Home / Browse projects / Mumbai Suburban, Maharashtra / DATTA RAMANAND CHS LTD
DATTA RAMANAND CHS LTD
RG-MH-10807 · RERA P51800001236 · Last updated on MahaRERA portal: 9 Jan 2023
Source: official MahaRERA filing
Red flags
- Completion date moved by 24 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 4 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DATTA RAMANAND CHS LTD is a Residential / Group Housing project by DISHA CONSTRUCTION in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001236 on 27 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing.
At a glance
Project
- NameDATTA RAMANAND CHS LTD
- TypeResidential / Group Housing
- Location
- HANUMAN X ROAD NO.2
- VILE PARLE (E)
- Andheri
- Mumbai Suburban
- 400057
- Pincode400057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800001236
- ReraGenie IDRG-MH-10807
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on27 Jul 2017
- Promised completion30 Dec 2021
- Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
- Buildings9 building records
- Documents filed90 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| B WING PHASE 1 | NA | 7 | 0 | 0 | 0 | 0 |
| C WING PHASE 1 | NA | 7 | 0 | 0 | 0 | 0 |
| D WING PHASE 1 | NA | 7 | 0 | 0 | 0 | 0 |
| E WING PHASE 1 | NA | 7 | 0 | 0 | 0 | 0 |
| F WING PHASE 1 | NA | 7 | 0 | 0 | 0 | 0 |
| G WING PHASE 1 | NA | 7 | 0 | 0 | 0 | 0 |
| H WING PHASE 1 | NA | 7 | 0 | 0 | 0 | 0 |
| I WING PHASE 1 | NA | 7 | 0 | 0 | 0 | 0 |
| A WING PHASE 1 | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building9
As on 9 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
90 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Podiums (if any), at 0%.
B WING PHASE 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
C WING PHASE 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
D WING PHASE 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
E WING PHASE 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
F WING PHASE 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
G WING PHASE 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
H WING PHASE 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
I WING PHASE 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
A WING PHASE 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 9 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | No | Not applicable |
Parking filed205
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| B WING PHASE 1 | 26 | 26 |
| C WING PHASE 1 | 24 | 24 |
| D WING PHASE 1 | 25 | 25 |
| E WING PHASE 1 | 19 | 19 |
| F WING PHASE 1 | 19 | 19 |
| G WING PHASE 1 | 19 | 19 |
| H WING PHASE 1 | 25 | 25 |
| I WING PHASE 1 | 23 | 23 |
| A WING PHASE 1 | 25 | 25 |
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| DATTA RAMANAND CHS LTD | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | PREMAL GOGRI |
| Engineer | SUNIL SHAH |
| Partner | Role in project |
|---|---|
| DISHA CONSTRUCTION | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWE HAVE ALREADY OBTAINED PART OC FOR 1 TO 5TH FLOOR AND HANDOVER POSSESSION TO ALL SOCIETY MEMBERS ONLY GROUND FLOOR FLATS TO CONSTRUCT AND DATE EXTENSION REQUIRED DUE TO CHANGE OF DCR TO NEW DCPR, TRANSITION POLICY DATE OF APPLICABILITY OF NEW DCPR, APPROVAL OF NEW DCPR
Litigation declared3
| Case | Court | Status |
|---|---|---|
| 397 /2013 | HIGH COURT | ON GOING |
| CC/IV193/2013 | CO OPERATIVE COURT | ON GOING |
| CC/IV/134/2016 | CO OPERATIVE COURT | ON GOING |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 14 Aug 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Aug 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 14 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 16 Dec 2021
Documents filed90
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FROM 5- DATTA 21-22.pdf | 9 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5 DATTARAMANAND 20-21.pdf | 2 Mar 2022 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FULL OC 2298196_OC_signed.pdf | 16 Dec 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_A_WING_16-12-2021.pdf | 16 Dec 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_B_WING_16-12-2021.pdf | 16 Dec 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_C_WING__16-12-2021.pdf | 16 Dec 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_D_WING__16-12-2021.pdf | 16 Dec 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_E_WING_-_16-12-2021.pdf | 16 Dec 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_G_WING_16-12-2021.pdf | 16 Dec 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_H_WING_16-12-2021.pdf | 16 Dec 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_I_WING_16-12-2021.pdf | 16 Dec 2021 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_F_WING.pdf | 16 Dec 2021 |
| OtherFile: FULL OC 2298196_OC_signed.pdf | 16 Dec 2021 |
| Certificates of CA (Form 3)File: FORM - 3 CA CERTI DATTA_compressed-1-5.pdf | 20 Oct 2021 |
| Declaration about Commencement CertificateFile: Declaration of CC DATTA.pdf | 19 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 ENGINEER CERTI DATTA_compressed.pdf | 14 Oct 2021 |
| PAN CardFile: DC.pdf | 12 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 ARCHITECT CERTI Datta.pdf | 12 Oct 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM - 2A DATTA_merged.pdf | 12 Oct 2021 |
| Building plan approvalFile: IOD GR FULL.pdf | 14 Aug 2021 |
| Layout approvalFile: GROUND FLOOR DRAWING.pdf | 14 Aug 2021 |
| Details of encumbrancesFile: ENCUMBRANCE ABFL.pdf | 14 Aug 2021 |
| Details of encumbrancesFile: ENCUMB LET TATA.pdf | 14 Aug 2021 |
| Copy of Layout Approval (in case of layout)File: GROUND FLOOR DRAWING.pdf | 14 Aug 2021 |
| Building Plan Approval (IOD)File: IOD GR FULL.pdf | 14 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC FULL GR.pdf | 14 Aug 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 ARCHITECT Datta_.pdf | 14 Aug 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINNER CERT FORM 2A 19-20_compressed.pdf | 14 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: form - 29 inventory list (3)_compressed.pdf | 14 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: form - 29 inventory list (2)_compressed.pdf | 14 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: form - 29 inventory list (1)_compressed.pdf | 14 Aug 2021 |
| Disclosure of sold/ booked inventoryFile: FORM 29 A.pdf | 14 Aug 2021 |
| Certificates of CA (Form 3)File: FORM - 3 CA CERTI DATTA_compressed.pdf | 14 Aug 2021 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: soc letter datta.pdf | 14 Aug 2021 |
| Status of ConveyanceFile: soc letter datta.pdf | 14 Aug 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5 2019 DATTA.pdf | 14 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5 2020 DATTA.pdf | 14 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER CERTI FORM 2A_compressed.pdf | 13 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: INVENTORY DISCLOSER_compressed.pdf | 13 Jul 2021 |
| Building plan approvalFile: GROUND FLOOR PLAN.pdf | 7 Sep 2020 |
| Building Plan Approval (IOD)File: GROUND FLOOR PLAN.pdf | 7 Sep 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: CC GROUND FLOOR.pdf | 7 Sep 2020 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTI.pdf | 7 Sep 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTI_compressed.pdf | 7 Sep 2020 |
| OtherFile: AGREEMENT FOR SALE abfl.pdf | 11 Mar 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 A WING.pdf | 9 Jan 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 B WING.pdf | 9 Jan 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 C WING.pdf | 9 Jan 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 D WING.pdf | 9 Jan 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 E WING.pdf | 9 Jan 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 F WING.pdf | 9 Jan 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 G WING.pdf | 9 Jan 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 H WING.pdf | 9 Jan 2020 |
| Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 I WING.pdf | 9 Jan 2020 |
| Details of encumbrancesFile: ENCUMBRANCE LET SBI.pdf | 12 Sep 2019 |
| Details of encumbrancesFile: no dues certificate sbi.pdf | 12 Sep 2019 |
| Details of encumbrancesFile: ENCUMBRANCE LET ABFL.pdf | 12 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certi Datta_compressed.pdf | 21 Jun 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTI DATTA_compressed.pdf | 21 Jun 2019 |
| Certificates of CA (Form 3)File: CA CERTIFICATRE DATTA.pdf | 21 Jun 2019 |
| Certificates of CA (Form 5)File: FORM 5 DATTA.pdf | 12 Feb 2019 |
| OtherFile: O C CERTIFICATE.pdf | 22 Oct 2018 |
| Certificates of CA (Form 3)File: CA CERTI DATTA.pdf | 14 May 2018 |
| Layout approvalFile: ground flr Drawing-1-1.pdf | 12 May 2018 |
| Copy of Layout Approval (in case of layout)File: ground flr Drawing-1-1.pdf | 12 May 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 12 May 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf | 12 May 2018 |
| Certificates of CA (Form 3)File: CA CERTI DATTA.pdf | 12 May 2018 |
| Building plan approvalFile: IOD 2.pdf | 25 Jul 2017 |
| Building plan approvalFile: IOD 3.pdf | 25 Jul 2017 |
| Building plan approvalFile: IOD 4.pdf | 25 Jul 2017 |
| Building plan approvalFile: IOD 1.pdf | 25 Jul 2017 |
| Copy of the legal title reportFile: TITLE CERTIFICATE DATTA.pdf | 25 Jul 2017 |
| Building Plan Approval (IOD)File: IOD 1.pdf | 25 Jul 2017 |
| Building Plan Approval (IOD)File: IOD 2.pdf | 25 Jul 2017 |
| Building Plan Approval (IOD)File: IOD 3.pdf | 25 Jul 2017 |
| Building Plan Approval (IOD)File: IOD 4.pdf | 25 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTI 1.pdf | 25 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTI 2.pdf | 25 Jul 2017 |
| Layout approvalFile: 01.pdf | 20 Jul 2017 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| D SQUARE | VILE PARLE | 60 | Completed | May 2014 | May 2014 |
| MALA PALACE CHS | VILE PARLE | 26 | Completed | Mar 2014 | Mar 2014 |
| E SQUARE | VILE PARLE | 100 | Completed | Jun 2013 | Jun 2013 |
| IRIS | VILE PARLE | 17 | Completed | Dec 2012 | Dec 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 90 filed documents as one ZIP, foldered, with a manifest
Keep DATTA RAMANAND CHS LTD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near VILE PARLE (E)6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 343 registered projects within 2 km.
Vijayraj Residency
Vijayraj Realtors
ZEE HAPPY VEENA
ZEE LIFESPACES
Romell Espalier
ROMELL REAL ESTATE PRIVATE LIMITED
ZEE SHAAN
TRISUL DEVELOPERS
SALE BUILDING 1 - CHAMUNDA CROWN AND SALE BUIL
Chamunda Builders & Developers
ARKADE PEARL 1
ARKADE DEVELOPERS LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: DISHA CONSTRUCTION
DISHA CONSTRUCTION has 5 registrations on MahaRERA, including DATTA RAMANAND CHS LTD and SAT ANUPA CHS PHASE 1. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if DATTA RAMANAND CHS LTD is delayed beyond 30 Dec 2021?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DATTA RAMANAND CHS LTD?
The registered promoter entity is DISHA CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DATTA RAMANAND CHS LTD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DATTA RAMANAND CHS LTD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DATTA RAMANAND CHS LTD?
The professionals named in the filing: Architect: PREMAL GOGRI; Engineer: SUNIL SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DATTA RAMANAND CHS LTD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback