Home / Browse projects / Thane, Maharashtra / CENTRAL EMPIRE

Registration lapsed No litigation declared Others project

CENTRAL EMPIRE

By AL ABRAAJ BUILDERS AND DEVELOPERS

RG-MH-28927 · RERA P51700027277 · Last updated on MahaRERA portal: 20 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
21 of 77Construction stages doneacross 7 buildings; furthest along: Sanitary Fittings within the flats /..., 75%
0Complaints at MahaRERAon this registration
Jump to the 38 documents Report an error

CENTRAL EMPIRE is a Others project by AL ABRAAJ BUILDERS AND DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700027277 on 1 Dec 2020. Possession was promised by 30 Jun 2026 and is now 4 months past that date.

At a glance

Project

  • NameCENTRAL EMPIRE
  • TypeOthers
  • Location
    • Talao Pali Road
    • Kausa
    • Mumbra
    • Thane (M Corp.)
    • Thane
    • 400612
  • Pincode400612
  • RERA no.P51700027277
  • ReraGenie IDRG-MH-28927

Builder

  • NameAL ABRAAJ BUILDERS AND DEVELOPERS
  • Entity typePartnership
  • PartnersUMAR SHAMSHAD USMANI, SALIM ABDUL MAJEED DHOLE, QAMAR ALAM MOHD UMAR SIDDIQUI, JAMALUDDIN RIYAZUDDIN KHAN, IQBAL ISMAIL MUKHRI, MOHAMMED IRFAN MOHAMMED NASIM KHAN

Key dates

4 months past promisethis monthRegisteredDec 2020PromisedJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Dec 2020
  • Promised completion30 Jun 2026
  • Revised completionNone
  • Buildings7 building records
  • Documents filed38 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING 1NA120000
BUILDING 2NA120000
BUILDING 3NA120000
BUILDING 4NA120000
BUILDING 5NA120000
BUILDING 6NA220000
BUILDING 7NA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building7

As on 20 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

21 of 77 construction stages are filed complete across 7 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 75%.

BUILDING 162%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)50%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
BUILDING 258%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
BUILDING 358%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
BUILDING 458%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
BUILDING 558%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
BUILDING 658%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%
BUILDING 758%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.65%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%

Progress on shared amenities15

As on 20 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,895 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI11767.58
Proposed, not sanctioned11,768 sq m
Buildings approved7
Buildings sanctioned7

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch576, Dosti Apartments, Old Mumbai Road, Kausa Thane, MH 400612

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSachin Charpe of RIGHT ANGLE Architect
EngineerSSCONS PROP BHONDE RAJKUMAR K
Chartered AccountantSHAIKH & ASSOCIATES
PartnerRole in project
AL ABRAAJ BUILDERS AND DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Nov 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Nov 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 7 Jan 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Jan 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed38

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1 -ARCH CERT-ALABRAAJ-DEC-24.pdf20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 AL- ABRAAJ BUILDER DEVELOPERS - SEPT-24.pdf19 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE - AL ABRAAJ - SEPT-24.pdf18 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 AL ABRAJ DEC-24.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Al Abaraaj 30-09-24.pdf18 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Al Abaraaj 31 12 2024.pdf18 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 - Architech Certificate- AL ABRAAJ 31032024.pdf28 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - ENGINEER - CERTIFICATE -Al Abraaj 31032024.pdf28 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 - CA CERTIFICATE - 31032024.pdf28 May 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - ANNUAL REPORT - 31032024.pdf28 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ALABRAAJ -Form 1 - ARCHITECT CERT-30092023_compressed.pdf10 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ALABRAAJ -Form 2 - ENGINEERS CERT-30092023.pdf10 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: AL ABRAAJ -Form 3 - CA Certificate - 30092023_compressed.pdf10 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ALABRAAJ -Form 5 - ANNUAL REPORT - FY-2022-23.pdf10 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_RERA CERTIFICATE _ AL-ABRAAJ_21122021_compressed.pdf19 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1 FORM 1 - ARCHITECT CERTIFICATE _ AL-ABRAAJ _31122022.pdf19 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2 - ENGINEERS CERTIFICATE - AL ABRAAJ -21122021.pdf19 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2 FORM 2 - ENGINEERS CERTIFICATE - AL ABRAAJ -31122022.pdf19 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 FORM 3 - CA CERTIFICATE - 21122021.pdf19 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 FORM 3 - CA CERTIFICATE - 31122022_compressed.pdf19 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: AL ABRAAJ_ FORM 5_ANNUAL REPORT -21-22.pdf19 Feb 2023
Building plan approvalFile: APPROVED PLAN - 31122021_compressed.pdf7 Jan 2022
Building Plan Approval / NA Order for plotted developmentFile: APPROVED PLAN - 31122021_compressed.pdf7 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENTCERTIFICATE - 2.pdf7 Jan 2022
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATEF-CC_S09_0110_21_31122021.pdf7 Jan 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: ANNUAL REPORT FORM 5 - 2020-21.pdf7 Jan 2022
Details of encumbrancesFile: FORM B Declaration - Alabraaj (1).pdf26 Nov 2020
Proforma of Allotment letterFile: Allotment Letter - amended.pdf26 Nov 2020
Proforma of Allotment letterFile: Al Abraaj (Central Empire) Agreement for Sale - AMENDED 26112020.pdf26 Nov 2020
Layout approvalFile: LAYOUT - PLAN - FINAL.pdf25 Nov 2020
Building plan approvalFile: BUILDING APROVAL PLAN - FINAL.pdf25 Nov 2020
PAN CardFile: PAN -ALABRAAJ.pdf25 Nov 2020
Copy of the legal title reportFile: TITLE CERTFICATE.pdf25 Nov 2020
Copy of Layout Approval (in case of layout)File: LAYOUT - PLAN - FINAL.pdf25 Nov 2020
Building Plan Approval / NA Order for plotted developmentFile: BUILDING APROVAL PLAN - FINAL.pdf25 Nov 2020
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATEF-CC_S09_0110_20.pdf25 Nov 2020
Declaration in FORM BFile: FORM B Declaration - Alabraaj (1).pdf25 Nov 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 CA CERTIFICATE.pdf25 Nov 2020

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CENTRAL EMPIRE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kausa, Mumbra7,600+ in Thane

Builder: AL ABRAAJ BUILDERS AND DEVELOPERS

AL ABRAAJ BUILDERS AND DEVELOPERS has 1 registration on MahaRERA, including CENTRAL EMPIRE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that CENTRAL EMPIRE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if CENTRAL EMPIRE is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CENTRAL EMPIRE?

The registered promoter entity is AL ABRAAJ BUILDERS AND DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CENTRAL EMPIRE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for CENTRAL EMPIRE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CENTRAL EMPIRE?

The professionals named in the filing: Architect: Sachin Charpe of RIGHT ANGLE Architect; Engineer: SSCONS PROP BHONDE RAJKUMAR K; Chartered Accountant: SHAIKH & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CENTRAL EMPIRE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CENTRAL EMPIRE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CENTRAL EMPIRE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.