Registration lapsed No litigation declared Others project

CHARMS HEIGHTS PHASE-III B2-B3

By Charms Developers

RG-MH-20289 · RERA P51700002081 · Last updated on MahaRERA portal: 13 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 42 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
14 of 22Construction stages doneacross 2 buildings; furthest along: Staircases, 98%
38 of 127Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 95 documents Report an error

CHARMS HEIGHTS PHASE-III B2-B3 is a Others project by Charms Developers in Thane, Maharashtra, registered with MahaRERA as P51700002081 on 31 Jul 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 42 months from the original filing. 89 of the 127 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameCHARMS HEIGHTS PHASE-III B2-B3
  • TypeOthers
  • Location
    • Sawarkar Nagar
    • Titwala
    • Manda
    • Kalyan
    • Thane
    • 421605
  • Pincode421605
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700002081
  • ReraGenie IDRG-MH-20289

Builder

  • NameCharms Developers
  • Entity typePartnership
  • PartnersJohn Mathew, Dhiraj Govind Patel, Sanjay Dhondu Borgaonkar, Bharat Pralhad Shah, Bharat Govind Vasani, Rajendra Devram Patel, Pradeep Purushottam Velani, Vishram Murji Gori, Deepak Shivji Patel, Gangaram Rajaram Sheganti, Bhavesh Popatlal Velani, Vishram Lalji Patel and 1 more
  • Other registrations7 more →
  • Completed2 of 8
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

10 months past promisethis monthRegisteredJul 2017First promiseJun 2022Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on31 Jul 2017
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 30 Jun 2022)
  • Buildings2 building records
  • Documents filed95 files

Current status

70%89 of 127 units booked
95.3%Work done, per cost certificate

Figures as on 13 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B2- BELUCANA111158765
B3- CORONANA121262062

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 13 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Staircases, at 98%.

B2- BELUCA90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor93%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.93%
B3- CORONA87%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises72%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.86%

Progress on shared amenities15

As on 13 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes66%
Street LightingYes66%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes66%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes66%
Open ParkingYes100%

Parking filed47

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots47
Closed/Covered25
Open Space22
BuildingClosed/CoveredOpen SpaceTotal
B2- BELUCA111223
B3- CORONA141024

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,710 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Jul 2025
LandownerVillageDistrict
RAJESH KRISHNABHAGWAN DIXITMandaThane

Approvals and building plan

Sanctioning authorityKDMC
Permissible FSI14339.24
Proposed, not sanctioned7,339 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSHOP NO 1 , YASHWANT BUILDING, GOKHALE ROAD, NAUPADA, THANE WEST MUMBAI 400602
Estimated costRs 22.50 cr
Cost incurredRs 21.45 cr
Work done95.33%
BuildingWingEstimatedIncurred
B3- CORONANARs 11.25 crRs 10.97 cr
B2- BELUCANARs 10.75 crRs 10.48 cr
-NARs 50.00 lakh-

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDilip Madhukar Dalvi
ArchitectD.M.DALVI AND ASSOCIATES
EngineerAjay Mahale
EngineerNITHYA THOMAS
Chartered AccountantMedha Jitendra Velani
Chartered AccountantHarish Gupta
Chartered AccountantHARISH OMPRAKASH GUPTA
PartnerRole in project
Charms Developers-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700017234Jun 2022 → Dec 2024

Reason as filed by the promoterDUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 31/12/2024

EXT51700012173Jun 2022 → Jun 2023

Reason as filed by the promoterWe request to grant extension for completion of the Project by 30th June , 2023 with the occupation certificate and accordingly we are applying for extension of time. Four Building in the phase 1 and phase 2 of the project have already received Occupational certificate. 70% construction of building B2 is completed and the construction of building B3 has been completed upto 65% which are registered as Phase III of the real estate project CHARMS HEIGHTS. We would like to convey that due to force majeure events, certain unavoidable circumstances and lastly due to the prevailing pandemic Covid-19,

