Clover Windermere Phase -II
RG-MH-09422 · RERA P52700001156 · Last updated on MahaRERA portal: 24 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Satara registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Clover Windermere Phase -II is a Plotted project by Amalfi Enterprise in Satara, Maharashtra, registered with MahaRERA as P52700001156 on 26 Jul 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. 4 of the 20 units on this registration are recorded sold or booked.
At a glance
Project
- NameClover Windermere Phase -II
- TypePlotted
- Location
- Clover Windermere phase 2 street
- Clover Windereme
- Kavathe
- Khandala
- Satara
- 412801
- Pincode412801
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52700001156
- ReraGenie IDRG-MH-09422
Builder
- NameAmalfi Enterprise
- Entity typePartnership
- PartnersJaved Faizullah Tapia, Zahid Azim Tapia
- Other registrations1 more →
- Completed1 of 2
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on26 Jul 2017
- Promised completion31 Dec 2025
- Revised completionNone
- BuildingsNot stated in filing
- Documents filed86 files
Current status
Figures as on 24 Apr 2025, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 24 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities18
As on 24 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
| Plot fencing and chain link fencing | Yes | 100% |
| Irrigation pipeline | Yes | 100% |
| Compound walls | Yes | 100% |
Land and ownership4
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| Nandkumar Bhalchandra Bhondve | Pimpari | Pune |
| Somnath Bhalchandra Bhondve | Pimpari | Pune |
| Prakash Dashrath Balwadkar | Pimpri Chinchawad (M Corp.) | Pune |
| Shila Prakash Balwadkar | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Supriya Yadav |
| Architect | Architheque |
| Engineer | Semac Consultants |
| Partner | Role in project |
|---|---|
| Amalfi Enterprise | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Feb 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 19 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Feb 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 24 Apr 2025
Documents filed86
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 86 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Mail.pdf | 24 Apr 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Final na layout approval.pdf | 27 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Clover Windermere Phase II 04 09 23.pdf | 11 Mar 2024 |
| Layout approvalFile: Final NA Approval windermere (1).pdf | 27 Feb 2024 |
| Copy of Layout Approval (in case of layout)File: Final NA Approval windermere (1).pdf | 27 Feb 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Final na layout approval 10-09-18.pdf | 27 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: cw ph 2 Form 1 31-3-22.pdf | 22 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: cw ph 2 Form 2 31-3-22.pdf | 22 Feb 2024 |
| Form 2AFile: form 2a ph 2 30-12-19.pdf | 22 Feb 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Inward Letter.pdf | 18 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CW ph2 form 1 30-12-23.pdf | 5 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CW ph2 form 2 30-12-23.pdf | 5 Jan 2024 |
| Certificates of CA (Form 3)File: AE - CW- Phase 2 - Form 3 - 31-12-2023.pdf | 5 Jan 2024 |
| Certificates of CA (Form 3)File: Form 3.pdf | 22 Nov 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CW ph2 form 2 30-9-23.pdf | 4 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CW ph2 form 1 30-9-23.pdf | 2 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: CW Phase 2 Form 5 -FY202223.pdf | 29 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Clover Windermere Phase II_Rera Updates_30-06-2023.pdf | 31 Aug 2023 |
| Certificates of CA (Form 3)File: AE - CW - Ph 2 - Form 3 - 30-06-2023.pdf | 22 Jul 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CW ph 2 form 1 june 2023.pdf | 19 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CW ph 2 form 2 june 2023.pdf | 19 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: CW Form 2A FY 2022-23.pdf | 19 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Clover Windermere Phase 2 - Form 2 - 30-06-2022.pdf | 11 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Clover Windermere Phase 2 - Form 2 - 31-03-2023.pdf | 11 May 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Clover Windermere Phase II 31-03-2023.pdf | 11 May 2023 |
| Certificates of CA (Form 3)File: Clover Windermere Ph 2 - Form - 3 - 31-03-2023 Today.pdf | 11 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CW Form 1.pdf | 17 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: CW Form 2.pdf | 17 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: CW Form 2a.pdf | 17 Apr 2023 |
| Certificates of CA (Form 3)File: CA Certificate Form 3.pdf | 11 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Clover Windermere Phase II.pdf | 8 Mar 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 4 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 4 Feb 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2a.pdf | 4 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: AE Phase II Form 5 21 22.pdf | 6 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: AE - Clover Windermere Phase II - CA Certificate - FORM 5 - F,Y,2020-21.pdf | 6 Jan 2023 |
