Dattatray Residency
RG-MH-21221 · RERA P52900007388 · Last updated on MahaRERA portal: 31 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 1 complaint at MahaRERA
- Completion date moved by 104 months
- 5 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Sindhudurg registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Dattatray Residency is a Others project by Sana Homes Private Limited in Sindhudurg, Maharashtra, registered with MahaRERA as P52900007388 on 17 Aug 2017. Possession is promised by 31 May 2028. The completion date has moved by 104 months from the original filing. 1 complaint is on record with the regulator.
At a glance
Project
- NameDattatray Residency
- TypeOthers
- Location
- Malvan Kasal Road
- Kumbharmath
- Malwan
- Sindhudurg
- 416606
- Pincode416606
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52900007388
- ReraGenie IDRG-MH-21221
Builder
- NameSana Homes Private Limited
- Entity typeCompany
- GSTIN27AAOCS3447G1Z1
- Managing DirectorDarshana Mahen Dholam
- DirectorDeepali Jayesh Chawda
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on17 Aug 2017
- Promised completion31 May 2028
- Revised completionRevised to 31 May 2028 (originally 30 Sep 2019)
- Buildings4 building records
- Documents filed83 files
Current status
Figures as on 31 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Blossom Wing A,B,C | NA | 6 | 0 | 0 | 0 | 0 |
| Daffodil Wing D,E | NA | 5 | 0 | 0 | 0 | 0 |
| Orchid Wing F,G,H | NA | 5 | 0 | 0 | 0 | 0 |
| Sana Pride | NA | 4 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 31 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
18 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 90%.
Blossom Wing A,B,C87%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Daffodil Wing D,E75%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 50% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 40% |
Orchid Wing F,G,H70%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 80% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
Sana Pride0%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 31 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 40% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 40% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 10% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed162
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| Blossom Wing A,B,C | 54 | 54 |
| Daffodil Wing D,E | 43 | 43 |
| Orchid Wing F,G,H | 18 | 18 |
| Sana Pride | 47 | 47 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Blossom Wing A,B,C | NA | Rs 8.46 cr | Rs 8.46 cr |
| Daffodil Wing D,E | NA | Rs 4.47 cr | Rs 4.46 cr |
| Orchid Wing F,G,H | NA | Rs 2.60 cr | Rs 3.51 cr |
| Sana Pride | NA | Rs 2.35 cr | - |
| - | NA | Rs 2.04 cr | Rs 1.45 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Taywade Patil & Associates |
| Engineer | Khurd V G |
| Engineer | Nikhil Vijay Nemalekar |
| Engineer | Nikhil M Dalvi |
| Chartered Accountant | Prasad Koyande & Co |
| Partner | Role in project |
|---|---|
| Sana Homes Private Limited | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterPandemic COVID 19 and non availability of labour and material, Heavy Rain. detailed letter attached
Reason as filed by the promoterDelay in getting height permission from 12 mtr to 15 mtr .(Application dated 01/06/2017 and permission received on 30/08/2019), Sand not available due to non opening of tender by Sindhudurga Collector from September 2017 to February 2018. Heavy rain and flood in the monsoon for the period June 2018 to August 2018 and June, 2019 to October, 2019. Malvan in Sindhudurga is 516 km away from Mumbai and due to weather problem difficulty in arrangement of labour etc.
Reason as filed by the promoterCOVID-19 pandemic, shortage of skilled labour, change in material credit policies in the market, extended rain till October, 22. Due to first festival after COVID-19 out of state resumed the work by February-March 2023. Also unseasonal Monsoon in the month of March and April 2023 finishing, waterproofing work affected. Coming heavy monsoon in Konkan region will also delay the finishing work. Commercial building work not yet started. OC procedure of four buildings will take time. so need extension.
Reason as filed by the promoterSince COVID-19 pandemic we are facing shortage of skilled labour and change in credit policies in the market, which affect construction work a lot. Our project is in the rural area therefore we face lots of transportation and other problems. In the year 2024 we were unable to speed up work as there was a heavy rain from June, 2024 till September, 2024 and unexpected rainfall in Konkan region due to cyclone in south India in the month of October, 2024 and November, 2024. Due to festivals like Holi and Gudi Padawa out of state labour did not resume the work in February and March 2024. Our water
Reason as filed by the promoterTill date we have completed 100% work of Building No. 1, 80% work of Building No. 2 and 70% work of Building No. 3. All are residential buildings. We have not yet started work of Commercial-cum-residential Building. As we are planning to complete the work of residential buildings first; we have not sold a single unit in commercial-cum-residential building. Since COVID-19 pandemic we are facing shortage of skilled labour and change in credit policies in the market, which affect construction work a lot. Our project is in the rural area therefore we face lots of transportation and other problems.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000303671 | ASHOK RAGHUNATH ANGANE | SANA HOMES PVT LTD | 21/12/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Dec 2019 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 26 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Nov 2019Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 May 2028
Documents filed83
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 83 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2023-2024)File: Nikhil Dalvi cert 2A 2023-24.pdf | 31 May 2026 |
| Form 2A (FY 2024-2025)File: Form 2A-2024-25.pdf | 31 May 2026 |
| Form 5 (FY 2023-2024)File: Prasad Koyande form 5 23-24.pdf | 31 May 2026 |
| Withdrawal Update Form 1File: Form 1.pdf | 27 May 2026 |
| Withdrawal Update Form 1File: Form 1 -.pdf | 27 May 2026 |
| Withdrawal Update Form 1File: Form 1 -.pdf | 27 May 2026 |
| Withdrawal Update Form 1File: Form 1 -.pdf | 27 May 2026 |
| Withdrawal Update Form 1File: Form 1_compressed.pdf | 27 May 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 27 May 2026 |
| Withdrawal Update Form 2File: Form 2 -.pdf | 27 May 2026 |
| Withdrawal Update Form 2File: Form 2 -.pdf | 27 May 2026 |
| Withdrawal Update Form 2File: Form 2 -.pdf | 27 May 2026 |
| Withdrawal Update Form 2File: Form 2_compressed.pdf | 27 May 2026 |
| Withdrawal Update Form 3File: Form 3.pdf | 27 May 2026 |
| Withdrawal Update Form 3File: Form 3 -.pdf | 27 May 2026 |
| Withdrawal Update Form 3File: Form 3 -.pdf | 27 May 2026 |
| Withdrawal Update Form 3File: Form 3 -.pdf | 27 May 2026 |
| Withdrawal Update Form 3File: Form 3_compressed.pdf | 27 May 2026 |
| Form 2A (FY 2025-2026)File: Form 2A-2025-26.pdf | 22 May 2026 |
| Form 5 (FY 2024-2025)File: Form 5 FY 2024-25.pdf | 22 May 2026 |
| Form 1File: Form 1_compressed.pdf | 21 May 2026 |
| Form 2File: Form 2_compressed.pdf | 21 May 2026 |
| Form 3File: Form 3_compressed.pdf | 21 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Booked and Sold Inventory as on 31 Mar 2026_compressed.pdf | 21 May 2026 |
| Form 1File: Form 1 - 31-12-2025.pdf | 10 Feb 2026 |
| Form 2File: Form 2 - 31-12-2025.pdf | 10 Feb 2026 |
| Form 3File: Form 3 as on 31-12-2025.pdf | 10 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: Booked and Sold Inventory 31-12-2025.pdf | 10 Feb 2026 |
| Form 1File: Form 1.pdf | 12 Jun 2025 |
| Form 2File: Form 2.pdf | 12 Jun 2025 |
| Form 3File: Form 3.pdf | 12 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold & Booked inventory- 31-05-2025.pdf | 12 Jun 2025 |
| Details of encumbrances concerned to FinanceFile: No encumbrance declaration.pdf | 3 Feb 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Designated Bank Account Format A_compressed.pdf | 3 Feb 2025 |
| Details of encumbrances concerned to LegalFile: No encumbrance declaration.pdf | 3 Feb 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: No encumbrance declaration.pdf | 3 Feb 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engn Certificate_compressed.pdf | 28 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: Sold inventory -28-12-2024_compressed.pdf | 28 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCH CERTIFICATE.pdf | 27 Dec 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed.pdf | 27 Dec 2024 |
| Certificates of CA (Form 3)File: Form 3_compressed.pdf | 27 Dec 2024 |