EXT51700027860Jun 2022 → Dec 2025

Reason as filed by the promoterReasons for Delay 1 COVID-19 Pandemic (2020-2021): The unprecedented crisis resulted in labour shortages, disrupted supply chains, and financial constramts, significantly slowing down construction progress. Though authorities provided relief extensions, the long-term effects of the pandemic continued to impact the industry 2 Low Sales Volume: Due to market uncertainty during and after the pandemic sales slowed, affecting financial inflow and project funding. This delay in revenue generation impacted the speed of project execution 3 Labor and Material Shortages: Given the project's location in

Litigation declared2

CaseCourtStatus
39/2015/2015CIVIL JUDGE SENIOR DIVISION KALYANPENDING
126/2015/2015DISTRICT JUDGE KALYANFIXED FOR FINAL HEARING

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12501892Shraddha Shashank MhatreCharms Developers10/06/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed95

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 95 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Charms Developers- form1 Charms heights ph3.pdf13 Jan 2026
Withdrawal Update Form 2File: Charms Developers -Form 2 charms heights ph 3.pdf13 Jan 2026
Withdrawal Update Form 3File: RERA Certificate form 3 Charms Heights Phase 3 RERA 30june2025.pdf13 Jan 2026
Withdrawal Update Form 1File: Architect Certificate Charms Heights Signed.pdf12 Jan 2026
Withdrawal Update Form 2File: Engineer Certificate Charms Heights Signed.pdf12 Jan 2026
Withdrawal Update Form 3File: Form 3 heights June 2025.pdf12 Jan 2026
Withdrawal Update Form 1File: Architect Certificate Charms Heights Signed.pdf10 Sep 2025
Withdrawal Update Form 2File: Engineer Certificate Charms Heights Signed.pdf10 Sep 2025
Withdrawal Update Form 3File: Form 3 heights June 2025.pdf10 Sep 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD Dec 24.pdf16 May 2025
Declaration in FORM BFile: Charms Developers - Form B.pdf10 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf10 Mar 2025
Certificates of CA (Form 3)File: form 3 dec 24 revised.pdf10 Mar 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf10 Mar 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD Dec.pdf10 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2A 22-23.pdf10 Mar 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2A 23-24.pdf10 Mar 2025
Certificates of CA (Form 3)File: form 3 june 24.pdf25 Feb 2025
Certificates of CA (Form 3)File: form 3 dec 24.pdf25 Feb 2025
Certificates of CA (Form 3)File: form 3 sep 24.pdf25 Feb 2025
Certificates of CA (Form 3)File: form 3 march 24.pdf25 Feb 2025
Certificates of CA (Form 3)File: form 3 dec 24.pdf25 Feb 2025
Certificates of CA (Form 3)File: form 3 sep 24.pdf25 Feb 2025
Certificates of CA (Form 3)File: form 3 june 24.pdf25 Feb 2025
Certificates of CA (Form 3)File: form 3 march 24.pdf25 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 Charms Heights March 2024 (2).pdf25 Feb 2025
Declaration in FORM BFile: FORM B.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: charms Height Jul 11 2023 .pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Adobe Scan Oct 19 2023 .pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: charms Hight Dec 2023.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DocScanner Apr 23 2024 .pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: JS2024.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Dec 2024.pdf20 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng 300623.pdf20 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng 300923compressed.pdf20 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: charms Hight Dec 2023.pdf20 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng 310324.pdf20 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineers certificate heights 300624.pdf20 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers certificate heights 300924.pdf20 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers certificate heights 311224.pdf20 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality 310324.pdf20 Feb 2025
Certificates of CA (Form 3)File: RERA Certificate Charms Heights Phase 3- RERA June 2023 Signed_11zon.pdf30 Nov 2023
Certificates of CA (Form 3)File: RERA Certificate Charms Heights Phase 3- RERA September 2023 Signed_11zon.pdf30 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 21-22.pdf2 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 22-23.pdf2 Aug 2023
Disclosure of sold/ booked inventoryFile: Charms Heights Sold Unsold Inventory (1).pdf28 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Charms Heights Signed.pdf26 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Charms Heights Signed.pdf26 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: charms Height Jul.pdf20 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Scan 19 Jul 23.pdf20 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form2A 22-23.pdf7 Jul 2023
Disclosure of sold/ booked inventoryFile: Sold Unsold Charms Heights_compressed.pdf11 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Charms Height May 3, 2023 1-46 PM_compressed.pdf3 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 engineers certificate CDcompressed.pdf3 May 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2 engineers certificate CDcompressed.pdf3 May 2023
Certificates of CA (Form 3)File: Form 3 2022 compressed.pdf3 May 2023
Certificates of CA (Form 5)File: charms compressed.pdf3 May 2023
Declaration about Commencement CertificateFile: Scan 09 Aug 22 · 19·12·21.pdf9 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21).pdf9 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Scan 09 Aug 22 · 19·07·09.pdf9 Aug 2022
CERSAI detailsFile: Scan 09 Aug 22 · 19·12·59.pdf9 Aug 2022
Disclosure of sold/ booked inventoryFile: Scan 09 Aug 22 · 19·13·32_compressed.pdf9 Aug 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20).pdf9 Aug 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 Charm heights.pdf4 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form2 Heights.pdf4 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QAheights.pdf4 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: B2 - B3.pdf30 Sep 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Charms Heights Phase III.pdf29 Sep 2020
Certificates of CA (Form 5)File: B2 B3 - charms.pdf30 Sep 2019
Certificates of CA (Form 5)File: Heights_phaseIII_b2-b3.pdf13 Oct 2018
Certificates of CA (Form 3)File: HeightsPh3.pdf15 Jan 2018
Building plan approvalFile: planB3_14.pdf27 Jul 2017
Building plan approvalFile: planB2_9.pdf27 Jul 2017
Building plan approvalFile: planB2_10.pdf27 Jul 2017
Building plan approvalFile: planB3_11.pdf27 Jul 2017
Building plan approvalFile: planB3_12.pdf27 Jul 2017
Building plan approvalFile: planB3_13.pdf27 Jul 2017
Building plan approvalFile: planB2_8.pdf27 Jul 2017
Layout approvalFile: Layout.pdf27 Jul 2017
PAN CardFile: CHarms Developers PAN.pdf27 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
CHARMS HEIGHTS PHASE-II A1-A2P51700002670Titwala, ThaneAug 2017CompletedMar 2021Registered original: Mar 2019May 2018

How this compares with Thane

70%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 42 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CHARMS HEIGHTS PHASE-III B2-B3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Titwala7,600+ in Thane

2 kmCHARMS HEIGHTS PHASE-IIICompleted 45Lapsed / revoked 23Other 36Dot size: filed unitsN

Filed coordinates, straight-line distance. 104 registered projects within 2 km.

Builder: Charms Developers

Charms Developers has 8 registrations on MahaRERA, including CHARMS HEIGHTS PHASE-II A1-A2 and CHARMS HEIGHTS PHASE-III B2-B3. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that CHARMS HEIGHTS PHASE-III B2-B3 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if CHARMS HEIGHTS PHASE-III B2-B3 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CHARMS HEIGHTS PHASE-III B2-B3?

The registered promoter entity is Charms Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CHARMS HEIGHTS PHASE-III B2-B3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CHARMS HEIGHTS PHASE-III B2-B3?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for CHARMS HEIGHTS PHASE-III B2-B3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CHARMS HEIGHTS PHASE-III B2-B3?

The professionals named in the filing: Architect: Dilip Madhukar Dalvi; Architect: D.M.DALVI AND ASSOCIATES; Engineer: Ajay Mahale; Engineer: NITHYA THOMAS; Chartered Accountant: Medha Jitendra Velani; Chartered Accountant: Harish Gupta. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CHARMS HEIGHTS PHASE-III B2-B3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CHARMS HEIGHTS PHASE-III B2-B3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CHARMS HEIGHTS PHASE-III B2-B3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.