| Certificates of CA (Form 3)File: AE CW Ph 2 Form 3.pdf | 8 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: AE Phase II Form 5.pdf | 1 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 11 Nov 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 11 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2a.pdf | 11 Nov 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1.pdf | 5 Sep 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 5 Sep 2022 |
| Form 2AFile: form 2a.pdf | 5 Sep 2022 |
| Certificates of CA (Form 3)File: AE CW Ph 2 Form 3 31 3 2022.pdf | 5 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: CW PH 2 Sold Unsold.pdf | 4 Mar 2022 |
| Certificates of CA (Form 3)File: Form 3 CW PH 2 - 31-12-21.pdf | 4 Mar 2022 |
| Declaration about Commencement CertificateFile: Commencement Declaration.pdf | 24 Feb 2022 |
| CERSAI detailsFile: CERSAI Declaration.pdf | 24 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: CW PH 2 Form 1 31-12-21.pdf | 29 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 CW PH2 31-12-21.pdf | 29 Jan 2022 |
| Form 2AFile: CW PH 2 form 2A 30-9-2020.pdf | 29 Jan 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2a for windermere ph 2 30-9-21.pdf | 29 Jan 2022 |
| Certificates of CA (Form 3)File: AE - CW - Phase 2 - FORM 3 - compressed.pdf | 28 Jan 2022 |
| Disclosure of sold/ booked inventoryFile: Invenotry Clover Windermere Phase-II.pdf | 5 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Amalfi Enterprise Clover Windermere Phase-II FY 2019-20.pdf | 5 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Windermere 18-19.pdf | 18 Mar 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engi certi windermere ph 2.pdf | 18 Feb 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engi cert windermere ph2.pdf | 18 Feb 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 windermere ph II.pdf | 18 Feb 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 engi certi.pdf | 18 Feb 2020 |
| Form 2AFile: Form 2A windermere ph 2.pdf | 18 Feb 2020 |
| Form 2AFile: Form 2a cert windermere ph2.pdf | 18 Feb 2020 |
| Form 2AFile: form 2a windermere ph II.pdf | 18 Feb 2020 |
| Form 2AFile: form 2a certi.pdf | 18 Feb 2020 |
| Certificates of CA (Form 5)File: Form 5 Phase 2.pdf | 9 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Windermere PH 2.pdf | 28 Dec 2018 |
| Certificates of CA (Form 5)File: Form 5 Phase 2.pdf | 21 Dec 2018 |
| Form 2AFile: Form 5 Phase 2.pdf | 20 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: NA Order 2016 Kawathe phase II.pdf | 30 Mar 2018 |
| Building plan approval or NA orderFile: Revise NA Order.pdf | 19 Jul 2017 |
| Layout approvalFile: sheet 2- Phase 2 layout .pdf | 19 Jul 2017 |
| PAN CardFile: Amalfi Enterprise - PAN Card.pdf | 19 Jul 2017 |
| Copy of the legal title reportFile: Gat No 39A-2 1987 to 2016.pdf | 19 Jul 2017 |
| Copy of the legal title reportFile: Gat No 93 1987 to 2016.pdf | 19 Jul 2017 |
| Copy of the legal title reportFile: Gat No 94 1987 to 2016.pdf | 19 Jul 2017 |
| Copy of the legal title reportFile: 01072017 Clover Windermere Supplementary Search Report Title Report.pdf | 19 Jul 2017 |
| Details of encumbrancesFile: No Encumbrance Certificate.pdf | 19 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: sheet 2- Phase 2 layout .pdf | 19 Jul 2017 |
| Building Plan Approval (IOD)File: Revise NA Order.pdf | 19 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Satara
Computed across the 1,100+ Satara projects on ReraGenie, from their own filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 86 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Clover Windermere Phase -II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Clover Windereme1,100+ in Satara
Filed coordinates, straight-line distance. 3 registered projects within 2 km.
GRAND AVENUE
ALANKAR REALITIES
Clover Windermere Phase -I
Amalfi Enterprise
PETALS
DINESH VASUDEV BHARGUDE
Nivaan Riviera
Riverfront Developers
AMBIKA VIHAR
MALEKAR TAMBE ASSOCIATES LLP
Quadra Town
Bhujbal Brothers Properties
See every Satara project, with the district possession charts
Builder: Amalfi Enterprise
Amalfi Enterprise has 2 registrations on MahaRERA, including Clover Windermere Phase -I and Clover Windermere Phase -II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Satara district page.
Frequently asked questions
What does it mean that Clover Windermere Phase -II shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Clover Windermere Phase -II is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Clover Windermere Phase -II?
The registered promoter entity is Amalfi Enterprise, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Clover Windermere Phase -II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Clover Windermere Phase -II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Clover Windermere Phase -II?
The professionals named in the filing: Architect: Supriya Yadav; Architect: Architheque; Engineer: Semac Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Clover Windermere Phase -II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback