Red flags

  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 4 earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2021Possession promisedregistration recorded completed
90 of 99Construction stages doneacross 9 buildings; furthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 90 documents Report an error

DATTA RAMANAND CHS LTD is a Residential / Group Housing project by DISHA CONSTRUCTION in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800001236 on 27 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2021. The completion date has moved by 24 months from the original filing.

At a glance

Project

  • NameDATTA RAMANAND CHS LTD
  • TypeResidential / Group Housing
  • Location
    • HANUMAN X ROAD NO.2
    • VILE PARLE (E)
    • Andheri
    • Mumbai Suburban
    • 400057
  • Pincode400057
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800001236
  • ReraGenie IDRG-MH-10807

Builder

  • NameDISHA CONSTRUCTION
  • Entity typePartnership
  • PartnersMAHENDRA JAGMOHANDAS SHAH, DISHALANDDEVELOPERPVT LAND DEVELOPER
  • Other registrations4 more →
  • Completed4 of 5
  • Declared earlier projects4 →

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toDec 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jul 2017
  • Promised completion30 Dec 2021
  • Revised completionRevised to 30 Dec 2021 (originally 31 Dec 2019)
  • Buildings9 building records
  • Documents filed90 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B WING PHASE 1NA70000
C WING PHASE 1NA70000
D WING PHASE 1NA70000
E WING PHASE 1NA70000
F WING PHASE 1NA70000
G WING PHASE 1NA70000
H WING PHASE 1NA70000
I WING PHASE 1NA70000
A WING PHASE 1NA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building9

As on 9 Jan 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

90 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Podiums (if any), at 0%.

B WING PHASE 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C WING PHASE 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
D WING PHASE 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E WING PHASE 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
F WING PHASE 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
G WING PHASE 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
H WING PHASE 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
I WING PHASE 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
A WING PHASE 191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 9 Jan 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed205

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots205
Closed/Covered205
BuildingClosed/CoveredTotal
B WING PHASE 12626
C WING PHASE 12424
D WING PHASE 12525
E WING PHASE 11919
F WING PHASE 11919
G WING PHASE 11919
H WING PHASE 12525
I WING PHASE 12323
A WING PHASE 12525

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,474 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
DATTA RAMANAND CHS LTDAndheriMumbai Suburban

Approvals and building plan

Permissible FSI11173.23
Proposed, not sanctioned10,332 sq m
Buildings approved9
Buildings sanctioned9

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMULUND

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPREMAL GOGRI
EngineerSUNIL SHAH
PartnerRole in project
DISHA CONSTRUCTION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005357Dec 2019 → Dec 2020

Reason as filed by the promoterWE HAVE ALREADY OBTAINED PART OC FOR 1 TO 5TH FLOOR AND HANDOVER POSSESSION TO ALL SOCIETY MEMBERS ONLY GROUND FLOOR FLATS TO CONSTRUCT AND DATE EXTENSION REQUIRED DUE TO CHANGE OF DCR TO NEW DCPR, TRANSITION POLICY DATE OF APPLICABILITY OF NEW DCPR, APPROVAL OF NEW DCPR

Litigation declared3

CaseCourtStatus
397 /2013HIGH COURTON GOING
CC/IV193/2013CO OPERATIVE COURTON GOING
CC/IV/134/2016CO OPERATIVE COURTON GOING

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Aug 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Aug 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Aug 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 16 Dec 2021

