Home / Browse projects / Solapur, Maharashtra / DAKSH RESIDENCY
DAKSH RESIDENCY
RG-MH-19336 · RERA P52600078465 · Last updated on MahaRERA portal: 6 May 2026
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.
See what the report covers Free either way: or have every new Solapur registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
DAKSH RESIDENCY is a Residential / Group Housing project by BHAGYODAY BUILDERS in Solapur, Maharashtra, registered with MahaRERA as P52600078465 on 12 Dec 2024. The registration is recorded completed; possession was promised by 31 Dec 2027.
At a glance
Project
- NameDAKSH RESIDENCY
- TypeResidential / Group Housing
- Location
- PRABHAT NAGAR
- KASBE SOLAPUR
- Solapur (M Corp.)
- Solapur North
- Solapur
- 413001
- Pincode413001
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52600078465
- ReraGenie IDRG-MH-19336
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on12 Dec 2024
- Promised completion31 Dec 2027
- Revised completionNone
- Buildings1 building record
- Documents filed51 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| DAKSH RESIDENCY | NA | 7 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
1 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 80%.
DAKSH RESIDENCY: 18% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 20% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed62
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VIRAL UDESHI |
| Engineer | JITENDRA PATEL |
| Chartered Accountant | DARESH PATIL |
| Partner | Role in project |
|---|---|
| BHAGYODAY BUILDERS | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Oct 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 Oct 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 8 Oct 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 9 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed51
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Architect Certificate.pdf | 6 May 2026 |
| Form 2File: Engineer Certificate.pdf | 6 May 2026 |
| Form 3File: CA Certificate_compressed.pdf | 6 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosere of Sold new.pdf | 6 May 2026 |
| Occupational CertificateFile: occupation certificate.pdf | 6 May 2026 |
| Form 1File: ARCHITECT CERTIFICATE FORM 1.pdf | 2 Feb 2026 |
| Form 2File: ENGINEER CERTIFICATE FORM 2.pdf | 2 Feb 2026 |
| Form 3File: CA Certificate FORM 3.pdf | 2 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY.pdf | 2 Feb 2026 |
| Form 1File: ARCHITECT CERTIFICATE FORM 1.pdf | 2 Feb 2026 |
| Form 2File: ENGINEER CERTIFICATE FORM 2.pdf | 2 Feb 2026 |
| Form 3File: CA CERTIFICATE FORM 3.pdf | 2 Feb 2026 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY 26.pdf | 2 Feb 2026 |
| Form 1File: arch.pdf | 5 Aug 2025 |
| Form 2File: eng cert.pdf | 5 Aug 2025 |
| Form 3File: ca.pdf | 5 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: inventry.pdf | 5 Aug 2025 |
| Form 1File: form1 arch certificate 24-5-25.pdf | 27 May 2025 |
| Form 3File: 15-5-25 CA CERTIFICATE DAKSH.pdf | 27 May 2025 |
| Form 2File: engineer certificate 14_5.pdf | 27 May 2025 |
| Other - FinanceFile: FORMAT A 2 12 2024.pdf | 2 Dec 2024 |
| Other - TechnicalFile: Annexure ‘A’ Declaration-Cum-undertaking.pdf | 29 Nov 2024 |
| Proforma of Allotment letterFile: allotment letter 22_compressed.pdf | 22 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca 02 12_compressed.pdf | 22 Nov 2024 |
| CERSAI detailsFile: cersaii.pdf | 22 Nov 2024 |
| Deviation Report with respect to Allotment letterFile: no deviation allotment.pdf | 22 Nov 2024 |
| Deviation Report with respect to model copy of AgreementFile: no deviation sale agrement.pdf | 22 Nov 2024 |
| Proforma of Agreement for saleFile: SALE DEED 2-12-24.pdf | 22 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: GIRISH UDESHI - Disclosure of Interest in Other Real Estate Organisations.pdf | 22 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: JAYESH UDESHI - Disclosure of Interest in Other Real Estate Organisations.pdf | 22 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DAKSHA UDESHI - Disclosure of Interest in Other Real Estate Organisations.pdf | 22 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: PURVITA UDESHI - Disclosure of Interest in Other Real Estate Organisations.pdf | 22 Nov 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: KHUSHBOO UDESHI - Disclosure of Interest in Other Real Estate Organisations.pdf | 22 Nov 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format-B.pdf | 22 Nov 2024 |
| Copy of the legal title reportFile: NEW SEARCH_compressed.pdf | 17 Oct 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: DISCLOSURE FIN.pdf | 17 Oct 2024 |
| Declaration in FORM BFile: FOR B AFF_compressed.pdf | 16 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: FINANCE ENCUB .pdf | 11 Oct 2024 |
| Details of encumbrances concerned to LegalFile: FINANCE ENCUB .pdf | 11 Oct 2024 |
| Building plan approvalFile: DAKSH PERM.pdf | 8 Oct 2024 |
| Layout approvalFile: AMALGATION DAKSH.pdf | 8 Oct 2024 |
| Copy of Layout Approval (in case of layout)File: AMALGATION DAKSH.pdf | 8 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: DAKSH PERM.pdf | 8 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE 1609.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENG CERTIFICATE 7102024.pdf | 7 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A NEW.pdf | 7 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: TO WHOM IT MAY CONCERN - 2.pdf | 9 Apr 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: SMC - BUILDING PERMISSION.pdf | 9 Apr 2024 |
| Declaration about Commencement CertificateFile: Declaration About Commencment Certificate - Format - D.pdf | 9 Apr 2024 |
| Details of encumbrances concerned to LegalFile: TO WHOM IT MAY CONCERN - 2.pdf | 9 Apr 2024 |
| PAN CardFile: PAN BHAGYODAY BUILDERS.pdf | 8 Apr 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| KUBER HEIGHTS | PLOT NO.5 KUBER HEIGHTS NEXT TO PADMINI NURSING HOME SOLAPUR | 18 | Completed | Jun 2025 | Apr 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Solapur
Computed across the 550+ Solapur projects on ReraGenie, from their own filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 51 filed documents as one ZIP, foldered, with a manifest
Keep DAKSH RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near KASBE SOLAPUR550+ in Solapur
Filed coordinates, straight-line distance. 44 registered projects within 2 km.
Vrundavan Park
Vrundavan Properties
Platinum Mall
M/S Ganesh Ramchandra Apte
INDRADHANU-Phase-IV
M/S Ganesh Ramchandra Apte
INDRADHANU-Phase-6
M/S Ganesh Ramchandra Apte
Jijau Residency
Rachana Developers
ROYAL SYNERGY
SHREE JAGDAMB DEVELOPERS
See every Solapur project, with the district possession charts
Builder: BHAGYODAY BUILDERS
BHAGYODAY BUILDERS has 2 registrations on MahaRERA, including DAKSH RESIDENCY and Venkatesh Haripriya. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Solapur district page.
Frequently asked questions
What are my rights if DAKSH RESIDENCY is delayed beyond 31 Dec 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of DAKSH RESIDENCY?
The registered promoter entity is BHAGYODAY BUILDERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in DAKSH RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for DAKSH RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at DAKSH RESIDENCY?
The professionals named in the filing: Architect: VIRAL UDESHI; Engineer: JITENDRA PATEL; Chartered Accountant: DARESH PATIL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in DAKSH RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback