Home / Browse projects / Mumbai Suburban, Maharashtra / CENTRICO
CENTRICO
By CRESCENT AMITY REALTORS PVT.LTD
RG-MH-24069 · RERA P51800008480 · Last updated on MahaRERA portal: 23 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 4 cases
- 12 complaints at MahaRERA
- Completion date moved by 36 months
- 3 extensions taken
Clear
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
CENTRICO is a Residential / Group Housing project by CRESCENT AMITY REALTORS PVT.LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800008480 on 19 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 142 of the 166 units on this registration are recorded sold or booked, and 14 of 22 construction stages are filed complete. 12 complaints are on record with the regulator.
At a glance
Project
- NameCENTRICO
- TypeResidential / Group Housing
- Location
- GAUTAM BUDDHA MARG
- ORLEM MALAD WEST
- Borivali
- Mumbai Suburban
- 400064
- Pincode400064
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800008480
- ReraGenie IDRG-MH-24069
Builder
- NameCRESCENT AMITY REALTORS PVT.LTD
- Entity typeCompany
- Managing DirectorJIGAR SHAILESH VORA
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on19 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
- Buildings2 building records
- Documents filed109 files
Current status
Figures as on 23 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| CENTRICO SALE BUILDING | NA | 49 | 41 | 166 | 0 | 166 |
| COMPOSITE BUILDING | NA | 26 | 26 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 23 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 94%.
CENTRICO SALE BUILDING75%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 90% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 94% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 5% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 80% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
COMPOSITE BUILDING100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 23 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 40% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed155
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| CENTRICO SALE BUILDING | 138 | 138 |
| COMPOSITE BUILDING | 17 | 17 |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 104.06 cr | Rs 96.15 cr |
| CENTRICO SALE BUILDING | NA | Rs 81.06 cr | Rs 73.15 cr |
| COMPOSITE BUILDING | NA | Rs 23.00 cr | Rs 23.00 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VISHWAS SATODIA |
| Engineer | GOKANI CONSULTANTS PVT LTD |
| Engineer | MAHESH TANAJI GODAMBE |
| Chartered Accountant | DILIP S KAPADIA |
| Partner | Role in project |
|---|---|
| CRESCENT AMITY REALTORS PVT.LTD | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1) Delay in fund release from financial institutions who have funded the project 2) Slow collections from buyers 3) Delay in work due to slow fund release of customer collections by financial institution which has control over the collection account 4) Approval delays 5). Repeated stoppages due to the above had a impact on the overall delivery cycle of the project.
Reason as filed by the promoterDue to delay in obtaining amended plan approvals from SRA, the project got delayed and hence we are applying for extension to Maharera. The construction work is substantially completed and only few finishing items are pending which will be completed as soon as possible. The project is on the verge of completion and will be finished within extended timelines proposed by us.
Reason as filed by the promoter1. Brief Summary of Major work which is completed is as follows :- (i) RCC work and major finishing work is completed as per Approved Plans. (ii) Three Lifts of the said Building are installed and operational. (iii) Electrical work is completed and meters are installed. (iv) STP work is completed (v) O.H tank, U.G.tank and plumbing work including work of installation of water pipes is completed. 2. Now, extension is sought for completion of following pending work:- (i) Fire Fighting Work (ii) Parking work 3. The pending work is expected to be completed in next 3 months. Thereafter application
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 2479/2014 | CITY CIVIL COURT DINDOSHI | Closed |
| 10/2014 | MAHARASHTRA SLUM TRIBUNAL | Closed |
| 3165/2015 | CITY CIVIL COURT DINDOSHI | Ongoing |
| 11/2019 | MAHARASHTRA SLUM TRIBUNAL | Ongoing |
Complaints filed with MahaRERA12