Documents filed90

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 90 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FROM 5- DATTA 21-22.pdf9 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM-5 DATTARAMANAND 20-21.pdf2 Mar 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: FULL OC 2298196_OC_signed.pdf16 Dec 2021
Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_A_WING_16-12-2021.pdf16 Dec 2021
Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_B_WING_16-12-2021.pdf16 Dec 2021
Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_C_WING__16-12-2021.pdf16 Dec 2021
Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_D_WING__16-12-2021.pdf16 Dec 2021
Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_E_WING_-_16-12-2021.pdf16 Dec 2021
Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_G_WING_16-12-2021.pdf16 Dec 2021
Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_H_WING_16-12-2021.pdf16 Dec 2021
Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_I_WING_16-12-2021.pdf16 Dec 2021
Architect’s Certificate on Completion of Project (Form 4)File: FORM_4_F_WING.pdf16 Dec 2021
OtherFile: FULL OC 2298196_OC_signed.pdf16 Dec 2021
Certificates of CA (Form 3)File: FORM - 3 CA CERTI DATTA_compressed-1-5.pdf20 Oct 2021
Declaration about Commencement CertificateFile: Declaration of CC DATTA.pdf19 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM - 2 ENGINEER CERTI DATTA_compressed.pdf14 Oct 2021
PAN CardFile: DC.pdf12 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 ARCHITECT CERTI Datta.pdf12 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM - 2A DATTA_merged.pdf12 Oct 2021
Building plan approvalFile: IOD GR FULL.pdf14 Aug 2021
Layout approvalFile: GROUND FLOOR DRAWING.pdf14 Aug 2021
Details of encumbrancesFile: ENCUMBRANCE ABFL.pdf14 Aug 2021
Details of encumbrancesFile: ENCUMB LET TATA.pdf14 Aug 2021
Copy of Layout Approval (in case of layout)File: GROUND FLOOR DRAWING.pdf14 Aug 2021
Building Plan Approval (IOD)File: IOD GR FULL.pdf14 Aug 2021
Commencement Certificates / NA Order for plotted developmentFile: CC FULL GR.pdf14 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM - 1 ARCHITECT Datta_.pdf14 Aug 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: ENGINNER CERT FORM 2A 19-20_compressed.pdf14 Aug 2021
Disclosure of sold/ booked inventoryFile: form - 29 inventory list (3)_compressed.pdf14 Aug 2021
Disclosure of sold/ booked inventoryFile: form - 29 inventory list (2)_compressed.pdf14 Aug 2021
Disclosure of sold/ booked inventoryFile: form - 29 inventory list (1)_compressed.pdf14 Aug 2021
Disclosure of sold/ booked inventoryFile: FORM 29 A.pdf14 Aug 2021
Certificates of CA (Form 3)File: FORM - 3 CA CERTI DATTA_compressed.pdf14 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: soc letter datta.pdf14 Aug 2021
Status of ConveyanceFile: soc letter datta.pdf14 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5 2019 DATTA.pdf14 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5 2020 DATTA.pdf14 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: ENGINEER CERTI FORM 2A_compressed.pdf13 Jul 2021
Disclosure of sold/ booked inventoryFile: INVENTORY DISCLOSER_compressed.pdf13 Jul 2021
Building plan approvalFile: GROUND FLOOR PLAN.pdf7 Sep 2020
Building Plan Approval (IOD)File: GROUND FLOOR PLAN.pdf7 Sep 2020
Commencement Certificates / NA Order for plotted developmentFile: CC GROUND FLOOR.pdf7 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTI.pdf7 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTI_compressed.pdf7 Sep 2020
OtherFile: AGREEMENT FOR SALE abfl.pdf11 Mar 2020
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 A WING.pdf9 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 B WING.pdf9 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 C WING.pdf9 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 D WING.pdf9 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 E WING.pdf9 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 F WING.pdf9 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 G WING.pdf9 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 H WING.pdf9 Jan 2020
Architect’s Certificate on Completion of Project (Form 4)File: FORM 4 I WING.pdf9 Jan 2020
Details of encumbrancesFile: ENCUMBRANCE LET SBI.pdf12 Sep 2019
Details of encumbrancesFile: no dues certificate sbi.pdf12 Sep 2019
Details of encumbrancesFile: ENCUMBRANCE LET ABFL.pdf12 Sep 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certi Datta_compressed.pdf21 Jun 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTI DATTA_compressed.pdf21 Jun 2019
Certificates of CA (Form 3)File: CA CERTIFICATRE DATTA.pdf21 Jun 2019
Certificates of CA (Form 5)File: FORM 5 DATTA.pdf12 Feb 2019
OtherFile: O C CERTIFICATE.pdf22 Oct 2018
Certificates of CA (Form 3)File: CA CERTI DATTA.pdf14 May 2018
Layout approvalFile: ground flr Drawing-1-1.pdf12 May 2018
Copy of Layout Approval (in case of layout)File: ground flr Drawing-1-1.pdf12 May 2018
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf12 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER CERTIFICATE.pdf12 May 2018
Certificates of CA (Form 3)File: CA CERTI DATTA.pdf12 May 2018
Building plan approvalFile: IOD 2.pdf25 Jul 2017
Building plan approvalFile: IOD 3.pdf25 Jul 2017
Building plan approvalFile: IOD 4.pdf25 Jul 2017
Building plan approvalFile: IOD 1.pdf25 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE DATTA.pdf25 Jul 2017
Building Plan Approval (IOD)File: IOD 1.pdf25 Jul 2017
Building Plan Approval (IOD)File: IOD 2.pdf25 Jul 2017
Building Plan Approval (IOD)File: IOD 3.pdf25 Jul 2017
Building Plan Approval (IOD)File: IOD 4.pdf25 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTI 1.pdf25 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTI 2.pdf25 Jul 2017
Layout approvalFile: 01.pdf20 Jul 2017

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
D SQUAREVILE PARLE60CompletedMay 2014May 2014
MALA PALACE CHSVILE PARLE26CompletedMar 2014Mar 2014
E SQUAREVILE PARLE100CompletedJun 2013Jun 2013
IRISVILE PARLE17CompletedDec 2012Dec 2012

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep DATTA RAMANAND CHS LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VILE PARLE (E)6,700+ in Mumbai Suburban

2 kmDATTA RAMANAND CHS LTDCompleted 138Lapsed / revoked 69Other 136Dot size: filed unitsN

Filed coordinates, straight-line distance. 343 registered projects within 2 km.

Builder: DISHA CONSTRUCTION

DISHA CONSTRUCTION has 5 registrations on MahaRERA, including DATTA RAMANAND CHS LTD and SAT ANUPA CHS PHASE 1. Its filings disclose 4 earlier MahaRERA projects: declares 4 of 4 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if DATTA RAMANAND CHS LTD is delayed beyond 30 Dec 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of DATTA RAMANAND CHS LTD?

The registered promoter entity is DISHA CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in DATTA RAMANAND CHS LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for DATTA RAMANAND CHS LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at DATTA RAMANAND CHS LTD?

The professionals named in the filing: Architect: PREMAL GOGRI; Engineer: SUNIL SHAH. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in DATTA RAMANAND CHS LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About DATTA RAMANAND CHS LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save DATTA RAMANAND CHS LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.