Home / Browse projects / Pune, Maharashtra / CAVANSITE

Registration lapsed No litigation declared Residential / Group Housing project

CAVANSITE

By S2 REALTY

RG-MH-01744 · RERA P52100004059 · Last updated on MahaRERA portal: 12 Nov 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 39 months past the filed date
  • 10 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2023Possession promised39 months past this date
18 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 0%
10Complaints at MahaRERAon this registration
Jump to the 23 documents Report an error

CAVANSITE is a Residential / Group Housing project by S2 REALTY in Pune, Maharashtra, registered with MahaRERA as P52100004059 on 7 Aug 2017. Possession was promised by 31 Jul 2023 and is now 39 months past that date. 10 complaints are on record with the regulator.

At a glance

Project

  • NameCAVANSITE
  • TypeResidential / Group Housing
  • Location
    • BANGALORE PUNE BYPASS
    • WARJE
    • Haveli
    • Pune
    • 411052
  • Pincode411052
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100004059
  • ReraGenie IDRG-MH-01744

Builder

  • NameS2 REALTY
  • Entity typePartnership
  • PartnerSACHIN BALKRISHNA KULKARNI
  • Other registrations6 more →
  • No longer live7 lapsed, de-registered or revoked
  • Declared earlier projects7 →

Key dates

39 months past promisethis monthRegisteredAug 2017PromisedJul 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Aug 2017
  • Promised completion31 Jul 2023
  • Revised completionNone
  • Buildings3 building records
  • Documents filed23 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA00000
BNA120000
CNA50000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 12 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.

A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
C82%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 12 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingNoNot applicable

Parking filed94

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots94
Closed/Covered94
BuildingClosed/CoveredTotal
B7070
C2424

Land and ownership7

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
LandownerVillageDistrict
GAJANAN SUNDARRAO BHELKEKothrudPune
UTTAMRAO SUNDARRAO BHELKEKothrudPune
DILIPKUMAR RAJARAM DHONEKothrudPune
BHELKE DHONE ASSOCIATESKothrudPune
SAHEBRAO SUNDARRAO BHELKEKothrudPune
BHALCHANDRA RAJARAM DHONEDhankawadiPune
LEELABAI DNYANESHWAR BARATEWarjePune

Approvals and building plan

Permissible FSI11896.07
Proposed, not sanctioned7,160 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKOTHRUD PUNE

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAY AERAM
EngineerSPECTRUM CONSULTANTS
PartnerRole in project
S2 REALTY-

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC005000000054184Darshana Anup Parnaik & Anup Arvind ParnaikS2 Realty26/03/2020
CC005000000064276Mr. Nilesh Uttam Dudhankar & Mrs. Archana Nilesh DudhankarS2 REALTY15/06/2020
CC005000000064282Mr. Mahesh Narasappa Bubanale & Mr. Mantesh Narasappa BubanaleS2 REALTY15/06/2020
CC005000000064283Rohan Ram Deshpande, Dipti Rohan Deshpande & Rohini Ram DeshpandeS2 Realty15/06/2020
CC005000000064285Mrs. Vrushali Janardan Shinde & Mr. Anil Arvind PatilS2 REALTY16/06/2020
CC005000000064301Mr. Dhananjay Gajanan Godbole & Mrs. Ashwini Dhananjay GodboleS2 REALTY25/06/2020
CC005000000064333Shubhangi Madhukar ShipteS2 REALTY01/07/2020
CC005000000085285Sangram Vishwas Shinde and Rakhi Sangram ShindeS2 Realty28/02/2021
CC005000000054192Suhas Jayant Kulkarni and Rasika Suhas KulkarniS2 REALTY02/04/2020
CC005000000054185Sachin Sushil WadiS2 Realty26/03/2020

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Nov 2024

Documents filed23

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4-Cavasnite.pdf12 Nov 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: CAVANSITE B WING society formation certificate.pdf8 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2024-03-21 11-28-Wing C Completion.pdf8 Nov 2024
Other - TechnicalFile: Letter to PMC for change of Name.pdf8 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: COMPLETION CERTIFICATE -B BUILDING.pdf26 Jun 2023
Other - TechnicalFile: S2 Realty Retirement Deed_11zon.pdf8 Apr 2023
Certificates of CA (Form 5)File: Cavansite.pdf15 Oct 2018
Details of encumbrancesFile: DHFL-No dues.pdf30 Mar 2018
Details of encumbrancesFile: Mortgage Deed - ICICI.pdf20 Dec 2017
Proforma of Allotment letterFile: Cavansite - RERA compliant Draft.pdf6 Sep 2017
Details of encumbrancesFile: Index II cavansite.pdf28 Jul 2017
Declaration in FORM BFile: Form B Cavansite.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate Cavansite.pdf27 Jul 2017
Certificates of CA (Form 3)File: CA Certificate Cavansite.pdf27 Jul 2017
Proforma of Allotment letterFile: Self Declaration Regarding Darfts Cavansite.pdf27 Jul 2017
Layout approvalFile: LAYOUT- CAVANSITE.pdf10 Jul 2017
Building plan approvalFile: LAYOUT- CAVANSITE.pdf10 Jul 2017
PAN CardFile: PAN S2 REALTY (2).PDF10 Jul 2017
Copy of the legal title reportFile: TSR- CAVANSITE.pdf10 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT- CAVANSITE.pdf10 Jul 2017
Building Plan Approval (IOD)File: LAYOUT- CAVANSITE.pdf10 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: cc- cavn.pdf10 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEER'S CERTIFICATE (SIGN) CAVANSITE Scan.pdf10 Jul 2017

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
ANANDGRAM YAVATYAVAT DAUND PUNE622CompletedDec 2014Late, Mar 2015
URBANGRAM KIRKATWADIKIRKATWADI HAVELI PUNE226CompletedJun 2014Late, Feb 2015
ANANDGRAM TALEGAON DHAMDHERETALEGAON DHAMDHERE SHIRUR PUNE303CompletedJun 2014Late, Oct 2014
URBANGRAM KONDHAVE DHAVADE PHASE 1KONDHAVE DHAVADE HAVELI PUNE165CompletedJan 2014Late, Jul 2014

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep CAVANSITE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near WARJE13,700+ in Pune

2 kmCAVANSITECompleted 38Lapsed / revoked 21Other 48Dot size: filed unitsN

Filed coordinates, straight-line distance. 107 registered projects within 2 km.

Builder: S2 REALTY

S2 REALTY has 7 registrations on MahaRERA, including CAVANSITE and URBANGRAM CHAKAN PHASE III. Its filings disclose 7 earlier MahaRERA projects: declares 0 of 7 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that CAVANSITE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if CAVANSITE is delayed beyond 31 Jul 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of CAVANSITE?

The registered promoter entity is S2 REALTY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in CAVANSITE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against CAVANSITE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for CAVANSITE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at CAVANSITE?

The professionals named in the filing: Architect: JAY AERAM; Engineer: SPECTRUM CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in CAVANSITE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About CAVANSITE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save CAVANSITE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.