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000209434 | Crescent Amity Realtors Pvt. Ltd. | Hemant Jayprakash Bhavsar | 16/12/2021 |
| CC006000000199013 | Hemant Bhavsar | Crecent Amity Pvt Ltd | 30/11/2021 |
| CC006000000221079 | KIRTI G. SANGHVI | M/S. CRESCENT AMITY REALTORS PVT. LTD. | 05/05/2022 |
| CC12500091 | CAROL PRIYESHKAR KUMAR | CRESCENT AMITY REALTORS PVT.LTD | 09/01/2025 |
| CC12501588 | Clyde Rebello | CRESCENT AMITY REALTORS PVT.LTD | 14/05/2025 |
| CC12501590 | Clyde Rebello | CRESCENT AMITY REALTORS PVT.LTD | 14/05/2025 |
| CC12600075 | VISHAL KANAHAIYALAL RAWAL | CRESCENT AMITY REALTORS PVT.LTD | 05/01/2026 |
| CC12600831 | Mrs Candice Waltrude Gomes | CRESCENT AMITY REALTORS PVT.LTD | 14/02/2026 |
| CC12600832 | Mrs Candice Waltrude Gomes | CRESCENT AMITY REALTORS PVT.LTD | 14/02/2026 |
| CC12602971 | Mark Thomas Miranda | CRESCENT AMITY REALTORS PVT.LTD | 20/05/2026 |
| CC12603051 | CRESCENT AMITY REALTORS PVT.LTD | Hitesh Dharamshi Savla (Allottee) | 23/05/2026 |
| CC12605125 | Elton Bruno DSouza | CRESCENT AMITY REALTORS PVT.LTD | 11/08/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 29 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Dec 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 2 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed109
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 109 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: form - 1 crescent 31-3-26.pdf | 23 May 2026 |
| Withdrawal Update Form 2File: form-2 crescent 31-3-26.pdf | 23 May 2026 |
| Withdrawal Update Form 3File: form-3 crescent 31-3-26.pdf | 23 May 2026 |
| Withdrawal Update Form 1File: form - 1 - 31-12-25.pdf | 16 Feb 2026 |
| Withdrawal Update Form 2File: form-2 31-12-25.pdf | 16 Feb 2026 |
| Withdrawal Update Form 3File: form-3 - 31-12-25.pdf | 16 Feb 2026 |
| Building plan approvalFile: Scan-1084 copy1.pdf | 31 Dec 2025 |
| Building plan approvalFile: Scan-1085 copy1.pdf | 31 Dec 2025 |
| Building plan approvalFile: Scan-1086 copy1.pdf | 31 Dec 2025 |
| Building plan approvalFile: Scan-1087 copy1.pdf | 31 Dec 2025 |
| Building plan approvalFile: Scan-1089 copy1.pdf | 31 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 Crescent.pdf | 10 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 Crescent.pdf | 10 Dec 2025 |
| Withdrawal Update Form 2File: form-2 30-9-25.pdf | 10 Dec 2025 |
| Withdrawal Update Form 2File: form-2 30-9-25.pdf | 10 Dec 2025 |
| Withdrawal Update Form 3File: FORM -3 CRESCENT.pdf | 10 Dec 2025 |
| Withdrawal Update Form 3File: FORM-3 CENTRICO 30-6-25.pdf | 10 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 Crescent.pdf | 9 Dec 2025 |
| Withdrawal Update Form 1File: Form 1 Crescent.pdf | 9 Dec 2025 |
| Withdrawal Update Form 2File: form-2 30-9-25.pdf | 9 Dec 2025 |
| Withdrawal Update Form 2File: form-2 30-9-25.pdf | 9 Dec 2025 |
| Withdrawal Update Form 3File: FORM -3 CRESCENT.pdf | 9 Dec 2025 |
| Withdrawal Update Form 3File: FORM -3 CRESCENT.pdf | 9 Dec 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 CENTRICO 31-3-25.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM-1 CENTRICO AS ON 31-3-25.pdf | 21 Apr 2025 |
| Certificates of CA (Form 3)File: crescent rera certificate 31-3-25.pdf | 16 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: crescent eng certificate 31-3-25.pdf | 16 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: orlem sale.pdf | 3 Feb 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: orlem rehab.pdf | 3 Feb 2025 |
| Declaration in FORM BFile: Crescent Form B.pdf | 11 Dec 2024 |
| Certificates of CA (Form 3)File: form-3.pdf | 11 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2.pdf | 11 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a as on 31-3-24.pdf | 11 Dec 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a as on 30-9-24.pdf | 11 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: RERA Inventory List.pdf | 4 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: RERA LIST.pdf | 2 Dec 2024 |
| Disclosure of sold/ booked inventoryFile: RERA LIST.pdf | 29 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: crpl_0001.pdf | 25 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form-1 rehab.pdf | 4 May 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form-1 sale.pdf | 4 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 from CA STATUTORY AUDITOR(31-3-2024).pdf | 4 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form -2.pdf | 18 Oct 2023 |
| Certificates of CA (Form 3)File: form-3.pdf | 18 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form -5.pdf | 18 Oct 2023 |
| Declaration about Commencement CertificateFile: Form D -Crescent.pdf | 14 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSER DOCUMENT.pdf | 14 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: QUALITY ASsURANCE.pdf | 12 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Certificate March-23.pdf | 12 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 from CA STATUTORY AUDITOR(31-3-2023).pdf | 12 Oct 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE FOR MAR-23 SALE.pdf | 29 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 ARCHITECT CERTIFICATE FOR MAR-23 REHAB.pdf | 29 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Certificate March-23.pdf | 29 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: discloser of flat- centrico_0001.pdf | 29 Apr 2023 |
| CERSAI detailsFile: CARSAI.pdf | 8 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form-1 rehab crescent.PDF | 3 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form-1 sales crescent.PDF | 3 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5 from CA STATUTORY AUDITOR(31-3-2019) (1).pdf | 30 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5 from CA STATUTORY AUDITOR(31-3-2020) (1).pdf | 30 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 from CA STATUTORY AUDITOR(31-3-2022) Crescent.pdf | 30 Jan 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: CC-SB-1.pdf | 2 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: QUALITY ASsURANCE sep 22.pdf | 2 Jan 2023 |
| Certificates of CA (Form 3)File: C A CERTIFICATE FORM 3.pdf | 22 Dec 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect-1.pdf | 26 May 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RB-2 (123).pdf | 26 May 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineers certificate 123.pdf | 26 May 2022 |
| Certificates of CA (Form 3)File: FORM 3 31-03-2022.pdf | 26 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: CC FOR REHAB BLDG 2.pdf | 4 Apr 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 from CA STATUTORY AUDITOR(31-3-2021).pdf | 29 Sep 2021 |
| Building plan approvalFile: IOD.pdf | 23 Sep 2021 |
| Building plan approvalFile: 1.pdf | 23 Sep 2021 |
| Building plan approvalFile: 2.pdf | 23 Sep 2021 |
| Building plan approvalFile: 3.pdf | 23 Sep 2021 |
| Building Plan Approval (IOD)File: IOD.pdf | 23 Sep 2021 |
| Building Plan Approval (IOD)File: 1.pdf | 23 Sep 2021 |
| Building Plan Approval (IOD)File: 2.pdf | 23 Sep 2021 |
| Building Plan Approval (IOD)File: 3.pdf | 23 Sep 2021 |
| Disclosure of sold/ booked inventoryFile: disclosure of sold flat centrico 1.pdf | 24 Aug 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: cc.pdf | 25 Jul 2020 |
| Certificates of CA (Form 5)File: CENTRICO -FORM 5.pdf | 22 Oct 2019 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: arc-certificate(1).pdf | 30 May 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 109 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep CENTRICO on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near ORLEM MALAD WEST6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 388 registered projects within 2 km.
Ruparel Stardom
AMI MODISPACES LLP
Chandak Treesourus
CHANDAK REALTORS PRIVATE LIMITED
ANCHORPOINT AVIARA
YUKTI INFRAPROJECTS LLP
AURIS ILARIA TOWER A
TRANSCON-SHETH CREATORS PRIVATE LIMITED
ADHRIT
MUNDARA DEVELOPERS
IRENE WING B PHASE 1
Sheth Creators and Sunvision Private Limit
See every Mumbai Suburban project, with the district possession charts
Builder: CRESCENT AMITY REALTORS PVT.LTD
CRESCENT AMITY REALTORS PVT.LTD has 1 registration on MahaRERA, including CENTRICO. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if CENTRICO is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of CENTRICO?
The registered promoter entity is CRESCENT AMITY REALTORS PVT.LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in CENTRICO?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against CENTRICO?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for CENTRICO?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at CENTRICO?
The professionals named in the filing: Architect: VISHWAS SATODIA; Engineer: GOKANI CONSULTANTS PVT LTD; Engineer: MAHESH TANAJI GODAMBE; Chartered Accountant: DILIP S KAPADIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in CENTRICO?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback