Home / Browse projects / Kolhapur, Maharashtra / Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist Kolhapur

Registered No litigation declared Residential / Group Housing project

Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist Kolhapur

By Pune Housing and Area Development Board Pune

RG-MH-15288 · RERA P53000028659 · Last updated on MahaRERA portal: 30 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 21 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Kolhapur registration emailed to you, free during the pilot beta.
Jun 2029Possession promisedno revision filed
0 of 99Construction stages doneacross 9 buildings; furthest along: Excavation, 50%
0Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist Kolhapur is a Residential / Group Housing project by Pune Housing and Area Development Board Pune in Kolhapur, Maharashtra, registered with MahaRERA as P53000028659 on 25 Mar 2021. Possession is promised by 30 Jun 2029.

At a glance

Project

  • NameConstruction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist Kolhapur
  • TypeResidential / Group Housing
  • Location
    • Kagal Sangaon Road
    • Behind Y D Mane polytecnic
    • Kagal (M Cl)
    • Kagal
    • Kolhapur
    • 416216
  • Pincode416216
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P53000028659
  • ReraGenie IDRG-MH-15288

Builder

  • NamePune Housing and Area Development Board Pune
  • Entity typePublic Authority
  • GSTIN27AAAJM0344H5ZA
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • Executive Engineer II PHADBManisha Ananda More
  • Chief Account OfficerLalit Pomeshwar Khapre
  • Other registrations21 more →
  • Completed9 of 22
  • No longer live7 lapsed, de-registered or revoked
  • Declared earlier projects4 →

Key dates

this monthRegisteredMar 2021PromisedJun 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Mar 2021
  • Promised completion30 Jun 2029
  • Revised completionNone
  • Buildings9 building records
  • Documents filed56 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
EWS-1NA44000
EWS-2NA40000
EWS-3NA40000
EWS-4NA40000
EWS-5NA40000
EWS-6NA40000
LIG-1NA90000
LIG-2NA80000
LIG-3NA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building9

As on 30 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Excavation, at 50%.

EWS-10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
EWS-20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
EWS-30%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
EWS-40%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
EWS-55%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
EWS-65%
ActivityProgress
Excavation50%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
LIG-10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
LIG-20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
LIG-30%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed2

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2
Closed/Covered2
BuildingClosed/CoveredTotal
LIG-111
LIG-311

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,000 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authoritykagal municpal corporation,kagal
Permissible FSI8138.38
Proposed, not sanctioned8,138 sq m
Buildings approved9
Buildings sanctioned9

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSachapir street Camp Pune

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPriya Nagesh Deshpande
EngineerA D Patil
EngineerExecutive Engineer II
Chartered AccountantSwati Parab
Chartered AccountantPune Housing and Area Development Board (MHADA Unit)
Chartered AccountantChief Accounts Officer NAIK
PartnerRole in project
Pune Housing and Area Development Board Pune-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Nov 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Nov 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Nov 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Nov 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2029

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM1ARCHTCERT1200.pdf30 Jun 2026
Form 3File: form3P659 OF1200compressed.pdf30 Jun 2026
Form 2File: FORM2ENGINECERT1200compressed.pdf30 Jun 2026
Disclosure of Sold and Booked InventoryFile: SOLD1200P.pdf30 Jun 2026
Form 5 (FY 2024-2025)File: 59.pdf5 Mar 2026
Form 1File: 1archct.pdf4 Mar 2026
Form 2File: 2enggcrt.pdf4 Mar 2026
Form 3File: 3cacert.pdf4 Mar 2026
Disclosure of Sold and Booked InventoryFile: unsold invetory.pdf4 Mar 2026
Form 1File: 1archct.pdf4 Mar 2026
Form 2File: 2enggcrt.pdf4 Mar 2026
Form 3File: 3cacert.pdf4 Mar 2026
Disclosure of Sold and Booked InventoryFile: unsold invetory.pdf4 Mar 2026
Form 1File: 1archct.pdf4 Mar 2026
Form 2File: 2enggcrt.pdf4 Mar 2026
Form 3File: 3cacert.pdf4 Mar 2026
Disclosure of Sold and Booked InventoryFile: unsold invetory.pdf4 Mar 2026
Form 1File: form1.pdf2 Mar 2026
Form 2File: form2.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: form3.pdf2 Mar 2026
Form 3File: form3.pdf2 Mar 2026
Form 1File: form1.pdf2 Mar 2026
Form 2File: form2.pdf2 Mar 2026
Form 3File: form3.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: form3.pdf2 Mar 2026
Form 1File: form1.pdf2 Mar 2026
Form 2File: form2.pdf2 Mar 2026
Form 3File: form3.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: form3.pdf2 Mar 2026
Form 1File: form1.pdf2 Mar 2026
Form 2File: form2.pdf2 Mar 2026
Form 3File: form3.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: form3.pdf2 Mar 2026
Form 1File: form1.pdf2 Mar 2026
Form 2File: form2.pdf2 Mar 2026
Form 3File: form3.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: form3.pdf2 Mar 2026
Form 1File: form1.pdf2 Mar 2026
Form 2File: form2.pdf2 Mar 2026
Form 3File: form3.pdf2 Mar 2026
Disclosure of Sold and Booked InventoryFile: form3.pdf2 Mar 2026
Layout approvalFile: lay out.pdf30 Nov 2019
Building plan approvalFile: EWS municipal drawing.pdf30 Nov 2019
Building plan approvalFile: LIG municipal drawing.pdf30 Nov 2019
PAN CardFile: pan card.pdf30 Nov 2019
Copy of the legal title reportFile: Land title certificate.pdf30 Nov 2019
Details of encumbrancesFile: Non encumbarance certificate.pdf30 Nov 2019
Copy of Layout Approval (in case of layout)File: lay out.pdf30 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: EWS municipal drawing.pdf30 Nov 2019
Building Plan Approval / NA Order for plotted developmentFile: LIG municipal drawing.pdf30 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: commancement certificate.pdf30 Nov 2019
Declaration in FORM BFile: Form B kagal ee Affidavit.pdf30 Nov 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf30 Nov 2019
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers certificate.pdf30 Nov 2019
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf30 Nov 2019
Proforma of Allotment letterFile: allotment letter.pdf30 Nov 2019

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise2 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Construction of 16 LIG tenements, 16 MIG tenements and 13 Shops at S No 252/1, SangliP53100024685Abhaynagar, Sangli45Feb 2020CompletedMar 2026Jun 2023
Composite Housing Scheme on Plot E2 at Sant Tukaram Nagar Pimpri PuneP52100049355Opposite Sant Tukaram Nagar Police Chowki, Pune64Feb 2023OngoingDec 2025Registered original: Dec 2024Not delivered
Composite Housing Scheme on Plot D1 at Sant Tukaram Nagar Pimpri PuneP52100049490Opposite Sant Tuakaram Nagar Police Chowki, Pune-Feb 2023OngoingDec 2024Not delivered
Const 72 MIG TenamentsAmboli Road Near Maruti Showroom Saswad72-CompletedMar 2017Mar 2017

How this compares with Kolhapur

17%of Kolhapur projects moved their completion datethis one has not
25%of Kolhapur registrations have lapsed or been cancelledthis one is on the register

Computed across the 880+ Kolhapur projects on ReraGenie, from their own filings.

Keep Construction of 96 EWS and 84 LIG T/s at Gat on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Behind Y D Mane polytecnic880+ in Kolhapur

2 kmConstruction of 96 EWS aCompleted 4Lapsed / revoked 4Other 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 13 registered projects within 2 km.

Builder: Pune Housing and Area Development Board Pune

Pune Housing and Area Development Board Pune has 22 registrations on MahaRERA, including Constructing 54 Tenements LIG and 36 Tenements MIG at Gat No 1712 part Dive Taluka Purander Dist Pun and Const.378 LIG,331MIG,154HIG T.. Its filings disclose 4 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Kolhapur district page.

Frequently asked questions

What are my rights if Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist Kolhapur is delayed beyond 30 Jun 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist Kolhapur?

The registered promoter entity is Pune Housing and Area Development Board Pune, a public authority as per the filing. Its GSTIN 27AAAJM0344H5ZA can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist Kolhapur?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist Kolhapur?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist Kolhapur?

The professionals named in the filing: Architect: Priya Nagesh Deshpande; Engineer: A D Patil; Engineer: Executive Engineer II; Chartered Accountant: Swati Parab; Chartered Accountant: Pune Housing and Area Development Board (MHADA Unit); Chartered Accountant: Chief Accounts Officer NAIK. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist Kolhapur?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Construction of 96 EWS and 84 LIG T/s at Gat no 425/2 part area 1.2 ha Kagal Dist Kolhapur. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Construction of 96 EWS and 84 LIG T/s at Gat to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.