| Certificates of CA (Form 5)File: Form 5 2023-24.pdf | 27 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 27 Dec 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 2023-24.pdf | 27 Dec 2024 |
| Declaration about Commencement CertificateFile: Format D.pdf | 12 Jul 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5.pdf | 12 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 29 Jun 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 29 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf | 29 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Booked Inventory.pdf | 29 Jun 2023 |
| Certificates of CA (Form 3)File: form 3.pdf | 29 Jun 2023 |
| Certificates of CA (Form 5)File: Form 5.pdf | 29 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: Disclosure of sold inventory.pdf | 22 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCH CERTIFICATE.pdf | 18 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE.pdf | 18 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: CA certificate 18-19 form-5.pdf | 18 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: New Forms 5-2021-22.pdf | 18 Jan 2023 |
| Proforma of Agreement for saleFile: Proforma Agreement to sale.pdf | 18 Jan 2023 |
| Proforma of Allotment letterFile: proforma Allotment Letter.pdf | 18 Jan 2023 |
| CERSAI detailsFile: CREDAI cert.pdf | 8 Jun 2022 |
| Disclosure of sold/ booked inventoryFile: Bookings as aon 30 April 2022.pdf | 8 Jun 2022 |
| Certificates of CA (Form 3)File: Form 3.pdf | 8 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 2019-20.pdf | 8 Jun 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 2020-21.pdf | 8 Jun 2022 |
| Layout approvalFile: Building layout.pdf | 12 Dec 2019 |
| Copy of Layout Approval (in case of layout)File: Building layout.pdf | 12 Dec 2019 |
| Certificates of CA (Form 5)File: CA certificate 18-19 form-5.pdf | 12 Dec 2019 |
| Commencement Certificates / NA Order for plotted developmentFile: Height permission.pdf | 27 Nov 2019 |
| Certificates of CA (Form 5)File: CA cert Form-5.pdf | 10 Oct 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 15 Jan 2018 |
| Building plan approvalFile: Declaration on IOD CC.pdf | 26 Jul 2017 |
| Details of encumbrancesFile: No Encumbarances.pdf | 26 Jul 2017 |
| Building Plan Approval (IOD)File: Declaration on IOD CC.pdf | 26 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate cum NA Order.pdf | 26 Jul 2017 |
| Declaration in FORM BFile: Form B affidavit.pdf | 26 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECTS CERTIFICATE.pdf | 26 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2.pdf | 26 Jul 2017 |
| Certificates of CA (Form 3)File: Form3-compressed.pdf | 26 Jul 2017 |
| Proforma of Allotment letterFile: proforma Allotment letter Sale Agreement conveyance.pdf | 26 Jul 2017 |
| Layout approvalFile: Layout 2017-11-29-compressed.pdf | 25 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Sindhudurg
Computed across the 530+ Sindhudurg projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 83 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Dattatray Residency on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kumbharmath530+ in Sindhudurg
Filed coordinates, straight-line distance. 19 registered projects within 2 km.
ATHANG SAI HOMES on S No 32/8/2 and 34/1B of V
Chandrashekhar Suryakant Morvekar
Siddhivinayak Residency
Vastu Builder & Land Developer
SEA MERIDIAN
SKY INFRASTRUCTURE
ATHANG LAXMI
Chandrashekhar Suryakant Morvekar
SEA PEARL
HIRAYA CONSTRUCTIONS LLP
AYAANS AMBARY
Suman Developers
See every Sindhudurg project, with the district possession charts
Builder: Sana Homes Private Limited
Sana Homes Private Limited has 1 registration on MahaRERA, including Dattatray Residency. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Sindhudurg district page.
Frequently asked questions
What are my rights if Dattatray Residency is delayed beyond 31 May 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Dattatray Residency?
The registered promoter entity is Sana Homes Private Limited, a company as per the filing. Its GSTIN 27AAOCS3447G1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Dattatray Residency?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Dattatray Residency?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Dattatray Residency?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Dattatray Residency?
The professionals named in the filing: Architect: Taywade Patil & Associates; Engineer: Khurd V G; Engineer: Nikhil Vijay Nemalekar; Engineer: Nikhil M Dalvi; Chartered Accountant: Prasad Koyande & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Dattatray Residency?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.