ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / KALAS DARSHAN

Registered No litigation declared Others project

KALAS DARSHAN

By JAY GANESH DEVELOPERS

RG-MH-69121 · RERA P51700034000 · Last updated on MahaRERA portal: 29 Jun 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
0 of 121Construction stages doneacross 11 buildings; furthest along: Excavation, 90%
295 of 1,357Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 126 documents Report an error

KALAS DARSHAN is a Others project by JAY GANESH DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700034000 on 17 Mar 2022. Possession is promised by 31 Dec 2026. 1,062 of the 1,357 units on this registration are recorded sold or booked, and 0 of 121 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameKALAS DARSHAN
  • TypeOthers
  • Location
    • Titwala
    • Kalyan
    • Thane
    • 421605
  • Pincode421605
  • RERA no.P51700034000
  • ReraGenie IDRG-MH-69121

Builder

  • NameJAY GANESH DEVELOPERS
  • Entity typePartnership
  • PartnersKARAN SATISH MISAL, SUBHASH HASTIMAL RANAWAT, RAJENDRA SUKHDEV MIRGANE, MAHESH NAMDEV INGALE
  • Other registrations5 more →
  • Completed1 of 6
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredMar 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Mar 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings11 building records
  • Documents filed126 files

Current status

78%1062 of 1,357 units booked

Figures as on 29 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 1NA881070107
Tower 2NA881070107
Tower 3NA881070107
Tower 4NA901980198
Tower 5NA902680268
Tower 6NA902680268
Tower 7NA7788088
-NA00000
-NA00000
-NA00000
Tower 8NA12122140214

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building11

As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 121 construction stages are filed complete across 11 buildings. The stage furthest along is Excavation, at 90%.

Tower 143%
ActivityProgress
Excavation90%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises52%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks71%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 243%
ActivityProgress
Excavation90%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises52%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks71%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 343%
ActivityProgress
Excavation90%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises52%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks71%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 443%
ActivityProgress
Excavation90%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises52%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks71%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 543%
ActivityProgress
Excavation90%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises52%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks71%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 643%
ActivityProgress
Excavation90%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises52%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks71%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 728%
ActivityProgress
Excavation90%
Basement (if any)9%
Podiums (if any)0%
Plinth9%
Stilt Floor0%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises52%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks71%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
-0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
-0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
-0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 843%
ActivityProgress
Excavation90%
Basement (if any)90%
Podiums (if any)0%
Plinth90%
Stilt Floor0%
Slabs of Super Structure70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises52%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks71%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities17

As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%
ExcavationYes20%
Basements & PlinthsYes15%

Parking filed2762

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots2,762
Open Space2,762
BuildingOpen SpaceTotal
Tower 1214214
Tower 2214214
Tower 3214214
Tower 4396396
Tower 5536536
Tower 6536536
Tower 7176176
Tower 8476476

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area59,800 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityMHADA
Permissible FSI125166.3
Proposed, not sanctioned125,166 sq m
Buildings approved11
Buildings sanctioned11

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMumbai

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUJWAL S BHOLE
EngineerPRATHAMESH EGADE
Chartered AccountantMUKESH SONI
Chartered AccountantNITIN DHAVAN balaji dhavan
PartnerRole in project
JAY GANESH DEVELOPERS-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
SM12500233Bhakti AchrekarJAY GANESH DEVELOPERS27/11/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 9 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed126

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 126 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: FORM 1 - JAY GANESH - MARCH 2026.pdf29 Jun 2026
Form 2File: FORM 2 - JAY GANESH - MARCH 2026_11zon.pdf29 Jun 2026
Form 3File: FORM 3 - JAY GANESH - MARCH 2026_11zon.pdf29 Jun 2026
Disclosure of Sold and Booked InventoryFile: FORM 3 - JAY GANESH - MARCH 2026_11zon.pdf29 Jun 2026
Form 1File: FORM 1 - JAY GANESH - DEC 25.pdf15 Apr 2026
Form 2File: FORM 2 - JAY GANESH - DEC 25_11zon.pdf15 Apr 2026
Form 3File: FORM 3 - JAY GANESH - DEC 25_11zon.pdf15 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCL FOR SOLD UNSOLD - DEC 25_11zon (1).pdf15 Apr 2026
Form 1File: FORM 1 - SEPT 25 - JAYGANESH.pdf18 Feb 2026
Form 2File: FORM 2 - SEPT 25 - JAYGANESH_11zon.pdf18 Feb 2026
Form 3File: FORM 3 - SEPT 25 - JAYGANESH_11zon.pdf18 Feb 2026
Disclosure of Sold and Booked InventoryFile: DISCL FOR SOLD UNSOLD - JAY GANESH - SEPT 25_11zon.pdf18 Feb 2026
Form 1File: FORM 1 - JAY GANESH - JUN 25.pdf5 Aug 2025
Form 2File: FORM 2 - JAY GANESH - JUN 25_11zon.pdf5 Aug 2025
Form 3File: FORM 3 - JAY GANESH - JUN 25_11zon.pdf5 Aug 2025
Disclosure of Sold and Booked InventoryFile: DISCL FOR SOLD UNSOLD - UPLOADATION - JUNE 2025.pdf5 Aug 2025
Form 1File: FORM 1 - JAY GANESH - MAR 2025.pdf15 Jul 2025
Form 2File: FORM 2 - JAY GANESH - MAR 2025- SIGN.pdf15 Jul 2025
Form 3File: FORM 3 - JAY GANESH - MAR 2025- 1_11zon.pdf15 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure for Sold-Unsold-31 March, 2025_11zon.pdf15 Jul 2025
Self-declaration of Quarterly ProgressFile: SELF DECL - JAY GANESH JAN TO MARCH - PDF- SIGN.pdf15 Jul 2025
Form 2A (FY 2024-2025)File: FORM 2A-31 March, 2025-Q4-F.Y.2024-25 (1)_11zon.pdf15 Jul 2025
Form 5 (FY 2024-2025)File: FORM 5 - JAY GANESH - FY 24-25.pdf15 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 30-06-2024.pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 30-09-2024.pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 31-12-2024.pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 31-03-2024.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 31 MARCH 2024.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 30 JUNE 2024.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 30 SEPTEMBER 2024.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 31 DECEMBER 2024.pdf6 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 31-03-2024.pdf6 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 31-12-2024.pdf6 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 30-09-2024.pdf6 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM -2 30-06-2024.pdf6 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM-05 01-04-2021 TO 31-03-2022.pdf6 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM -2A 2021-22.pdf6 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM -2A 2022-23.pdf6 Feb 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM -2A 2023-24.pdf6 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM-3 31 DECEMBER 2024.pdf6 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Q4-new.pdf5 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Q1_new.pdf5 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Q2-new.pdf5 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form-1 Q3-new.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 Q-4_11zon.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 Q-1_11zon.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 Q-2_11zon.pdf5 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 Q-3_11zon.pdf5 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 for Q1 FY 2023-24_11zon-DS.pdf4 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 for Q2 FY 2023-24_11zon-DS.pdf4 Mar 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3 for Q3 FY 2023-24_11zon-DS.pdf4 Mar 2024
PAN CardFile: pan card jay ganesh dev.pdf20 Feb 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 for FY 2022-23.pdf8 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ilovepdf_merged_11zon-sign.pdf11 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-Form 3 Q2-signed.pdf26 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate -Form 3- Q3-signed.pdf26 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Q2.pdf25 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate -Q3.pdf25 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: QUARTER-2-Engineer-COMPRESSED.pdf25 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: QUARTER-3-engineer_COMPRESSED.pdf25 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate.pdf2 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 08-07-2022- Engineer_COMPRESSED.pdf2 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Scanned (2).pdf2 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate.pdf1 Feb 2023
Building plan approvalFile: Building Approval.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-9_compressed.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-10_compressed.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-11_compressed.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-12.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-13.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-14.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-15.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-16.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-17.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-18.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-19.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-20.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-21.pdf11 Apr 2022
Building plan approvalFile: BUILDING PERMISSION AND PLANS-22.pdf11 Apr 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Approval.pdf11 Apr 2022

How this compares with Thane

78%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep KALAS DARSHAN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Titwala7,600+ in Thane

Builder: JAY GANESH DEVELOPERS

JAY GANESH DEVELOPERS has 6 registrations on MahaRERA, including OMSHREE and JAY GANESH RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if KALAS DARSHAN is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of KALAS DARSHAN?

The registered promoter entity is JAY GANESH DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in KALAS DARSHAN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against KALAS DARSHAN?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for KALAS DARSHAN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at KALAS DARSHAN?

The professionals named in the filing: Architect: UJWAL S BHOLE; Engineer: PRATHAMESH EGADE; Chartered Accountant: MUKESH SONI; Chartered Accountant: NITIN DHAVAN balaji dhavan. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in KALAS DARSHAN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About KALAS DARSHAN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save KALAS DARSHAN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.