Home / Browse projects / Pune, Maharashtra / CITY PLAZA
CITY PLAZA
By Shreenathji Construction LLP
RG-MH-17215 · RERA P52100028180 · Last updated on MahaRERA portal: 30 Jun 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 48 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
- All 1 earlier projects delivered on promise
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CITY PLAZA is a Commercial project by Shreenathji Construction LLP in Pune, Maharashtra, registered with MahaRERA as P52100028180 on 10 Feb 2021. The registration is recorded completed; possession was promised by 31 Dec 2026. The completion date has moved by 48 months from the original filing. 21 of the 63 units on this registration are recorded sold or booked, and 11 of 11 construction stages are filed complete.
At a glance
Project
- NameCITY PLAZA
- TypeCommercial
- Location
- 912/2
- 913/3 PLOT NO. A-2 AND A-3
- SAMSON NAGAR NEXT TO BANK OF MAHARASHTRA
- NEAR TALEGAON DABHADE RAILWAY STATION
- TALEGAON DABHADE
- TAL.- MAWAL
- DIST....
- Pincode410506
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100028180
- ReraGenie IDRG-MH-17215
Builder
- NameShreenathji Construction LLP
- Entity typePartnership
- GSTIN27ACYFS8448Q1ZL
- Declared earlier projects1 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on10 Feb 2021
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2022)
- Buildings1 building record
- Documents filed192 files
Current status
Figures as on 30 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CITY PLAZA | 1 | 8 | 6 | 0 | 63 | 63 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
CITY PLAZA · wing 1: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 30 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed77
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| CITY PLAZA | 1 | Rs 8.10 cr | Rs 8.10 cr |
| - | NA | Rs 55.00 lakh | Rs 55.00 lakh |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SAIE ENGINEERS & ALLIED DESIGNERS |
| Engineer | SAIE ENGINEERS & ALLIED DESIGNERS |
| Chartered Accountant | NEERAJ GORAKSH KALE |
| Chartered Accountant | PUSHPA BOGATI |
| Partner | Role in project |
|---|---|
| Shreenathji Construction LLP | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterDate-04/02/2023 To, The Maharashtra Real Estate Regulatory Authority, Reference- RERA REGISTRATION NO- P52100028180 Subject: Application for extension of date of completion. Hon. Sir/Madam, We, Partner 1. Sagar Ashok Shah 2. Rupesh manubhai Mehta 3. Yatin Suresh Shah of Shreenathji Construction LLP, have not yet completed the RERA projects namely- CITY PLAZA , Plot no-602 but complied with all the rules & regulations prescribed under RERA Act till date. Sir, , Yatin S. Shah - partner would like to prey as under - 1. Due to Covid 19 pandamic, I was in huge losses in my losses and my business ha
Reason as filed by the promoterDue to Covid 19 pandemic we were not able to construct anymore because of lack of labour contractor and the poor market condition, we were unable to complete the project within the due time.
Reason as filed by the promoter1. Project Details That we are the promoters/partners of the project namely “City Plaza”, registered with Maharashtra Real Estate Regulatory Authority under Registration No. P52100028180. 2. Declaration Regarding Project Status That the above-mentioned project has been marked as Lapsed by MahaRERA Authority, due to which we were unable to proceed further with the submission of the Completion Certificate (CC) and other documents required for compliances within the stipulated time. 3. Reason for Delay That the delay in completion and submission of documents has occurred due to the project being
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jan 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 28 Jan 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jun 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Jun 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 25 Feb 2025
Documents filed192
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 192 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: Full Occupancy Certificate 200225.pdf | 30 Jun 2026 |
| Occupational CertificateFile: city plaza resvised final plan 20 feb 25.pdf | 30 Jun 2026 |
| Occupational CertificateFile: City plaza revised final plan 2 20 feb 25.pdf | 30 Jun 2026 |
| Building plan approvalFile: Master Plan 29112024 highlighted.pdf | 25 Jun 2026 |
| Building plan approvalFile: city plaza revised plan 29 nov 2024 2.pdf | 10 Jun 2026 |
| Building plan approvalFile: City Plaza Revised cc order 29 nov 2024.pdf | 10 Jun 2026 |
| Commencement certificateFile: Commencement Certificates NA Order 130320.pdf | 8 Jun 2026 |
| Form 1File: FORM 1 Q2 300924.pdf | 8 Jun 2026 |
| Form 2File: FORM 2 Q2 300924.pdf | 8 Jun 2026 |
| Form 3File: FORM 3 Q2 300924.pdf | 8 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold booked inventory.pdf | 8 Jun 2026 |
| Form 1File: FORM 1 Q3 311224.pdf | 8 Jun 2026 |
| Form 2File: FORM 2 Q3 311224.pdf | 8 Jun 2026 |
| Form 3File: FROM 3 Q3 311224.pdf | 8 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold booked inventory.pdf | 8 Jun 2026 |
| Form 1File: FORM 1 Q4 310325.pdf | 8 Jun 2026 |
| Form 2File: FORM 2 Q4 310325.pdf | 8 Jun 2026 |
| Form 3File: FORM 3 Q4 310325.pdf | 8 Jun 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold unsold inventory Q4.pdf | 8 Jun 2026 |
| Withdrawal Update Form 1File: city 1.pdf | 8 Jun 2026 |
| Withdrawal Update Form 1File: city 1.pdf | 8 Jun 2026 |
| Withdrawal Update Form 1File: city 1.pdf | 8 Jun 2026 |
| Withdrawal Update Form 1File: city 1.pdf | 8 Jun 2026 |
| Withdrawal Update Form 1File: city 1.pdf | 8 Jun 2026 |
| Withdrawal Update Form 1File: city 1.pdf | 8 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2 Q1 300625.pdf | 8 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2 Q1 300625.pdf | 8 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2 Q1 300625.pdf | 8 Jun 2026 |
