Home / Browse projects / Pune, Maharashtra / Clover Casablanca Phase II
Clover Casablanca Phase II
By Worthwhile Properties Pvt. Ltd.
RG-MH-11283 · RERA P52100002277 · Last updated on MahaRERA portal: 7 Jul 2021
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Clover Casablanca Phase II is a Residential / Group Housing project by Worthwhile Properties Pvt. Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100002277 on 31 Jul 2017. The registration is recorded completed; possession was promised by 31 Dec 2019. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameClover Casablanca Phase II
- TypeResidential / Group Housing
- Location
- Clover Casablanca road
- Sate
- Mawal
- Pune
- 412106
- Pincode412106
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100002277
- ReraGenie IDRG-MH-11283
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on31 Jul 2017
- Promised completion31 Dec 2019
- Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
- Buildings3 building records
- Documents filed44 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| F | NA | 8 | 0 | 0 | 0 | 0 |
| G | NA | 8 | 0 | 0 | 0 | 0 |
| I | NA | 6 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 7 Jul 2021, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
30 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Podiums (if any), at 0%.
F91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
G91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
I91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 7 Jul 2021, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed69
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| F | 23 | 23 |
| G | 23 | 23 |
| I | 23 | 23 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VOUSSIOR |
| Architect | Architheque |
| Engineer | Semac Consultants |
| Partner | Role in project |
|---|---|
| Worthwhile Properties Pvt. Ltd. | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1) Change in government Policies
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 25 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Dec 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Dec 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Mar 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Nov 2019
Documents filed44
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 - WPPL - Casablanca - FY 2019-20.pdf | 7 Jul 2021 |
| Certificates of CA (Form 3)File: Form 3 Casablanca.pdf | 18 Nov 2019 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Casablanca I Bldg OC.pdf | 18 Nov 2019 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC F and G building.pdf | 18 Nov 2019 |
| Certificates of Architect (Form 4)File: bldg I.pdf | 18 Nov 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc Cert.pdf | 14 Nov 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cert form 2.pdf | 14 Nov 2019 |
| Form 2AFile: Eng form 2a.pdf | 14 Nov 2019 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form - 5 Casablanca.pdf | 14 Nov 2019 |
| Certificates of CA (Form 5)File: form-5.pdf | 30 Sep 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 casablanca ph II.pdf | 30 Aug 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 casablanca ph II.pdf | 30 Aug 2019 |
| Certificates of CA (Form 3)File: Form 3 WPPL As on 30 06 2019.pdf | 30 Aug 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch cert Casablanca ph2.pdf | 3 May 2019 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engi cert Casablanca ph2.pdf | 3 May 2019 |
| Form 2AFile: Form 2a Casablanca ph2.pdf | 3 May 2019 |
| Certificates of CA (Form 3)File: WPPL Form 3.pdf | 12 Mar 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arc.pdf | 6 Feb 2019 |
| Form 2AFile: Form 2a casablanca ph 2.pdf | 6 Feb 2019 |
| Certificates of CA (Form 5)File: Form 5 Worthwhile.pdf | 21 Dec 2018 |
| Proforma of Allotment letterFile: Clover Casablanca Agreement for Sale .pdf | 30 Nov 2018 |
| Certificates of Architect (Form 4)File: bldg f form 4.pdf | 30 Nov 2018 |
| Certificates of Architect (Form 4)File: Form 4 bld G.pdf | 30 Nov 2018 |
| OtherFile: OC F and G building.pdf | 20 Jul 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: commencement certificate casablanca.pdf | 8 Mar 2018 |
| Building plan approvalFile: I bldg Sanction building plan.pdf | 21 Dec 2017 |
| Layout approvalFile: 23112017 sanction Layout.pdf | 21 Dec 2017 |
| Copy of Layout Approval (in case of layout)File: 23112017 sanction Layout.pdf | 21 Dec 2017 |
| Building Plan Approval (IOD)File: I bldg Sanction building plan.pdf | 21 Dec 2017 |
| Certificates of CA (Form 3)File: Form 3- CA Certificate-revised-Compressed.pdf | 26 Jul 2017 |
| Proforma of Allotment letterFile: Agreement and allotment letter.pdf | 26 Jul 2017 |
| Building plan approvalFile: F and G Layout.pdf | 25 Jul 2017 |
| Layout approvalFile: Layout sheet F, G and I.pdf | 25 Jul 2017 |
| PAN CardFile: Pancard Worthwhile.pdf | 25 Jul 2017 |
| Copy of the legal title reportFile: 91,1 Supplementary Title and Search Sate Kolan.pdf | 25 Jul 2017 |
| Copy of the legal title reportFile: 91,2 Supplementary Title and Search Sate Kolan.pdf | 25 Jul 2017 |
| Copy of the legal title reportFile: Title Report Padam No 91,1.pdf | 25 Jul 2017 |
| Copy of the legal title reportFile: Title Report Padam No 91,2.pdf | 25 Jul 2017 |
| Details of encumbrancesFile: No Encumbrance Certificate WPPL.pdf | 25 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Layout sheet F, G and I.pdf | 25 Jul 2017 |
| Building Plan Approval (IOD)File: F and G Layout.pdf | 25 Jul 2017 |
| Declaration in FORM BFile: Form B WPPL.pdf | 25 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 Arch certi CC ph 20001-min.pdf | 25 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering certificate.pdf | 25 Jul 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Clover Casablanca Phase I, A,B,C,D,E,H | 91-1 91- 2 Village Mouje Sate Taluka Maval Dist Pune | 138 | Completed | Dec 2016 | Late, Jan 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 44 filed documents as one ZIP, foldered, with a manifest
Keep Clover Casablanca Phase II on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Sate13,700+ in Pune
Filed coordinates, straight-line distance. 32 registered projects within 2 km.
Residential Building on CTS No 107/1P -GIRIVAR
SHRIVAR BUILDERS LLP
Aranya
Naiknavare Township LLP.
Land of Dreams
Krisala Buildscape LLP
Mount Vista
Tirupati Lands and Building Constructions
Osian LifeLands 2
Planet-i Realty
RKL INDRAYANI CITY
R K LUNKAD HOUSING COMPANY
Builder: Worthwhile Properties Pvt. Ltd.
Worthwhile Properties Pvt. Ltd. has 2 registrations on MahaRERA, including Clover Casablanca Phase II and Clover CASA 30. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Clover Casablanca Phase II is delayed beyond 31 Dec 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Clover Casablanca Phase II?
The registered promoter entity is Worthwhile Properties Pvt. Ltd., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Clover Casablanca Phase II?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Clover Casablanca Phase II?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Clover Casablanca Phase II?
The professionals named in the filing: Architect: VOUSSIOR; Architect: Architheque; Engineer: Semac Consultants. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Clover Casablanca Phase II?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback