Continuum
RG-MH-57050 · RERA P51800005235 · Last updated on MahaRERA portal: 16 Nov 2018
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 82 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Continuum is a Commercial project by Narang & Ruchi Developers in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800005235 on 11 Aug 2017. Possession was promised by 31 Dec 2019 and is now 82 months past that date. 15 of the 19 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.
At a glance
Project
- NameContinuum
- TypeCommercial
- Location
- cts no 1315
- Andheri
- Mumbai Suburban
- 400057
- Pincode400057
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800005235
- ReraGenie IDRG-MH-57050
Builder
- NameNarang & Ruchi Developers
- Entity typePartnership
- PartnersNarang Developers Private Limited through Amit Narang Private Limited, Ruchi Infrastructure Limited through Narendra Shah Limited
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on11 Aug 2017
- Promised completion31 Dec 2019
- Revised completionNone
- Buildings1 building record
- Documents filed44 files
Current status
Figures as on 16 Nov 2018, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Continuum | NA | 8 | 7 | 0 | 19 | 19 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 16 Nov 2018, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
7 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 91%.
Continuum: 80% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 91% |
| Sanitary Fittings within the flats / premises | 91% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 16 Nov 2018, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 50% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Santosh Acharya |
| Engineer | Pravin Gala Consultants Pvt Ltd |
| Chartered Accountant | ketan kataria & associates |
| Partner | Role in project |
|---|---|
| Narang & Ruchi Developers | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 30 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed44
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| OtherFile: Declaration for Continuum 5th Quarter Rera Updation.pdf | 16 Nov 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Continuum 5th Quarter.pdf | 13 Nov 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Continuum 5th Quarter RERA.pdf | 6 Nov 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Continuum 5th Quarter RERA.pdf | 6 Nov 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 27072018 Engineers Certificate Continuum.pdf | 5 Nov 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 29012018 (Engineers Certificate) Continuum.pdf | 29 Sep 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 06022018 (Architects Certificate) Continuum.pdf | 28 Sep 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Continuum 4th Quarter.pdf | 28 Sep 2018 |
| Certificates of CA (Form 5)File: FOrm 5 sign.pdf | 28 Sep 2018 |
| OtherFile: 29012018 (Declaration) Continuum.pdf | 28 Sep 2018 |
| OtherFile: 27072018 (Declaration) Continuum.pdf | 28 Sep 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Form 1 (2) 1.pdf | 1 Mar 2018 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate (Continuum).pdf | 1 Mar 2018 |
| OtherFile: Continuum (Declaration).pdf | 1 Mar 2018 |
| OtherFile: Continuum Declaration.pdf | 13 Dec 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Continuum Engineer's Certificate.pdf | 30 Nov 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Continum_Architect Certificate_Form-1.pdf | 8 Nov 2017 |
| Building plan approvalFile: 08082008 IODcontinuum.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: 08082008 IODcontinuum.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: rev cert.pdf | 31 Jul 2017 |
| Layout approvalFile: 25 03 2010 Amended Plan 1.pdf | 30 Jul 2017 |
| Layout approvalFile: 2503 2010 Amended Plan 2.pdf | 30 Jul 2017 |
| Layout approvalFile: 25 03 2010 Amended Plan 3.pdf | 30 Jul 2017 |
| Layout approvalFile: 25 03 2010 Amended Plan 4.pdf | 30 Jul 2017 |
| Layout approvalFile: 25 03 2010 Amended Plan 5.pdf | 30 Jul 2017 |
| Building plan approvalFile: 25032010continuum amended IOD.pdf | 30 Jul 2017 |
| PAN CardFile: Pan Card.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: 07072010 title certificate-Continuum.pdf | 30 Jul 2017 |
| Copy of the legal title reportFile: Index 02.pdf | 30 Jul 2017 |
| Details of encumbrancesFile: Encumbrance Certificate.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 25 03 2010 Amended Plan 1.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 2503 2010 Amended Plan 2.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 25 03 2010 Amended Plan 3.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 25 03 2010 Amended Plan 4.pdf | 30 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: 25 03 2010 Amended Plan 5.pdf | 30 Jul 2017 |
| Building Plan Approval (IOD)File: 25032010continuum amended IOD.pdf | 30 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: CC till 5th Floor-Continuum.pdf | 30 Jul 2017 |
| Declaration in FORM BFile: Form B.pdf | 30 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf | 30 Jul 2017 |
| Certificates of CA (Form 3)File: CA Certificate Final.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Pages from Draft Ag for Sale (Continuum) 0109.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Pages from Draft Ag for Sale (Continuum) 1020.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Pages from Draft Ag for Sale (Continuum) 011-032.pdf | 30 Jul 2017 |
| Proforma of Allotment letterFile: Draft Allotment Letter Continuum.pdf | 30 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 44 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Continuum on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Andheri6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 343 registered projects within 2 km.
Vijayraj Residency
Vijayraj Realtors
ZEE HAPPY VEENA
ZEE LIFESPACES
Romell Espalier
ROMELL REAL ESTATE PRIVATE LIMITED
ZEE SHAAN
TRISUL DEVELOPERS
SALE BUILDING 1 - CHAMUNDA CROWN AND SALE BUIL
Chamunda Builders & Developers
ARKADE PEARL 1
ARKADE DEVELOPERS LIMITED
See every Mumbai Suburban project, with the district possession charts
Builder: Narang & Ruchi Developers
Narang & Ruchi Developers has 1 registration on MahaRERA, including Continuum. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that Continuum shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Continuum is delayed beyond 31 Dec 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Continuum?
The registered promoter entity is Narang & Ruchi Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Continuum?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Continuum?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Continuum?
The professionals named in the filing: Architect: Santosh Acharya; Engineer: Pravin Gala Consultants Pvt Ltd; Chartered Accountant: ketan kataria & associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Continuum?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.