Home / Browse projects / Satara, Maharashtra / Dattakrupa Apartment
Dattakrupa Apartment
RG-MH-23061 · RERA P52700033368 · Last updated on MahaRERA portal: 7 Jul 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 53 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Dattakrupa Apartment is a Residential / Group Housing project by SAGAR MAHADEV JARAD in Satara, Maharashtra, registered with MahaRERA as P52700033368 on 16 Feb 2022. Possession is promised by 30 Jun 2029. The completion date has moved by 53 months from the original filing.
At a glance
Project
- NameDattakrupa Apartment
- TypeResidential / Group Housing
- Location
- RAJAVLI BABA
- BACK SITE OF REGISTRAR OFFICE
- Khandala
- Satara
- 412802
- Pincode412802
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52700033368
- ReraGenie IDRG-MH-23061
Builder
- NameSAGAR MAHADEV JARAD
- Entity typeIndividual
- Other registrations1 more →
- Completed1 of 2
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on16 Feb 2022
- Promised completion30 Jun 2029
- Revised completionRevised to 30 Jun 2029 (originally 10 Jan 2025)
- Buildings2 building records
- Documents filed81 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DATTAKRUPA APARTMENT A WING | NA | 6 | 0 | 0 | 0 | 0 |
| Dattakrupa Apartment B Wing | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 7 Jul 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 20%.
DATTAKRUPA APARTMENT A WING2%
| Activity | Progress |
|---|---|
| Excavation | 5% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 20% |
Dattakrupa Apartment B Wing91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 7 Jul 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed30
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| DATTAKRUPA APARTMENT A WING | 6 | 3 | 9 |
| Dattakrupa Apartment B Wing | 21 | 0 | 21 |
Land and ownership2
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SAGAR MAHADEV JARAD | Khandala | Satara |
| Keshav Tukaram Raut | Khandala | Satara |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Rahul Hanuamant Bhokre |
| Engineer | MANGESH AVINASH LAWAND |
| Chartered Accountant | Kumudini Pravin Chavan |
| Chartered Accountant | GANESH KHATAVKAR AND ASSOCIATES |
| Partner | Role in project |
|---|---|
| SAGAR MAHADEV JARAD | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDue to COVIDE 19 we are not getting booking as we have expected in early phase so we have decided to complete one by one wing. So we decide to start Wing B from our project and first to complete completed our B WING and also received OC from planning department for wing B and just start A WING of project and .We have hand over the sold flats to Alloties of Wing B . AND WING A HAS BEEN REVISED SANCTION ON 27-03-2025 AND ALSO UPLOADED ON RERA We are in planning to get revised our drawing and convert our offices spaces to residential area as per local public demand and customers afterward we will
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Feb 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Dec 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Jul 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Apr 2025
Documents filed81
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 81 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Building plan approvalFile: NEW PLAN 111.pdf | 7 Jul 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: FINAL CERTIFICATE NEW.pdf | 7 Jul 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: NEW PLAN 111.pdf | 7 Jul 2025 |
| Declaration about Commencement CertificateFile: DEC CC NEW.pdf | 7 Jul 2025 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: wing b society.pdf | 30 Jun 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: AXIS BANK RERA AC NO.pdf | 4 Jun 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form no 3 march 23.pdf | 26 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form no 3 JUNE 23.pdf | 26 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form no 3 SEPT 23.pdf | 26 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form no 3 dec 23.pdf | 26 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form no 3 march 24.pdf | 26 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form no 3 JUNE 24.pdf | 26 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form no 3 SEPT 24.pdf | 26 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form no 3 dec 24.pdf | 26 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form no 3 march 25.pdf | 26 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no 1 june 22.PDF | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no 1 MARCH 22.PDF | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no 1 march 25.PDF | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no 2 dec 24.pdf | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no 1 sept 24.PDF | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no 1 june 24.PDF | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no 1 march 24.PDF | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 2 Architect’s Certificate of Percentage of Completion of Work (Form 1) DEC 23.pdf | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)SEPT 23.pdf | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no 1 june 23.PDF | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no 1 march 23.PDF | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no 1dec 22.PDF | 22 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form no 2 sept 22.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 Engineer’s Certificate on Cost Incurred on Project (Form 2) MARCH 25.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no 2 dec 24.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no 2 sept 24.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no 2 june 24.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no 2 march 24.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no 2 dec 23.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no 2 sept 23.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no 2 june 23.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no 2 march 23.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no 1dec 22.PDF | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no 2 sept 22.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no 2 june 22.pdf | 22 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form no 2 MARCH 22.pdf | 22 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3 ca.PDF | 18 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf | 18 Apr 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: DATTAKRUPA APARTMENT PART COMPLETION CERTIFICATE.pdf | 18 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2a 22- 23.pdf | 18 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 22- 23.pdf | 18 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 2a 23-24.pdf | 18 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 23-24.pdf | 18 Apr 2025 |
| Declaration in FORM BFile: FORMAT B.pdf | 9 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH.PDF | 9 Jan 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PART OC.PDF | 9 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD INVENTORY.PDF | 9 Jan 2025 |
| Proforma of Agreement for saleFile: 1 Proforma of Allotment letter (1).pdf | 9 Jan 2025 |
| Details of encumbrances concerned to FinanceFile: ENCUMBERANCE.PDF | 13 Jun 2024 |
| Details of encumbrances concerned to LegalFile: ENCUMBERANCE.PDF | 13 Jun 2024 |
| Declaration about Commencement CertificateFile: DEC CC.PDF | 13 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH SEPT 23.PDF | 13 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH DEC 23.PDF | 13 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH MARCH 24.PDF | 13 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG MARCH 2024.PDF | 13 Jun 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA MARCH 2024.PDF | 13 Jun 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: INTEREST.PDF | 13 Jun 2024 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.PDF | 13 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK.PDF | 13 Jun 2024 |
| Deviation Report with respect to Allotment letterFile: DEV ALLOTMENT.PDF | 13 Jun 2024 |
| Deviation Report with respect to model copy of AgreementFile: DEV AGGREMENT.PDF | 13 Jun 2024 |
| Building plan approvalFile: scan0137_compressed.pdf | 7 Feb 2022 |
| Copy of the legal title reportFile: Legal Tital Report _Final_1.pdf | 7 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: scan0137_compressed.pdf | 7 Feb 2022 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT COMMENCEMENT CERTIFICATE PDF.pdf | 7 Feb 2022 |
| Building plan approvalFile: 136 - Copy.pdf | 6 Feb 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: 136 - Copy.pdf | 6 Feb 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement certificate.pdf | 6 Feb 2022 |
| CERSAI detailsFile: CERSAI REPORT DATTAKRUPA APARTMENT.pdf | 4 Feb 2022 |
| Declaration in FORM BFile: Form B.pdf | 27 Dec 2021 |
| Layout approvalFile: n a layout-converted.pdf | 24 Dec 2021 |
| Copy of Layout Approval (in case of layout)File: n a layout-converted.pdf | 24 Dec 2021 |
| Proforma of Allotment letterFile: SELL AGGRIMENET PDF.pdf | 19 Dec 2021 |
| PAN CardFile: sagar pan card.pdf | 18 Dec 2021 |
| Details of encumbrancesFile: encumbrance letter_Letter Head.pdf | 18 Dec 2021 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Satara
Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 81 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Dattakrupa Apartment on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near BACK SITE OF REGISTRAR OFFICE1,100+ in Satara
Filed coordinates, straight-line distance. 10 registered projects within 2 km.
GOLDFIELDS
UNIVERSAL DEVELOPERS
Snehbhoomi
Pushkar Realty
HILL CREST PARK
LIMRA DEVELOPERS
Terra Nova
BHIMASHANKAR DEVELOPERS
Woodwinds Phase I
Alliance Vanashree Ventures
Vaarsahighland1
BHIMASHANKAR DEVELOPERS
See every Satara project, with the district possession charts
Builder: SAGAR MAHADEV JARAD
SAGAR MAHADEV JARAD has 2 registrations on MahaRERA, including Dattakrupa Apartment and Snehsagar Apartment. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.
Frequently asked questions
What are my rights if Dattakrupa Apartment is delayed beyond 30 Jun 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Dattakrupa Apartment?
The registered promoter entity is SAGAR MAHADEV JARAD, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Dattakrupa Apartment?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Dattakrupa Apartment?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Dattakrupa Apartment?
The professionals named in the filing: Architect: Rahul Hanuamant Bhokre; Engineer: MANGESH AVINASH LAWAND; Chartered Accountant: Kumudini Pravin Chavan; Chartered Accountant: GANESH KHATAVKAR AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Dattakrupa Apartment?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback