Chandrasmit
By Metricon Builders Private Limited
RG-MH-75707 · RERA P52100047222 · Last updated on MahaRERA portal: 29 Jun 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 1 extension taken
- Rs 12.00 crore secured on the land, in favour of AU Small Finance Bank Ltd
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Chandrasmit is a Others project by Metricon Builders Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100047222 on 12 Oct 2022. The registration is recorded completed; possession was promised by 29 Jun 2026. The completion date has moved by 12 months from the original filing. 21 of the 53 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.
At a glance
Project
- NameChandrasmit
- TypeOthers
- Location
- Karve Road
- Kothrud
- Pune (M Corp.)
- Pune City
- Pune
- 411038
- Pincode411038
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100047222
- ReraGenie IDRG-MH-75707
Builder
- NameMetricon Builders Private Limited
- Entity typeCompany
- Managing DirectorAnil Malhari Salunkhe
- DirectorsSantosh Shivaji Kakade, Sandeep Dinkar Hawaldar, Harshavardhan Pravin Shimpi
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on12 Oct 2022
- Promised completion29 Jun 2026
- Revised completionRevised to 29 Jun 2026 (originally 30 Jun 2025)
- Buildings1 building record
- Documents filed134 files
Current status
Figures as on 29 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Chandrasmit | NA | 15 | 14 | 51 | 2 | 53 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 90%.
Chandrasmit: 64% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 65% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | Not applicable |
| Storm Water Drains | No | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed164
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership2
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Chandrakans Co-operative Housing Society Limited | Pune (M Corp.) | Pune |
| Anuya Co-operative Housing Society Limited | Pune (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Chandrasmit | NA | Rs 20.20 cr | Rs 15.49 cr |
| - | NA | Rs 20.90 lakh | - |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mangesh Gotal |
| Engineer | Pramod D Vitkare |
| Chartered Accountant | Deepak Sasar |
| Partner | Role in project |
|---|---|
| Metricon Builders Private Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Project “Chandrasmit” was registered with MAHARERA for a period commencing from 12.10.2022 and ending with 30.06.2025. The said Project got delayed because of prolongment on the part of sanctioning authority in connection to road handover and tree cutting permission. The promoter has taken due efforts to accentuate the construction work. The said project is nearly 60% complete as on date. The promoter hereby requests the MAHARERA authority to extend the project for a period of one year i.e. till 29.06.2026 under section 7 of the act.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Sep 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Oct 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 7 Feb 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Feb 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed134
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 134 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: FULL AND PART OC UPLOAD.pdf | 29 Jun 2026 |
| Withdrawal Update Form 1File: Metricon Form I Q4.pdf | 24 Apr 2026 |
| Withdrawal Update Form 2File: Metricon Form II Q4.pdf | 24 Apr 2026 |
| Withdrawal Update Form 3File: Metricon Form III Q4.pdf | 24 Apr 2026 |
| Withdrawal Update Form 1File: Form I Metricon Q3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 2File: Form II Metricon Q3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 3File: Form III Metricon Q3.pdf | 19 Jan 2026 |
| Withdrawal Update Form 1File: Metricon Form I Q2.pdf | 15 Oct 2025 |
| Withdrawal Update Form 2File: Metricon Form II Q2.pdf | 15 Oct 2025 |
| Withdrawal Update Form 3File: Metricon Form III Q2 FY 2025-26.pdf | 15 Oct 2025 |
| Withdrawal Update Form 1File: Metricon Form I Q 1 FY 2025-26.pdf | 2 Sep 2025 |
| Withdrawal Update Form 2File: Metricon Form II Q 1.pdf | 2 Sep 2025 |
| Withdrawal Update Form 3File: Metricon Form III Q4.pdf | 2 Sep 2025 |
| Form 5 (FY 2024-2025)File: Metricon Builders Pvt Ltd Form5 FY 2023-24.pdf | 18 Jun 2025 |
| Form 1File: Metricon Form I Q4.pdf | 16 Jun 2025 |
| Form 2File: Metricon Form II Q 4.pdf | 16 Jun 2025 |
| Form 3File: Form III Q4 Reivse.pdf | 16 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: SoldUnsold Inventory 31032025.pdf | 16 Jun 2025 |
| Disclosure of sold/ booked inventoryFile: Disclosure SOLD_UNSOLD Inventory 752025.pdf | 7 May 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure SALUNKHE SIR 742025.pdf | 7 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate FY 2023.pdf | 7 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Quality Assurance Certificate FY 2024.pdf | 7 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Metricon Form I Q4.pdf | 5 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Metricon Form III Q4.pdf | 5 May 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Metricon Form II Q 4.pdf | 5 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I Metricon FY 2024-25 Q3.pdf | 11 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III Metricon FY 2024-25 Q3.pdf | 11 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form II Metricon FY 2024-25 Q3.pdf | 11 Feb 2025 |
| Building plan approvalFile: 1.pdf | 7 Feb 2025 |
| Building plan approvalFile: 2.pdf | 7 Feb 2025 |
| Building plan approvalFile: 3.pdf | 7 Feb 2025 |
| Building plan approvalFile: 4.pdf | 7 Feb 2025 |
| Building plan approvalFile: 5.pdf | 7 Feb 2025 |
| Building plan approvalFile: 6.pdf | 7 Feb 2025 |
| Building plan approvalFile: 7.pdf | 7 Feb 2025 |
| Building plan approvalFile: 8.pdf | 7 Feb 2025 |
| Building plan approvalFile: 9.pdf | 7 Feb 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf | 7 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 7 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 9.pdf | 7 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 8.pdf | 7 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 7.pdf | 7 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 6.pdf | 7 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 5.pdf | 7 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 4.pdf | 7 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 7 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: 1.pdf | 7 Feb 2025 |
| Declaration about Commencement CertificateFile: FORMAT D.pdf | 7 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Metricon Builders Pvt Ltd Form5 FY 2023-24.pdf | 12 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I Metricon FY 2024-25 Q2.pdf | 23 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form III Metricon FY 2024-25 Q2.pdf | 23 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form II Metricon FY 2024-25 Q2.pdf | 23 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Metricon Form 1 Q 1.pdf | 30 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Metricon Form II Q 1.pdf | 30 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Metrion Form III Q 1.pdf | 30 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form I Metricon FY 2023-24 Q4.pdf | 8 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form II Metricon FY 2023-24 Q4.pdf | 8 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RERA Form III FY 2023-24 Q4 Metricon.pdf | 8 May 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_Asset_Id_Based_Search_12_03_2024_14_20_05_255.pdf | 13 Mar 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Discloure of interest in other Real Estate Anil Salunkhe sir.pdf | 17 Feb 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Discloure of interest in other Real Estate Sandeep Hawaldar sir.pdf | 14 Feb 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: FORMAT A.pdf | 14 Feb 2024 |
| Declaration about Commencement CertificateFile: Declaration about Commencemetn Certificate_compressed.pdf | 6 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Metricon Certificate.pdf | 6 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate Metricon.pdf | 6 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Metricon Builders.pdf | 6 Feb 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate_compressed.pdf | 6 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Metricon Form 5.pdf | 19 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 28 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 28 Nov 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 28 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf | 28 Oct 2023 |
| Building plan approvalFile: 2.pdf | 4 Oct 2023 |
| Building plan approvalFile: 3.pdf | 4 Oct 2023 |
| Building plan approvalFile: 4.pdf | 4 Oct 2023 |
| Building plan approvalFile: 5.pdf | 4 Oct 2023 |
| Building plan approvalFile: 6.pdf | 4 Oct 2023 |
| Building plan approvalFile: 7.pdf | 4 Oct 2023 |
| Building plan approvalFile: 8.pdf | 4 Oct 2023 |
| Building plan approvalFile: 9.pdf | 4 Oct 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 134 filed documents as one ZIP, foldered, with a manifest
Keep Chandrasmit on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kothrud13,700+ in Pune
Filed coordinates, straight-line distance. 295 registered projects within 2 km.
Pratik Nagar Palladio Kothrud Central
Vilas Javdekar Infinitee Developers Pvt. L
NEW FRIENDS
MAJESTIQUE DUROPOLIS PRIVATE LIMITED
SARVATRA CO-OP HSG SOCIETY LTD
Suryakant Kakade
Kshitij Residency
Yash Buildcon
MAYUK
MAYUR CORPORATION
Pune Baner Project-Tower 4 and 5
Goel Ganga Ventures India Private Limited
Builder: Metricon Builders Private Limited
Metricon Builders Private Limited has 1 registration on MahaRERA, including Chandrasmit. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Chandrasmit is delayed beyond 29 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Chandrasmit?
The registered promoter entity is Metricon Builders Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Chandrasmit?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Chandrasmit?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Chandrasmit?
The professionals named in the filing: Architect: Mangesh Gotal; Engineer: Pramod D Vitkare; Chartered Accountant: Deepak Sasar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Chandrasmit?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback