ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / CHAUHAN MANZIL

Registered No litigation declared Others project

CHAUHAN MANZIL

By GEETAI REALTY

RG-MH-31624 · RERA P51700079959 · Last updated on MahaRERA portal: 28 Mar 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
0 of 22Construction stages doneacross 2 buildings; furthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 34 documents Report an error

CHAUHAN MANZIL is a Others project by GEETAI REALTY in Thane, Maharashtra, registered with MahaRERA as P51700079959 on 8 Apr 2025. Possession is promised by 31 Dec 2027.

At a glance

Project

  • NameCHAUHAN MANZIL
  • TypeOthers
  • Location
    • KOHOJ KHUNTAVALI
    • AMBERNATH
    • Khuntavali
    • Ambarnath
    • Thane
    • 421501
  • Pincode421501
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700079959
  • ReraGenie IDRG-MH-31624

Builder

  • NameGEETAI REALTY
  • Entity typePartnership
  • Other registrations1 more →

Key dates

this monthRegisteredApr 2025PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Apr 2025
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed34 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CHAUHAN MANZIL WING-ANA80000
CHAUHAN MANZIL WING-BNA80000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 28 Mar 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Excavation, at 0%.

CHAUHAN MANZIL WING-A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
CHAUHAN MANZIL WING-B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 Mar 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed32

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots32
Closed/Covered7
Open Space25

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area864 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Mr Azazuddin A ChauhanAmbarnath(M Cl)Thane

Approvals and building plan

Sanctioning authorityAmbernath Municipal Council
Permissible FSI2964.17
Proposed, not sanctioned2,964 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 11 12, PANVELKAR PLAZA AMBERNATH EAST- 421501

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSR ARCHITECT
EngineerATUL KUDTARKAR
Chartered AccountantS U RADHAKRISHNANI
PartnerRole in project
GEETAI REALTY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 4 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed34

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3_280325.pdf28 Mar 2025
Other - FinanceFile: declaration on promoter letterhead.pdf26 Mar 2025
Other - FinanceFile: Declaration landowner.pdf26 Mar 2025
Other - FinanceFile: No Land Cost.pdf12 Mar 2025
Other - FinanceFile: Declaration cum undertaking for no sale.pdf12 Mar 2025
Other - TechnicalFile: lof dec lh.pdf12 Mar 2025
Proforma of Agreement for saleFile: AFS.pdf12 Mar 2025
PAN CardFile: Pan card.pdf11 Mar 2025
Copy of the legal title reportFile: title chauhan.pdf11 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: format A chauhan manzil update.pdf11 Mar 2025
Layout approvalFile: Plan 1.pdf4 Mar 2025
Building plan approvalFile: scan0274_compressed_11zon.pdf4 Mar 2025
Building plan approvalFile: scan0275_compressed_11zon.pdf4 Mar 2025
Copy of Layout Approval (in case of layout)File: Plan 1.pdf4 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: scan0274_compressed_11zon.pdf4 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: scan0275_compressed_11zon.pdf4 Mar 2025
Deviation Report with respect to model copy of AgreementFile: Deviataion AFS.pdf4 Mar 2025
Details of encumbrances concerned to FinanceFile: No Encumberance to Finance.pdf1 Mar 2025
Details of encumbrances concerned to FinanceFile: Non Encumberance of Legal.pdf1 Mar 2025
Proforma of Allotment letterFile: Allotment Letter.pdf1 Mar 2025
Declaration in FORM BFile: Form B - Dilip Mahale.pdf1 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: commencement certificate.pdf1 Mar 2025
Declaration about Commencement CertificateFile: declaration for CC.pdf1 Mar 2025
CERSAI detailsFile: Declaration for Cersai.pdf1 Mar 2025
Details of encumbrances concerned to LegalFile: No Encumberance to Finance.pdf1 Mar 2025
Details of encumbrances concerned to LegalFile: Non Encumberance of Legal.pdf1 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B - Bank.pdf1 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of Secured Unsecured Finance.pdf1 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect.pdf9 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2 engineer certificate.pdf18 Nov 2024
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT ALLOTMENT LETTER.pdf18 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: dilip mahale.pdf18 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: mashallah.pdf18 Nov 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: pritam narayan panvelkar.pdf18 Nov 2024

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CHAUHAN MANZIL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AMBERNATH7,600+ in Thane

2 kmCHAUHAN MANZILCompleted 213Lapsed / revoked 79Other 133Dot size: filed unitsN

Filed coordinates, straight-line distance. 425 registered projects within 2 km.

Builder: GEETAI REALTY

Geetai Realty has 2 registrations on MahaRERA, including VENU ZIPA TOWER and CHAUHAN MANZIL. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if CHAUHAN MANZIL is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CHAUHAN MANZIL?

The registered promoter entity is GEETAI REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CHAUHAN MANZIL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CHAUHAN MANZIL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CHAUHAN MANZIL?

The professionals named in the filing: Architect: SR ARCHITECT; Engineer: ATUL KUDTARKAR; Chartered Accountant: S U RADHAKRISHNANI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CHAUHAN MANZIL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CHAUHAN MANZIL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CHAUHAN MANZIL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.