbrances concerned to LegalFile: 3 - Annexure K-Non-Encumbrance Concerned to Finance.pdf23 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_Q3.pdf23 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - TIPNIS - CF.pdf23 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_311223.pdf23 Jan 2024
Disclosure of sold/ booked inventoryFile: 4 - REVISED_Annexure B-Disclosure of Sold or Unsold Inventory.pdf23 Jan 2024
CERSAI detailsFile: 1 - Annexure L- Debtor Based Declaration.pdf23 Jan 2024
CERSAI detailsFile: 2 - Annexure G-Asset Based Declaration.pdf23 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Dattavihar_Q2_Signed.pdf22 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 _Dattavihar FY 22-23_compressed.pdf9 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 _Dattavihar FY 22-23_compressed.pdf9 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Q2 (July- September 23).pdf21 Oct 2023
Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf20 Oct 2023
Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf20 Oct 2023
CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf20 Oct 2023
CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf20 Oct 2023
Disclosure of sold/ booked inventoryFile: REVISED_Annexure B-Disclosure of Sold or Unsold Inventory.pdf20 Oct 2023
Layout approvalFile: PLAN - 6-3-23.pdf15 Sep 2023
Copy of Layout Approval (in case of layout)File: PLAN - 6-3-23.pdf15 Sep 2023
Commencement Certificates / NA Order for plotted developmentFile: AMENDED CC - 6-3-23.pdf15 Sep 2023
Declaration about Commencement CertificateFile: Declaration about CC-DATTAVIHAR.pdf15 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - DATTAVIHAR_compressed.pdf31 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_Q1.pdf24 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - TIPNIS - CF.pdf24 Aug 2023
Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf29 Jul 2023
Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Finance.pdf29 Jul 2023
Disclosure of sold/ booked inventoryFile: Annexure B-Disclosure of Sold or Unsold Inventory.pdf29 Jul 2023
CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf29 Jul 2023
CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf29 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A - DATTA VIHAR.pdf26 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - DATTAVIHAR.pdf16 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1- 31-3-23.pdf6 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 dtd 04042023.pdf6 May 2023
Disclosure of sold/ booked inventoryFile: 100423_Annexure BDisclosure of Sold or Unsold Inventory.pdf6 May 2023
Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Legal.pdf20 Apr 2023
Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Legal.pdf20 Apr 2023
CERSAI detailsFile: Annexure G-Asset Based Declaration.pdf20 Apr 2023
CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf20 Apr 2023
Disclosure of sold/ booked inventoryFile: Annexure B-Disclosure of Sold or Unsold Inventory.pdf20 Apr 2023
Details of encumbrances concerned to FinanceFile: Annexure K-Non-Encumbrance Concerned to Legal.pdf20 Mar 2023
Details of encumbrances concerned to LegalFile: Annexure K-Non-Encumbrance Concerned to Legal.pdf20 Mar 2023
Disclosure of sold/ booked inventoryFile: Annexure B-Disclosure of Sold or Unsold Inventory.pdf20 Mar 2023
CERSAI detailsFile: Annexure G-Asset Based Declaration1.pdf20 Mar 2023
CERSAI detailsFile: Annexure L- Debtor Based Declaration.pdf20 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - DVIHAR.pdf8 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5- FY 2021-22 - DATTA VIHAR.pdf6 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Roshan.pdf2 Nov 2022
Disclosure of sold/ booked inventoryFile: Disclosure of Sold or Unsold Inventory.pdf21 Oct 2022
Layout approvalFile: PLAN - SHEET 1 - 7-6-2022_compressed.pdf20 Oct 2022
Layout approvalFile: PLAN - SHEET 2 - 7-6-2022_compressed.pdf20 Oct 2022
Layout approvalFile: PLAN - SHEET 3 - 7-6-2022_compressed.pdf20 Oct 2022
Details of encumbrances concerned to LegalFile: NonEncumbrance Concerned to Finance LegalDATTAVIHARQ22223.pdf20 Oct 2022
Copy of Layout Approval (in case of layout)File: PLAN - SHEET 1 - 7-6-2022_compressed.pdf20 Oct 2022
Copy of Layout Approval (in case of layout)File: PLAN - SHEET 2 - 7-6-2022_compressed.pdf20 Oct 2022
Copy of Layout Approval (in case of layout)File: PLAN - SHEET 3 - 7-6-2022_compressed.pdf20 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: AMENDED CC 07062022.pdf20 Oct 2022
Declaration about Commencement CertificateFile: Declaration about CC-DATTAVIHAR-Q2-22-23.pdf20 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CF - FORM 1 - 2-9-22.pdf20 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CF - FORM 2.pdf20 Oct 2022
Proforma of Allotment letterFile: AGREEMENT FOR SALE - DRAFT.pdf20 Oct 2022

Promoter's earlier projects3

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
JEEVAN CHS LTDRAVI COMPOUND PANCHPAKHADI41CompletedOct 2022Late, Jan 2023
MAITHILI CHS LTDRAVI COMPOUND PANCHPAKHADI THANE26CompletedMar 2019Feb 2019
GANESH KRIPANEAR GURUKUL SOCIETY PANCHPAKHADI THANE WEST17CompletedAug 2016May 2016

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DATTAVIHAR on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near THANE7,600+ in Thane

Builder: SHARDA VASTU NIRMITEE PVT. LTD.

SHARDA VASTU NIRMITEE PVT. LTD. has 6 registrations on MahaRERA, including Maithili and JEEVAN CHS LTD. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if DATTAVIHAR is delayed beyond 31 Mar 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DATTAVIHAR?

The registered promoter entity is SHARDA VASTU NIRMITEE PVT. LTD., a company as per the filing. Its CIN U45400MH2010PTC209309 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DATTAVIHAR?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DATTAVIHAR?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DATTAVIHAR?

The professionals named in the filing: Architect: Godbole Mukadam & Associates; Engineer: R.C. Tipnis; Chartered Accountant: Shet & Associates; Chartered Accountant: A K O R D & Co; Chartered Accountant: Roshan Gawde & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DATTAVIHAR?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DATTAVIHAR. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DATTAVIHAR to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.