| Withdrawal Update Form 2File: FORM 2 Q1 300625.pdf | 8 Jun 2026 |
| Withdrawal Update Form 2File: FORM 3 Q4 310326.pdf | 8 Jun 2026 |
| Withdrawal Update Form 2File: FORM 3 Q4 310326.pdf | 8 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 Q1 300625.pdf | 8 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 Q2 300925.pdf | 8 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 Q3 311225.pdf | 8 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 Q3 311225.pdf | 8 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 Q3 311225.pdf | 8 Jun 2026 |
| Withdrawal Update Form 3File: FORM 3 Q3 311225.pdf | 8 Jun 2026 |
| Form 1File: Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 9 Aug 2025 |
| Form 2File: Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 9 Aug 2025 |
| Form 3File: CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf | 9 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 2 Disclosure of sold_ booked inventory.pdf | 9 Aug 2025 |
| Form 1File: Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 9 Aug 2025 |
| Form 2File: Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 9 Aug 2025 |
| Form 3File: CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf | 9 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 3 Disclosure of sold_ booked inventory.pdf | 9 Aug 2025 |
| Form 1File: Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 9 Aug 2025 |
| Form 2File: Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 9 Aug 2025 |
| Form 3File: CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf | 9 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 6 Disclosure of sold_ booked inventory.pdf | 9 Aug 2025 |
| Form 1File: Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 9 Aug 2025 |
| Form 2File: Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 9 Aug 2025 |
| Form 3File: CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf | 9 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 7 Disclosure of sold_ booked inventory.pdf | 9 Aug 2025 |
| Form 1File: Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 9 Aug 2025 |
| Form 2File: Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 9 Aug 2025 |
| Form 3File: CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf | 9 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 8 Disclosure of sold_ booked inventory.pdf | 9 Aug 2025 |
| Form 1File: Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 9 Aug 2025 |
| Form 2File: Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 9 Aug 2025 |
| Form 3File: CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf | 9 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 9 Disclosure of sold_ booked inventory.pdf | 9 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 10 Disclosure of sold_ booked inventory.pdf | 9 Aug 2025 |
| Form 1File: Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 9 Aug 2025 |
| Form 2File: Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 9 Aug 2025 |
| Form 3File: CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf | 9 Aug 2025 |
| Form 1File: Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 9 Aug 2025 |
| Form 2File: Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 9 Aug 2025 |
| Form 3File: CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf | 9 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 11 Disclosure of sold_ booked inventory.pdf | 9 Aug 2025 |
| Form 1File: Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 9 Aug 2025 |
| Form 2File: Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 9 Aug 2025 |
| Form 3File: CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf | 9 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold_ booked inventory.pdf | 9 Aug 2025 |
| Form 1File: 12 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 9 Aug 2025 |
| Form 2File: 12 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 9 Aug 2025 |
| Form 3File: 12 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf | 9 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: 12 Disclosure of sold_ booked inventory.pdf | 9 Aug 2025 |
| Form 1File: 13 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 9 Aug 2025 |
| Form 2File: 13 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf | 9 Aug 2025 |
| Form 3File: 13 CA Certificate on Project Cost & Fund withdrawal (Form 3).pdf | 9 Aug 2025 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| SHRINIDHI APARTMENT | NEAR SARASWATI VIDYA MANDIR TAPODHAM COLONY TALEGAON DABHADE | 1 | Completed | Jun 2018 | Dec 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 192 filed documents as one ZIP, foldered, with a manifest
Keep CITY PLAZA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near TALEGAON DABHADE13,700+ in Pune
Filed coordinates, straight-line distance. 138 registered projects within 2 km.
Everland
EVITA KRISALA TOWNSHIP LLP
EVERLYN
EVITA KRISALA TOWNSHIP LLP
ABHIMAAN HOMES PHASE 3
RISING PROPCON LLP
SURABHI CITY PHASE 1
Surabhi Group
ROHAN ANAND PHASE I
ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITE
Urban Life Phase 1
Kakade Vtp Associates
Builder: Shreenathji Construction LLP
Shreenathji Construction LLP has 1 registration on MahaRERA, including CITY PLAZA. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if CITY PLAZA is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CITY PLAZA?
The registered promoter entity is Shreenathji Construction LLP, a partnership as per the filing. Its GSTIN 27ACYFS8448Q1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CITY PLAZA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for CITY PLAZA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CITY PLAZA?
The professionals named in the filing: Architect: SAIE ENGINEERS & ALLIED DESIGNERS; Engineer: SAIE ENGINEERS & ALLIED DESIGNERS; Chartered Accountant: NEERAJ GORAKSH KALE; Chartered Accountant: PUSHPA BOGATI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CITY PLAZA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback